1Computer system validation plan template, section by section.
No US regulation uses the words “validation plan” for a computer system. The duty behind one is in 21 CFR 211.68(b), which requires appropriate controls over computer systems and checks of their input and output, and, for electronic records, 21 CFR 11.10(a), which requires “Validation of systems to ensure accuracy, reliability, consistent intended performance, and the ability to discern invalid or altered records.”1,
| Section | What it commits to | Basis |
|---|---|---|
| Scope and intended use | System, version, records, GxP decisions; what is out | Guidance: WHO App. 5, 3.3; Guidance (devices): FDA CSA V.A(1) |
| System description | Components, interfaces, data flows, hosting, security | Guidance: Annex 11, 4.3 |
| Roles and sign-offs | Who does, reviews and approves each deliverable | Guidance: FDA PV IV.C.1; Annex 11, 2 |
| Risk approach | Method, when it runs, how it sets depth | Guidance: Annex 11, 1; Guidance (devices): FDA CSA V.A(2) |
| Suppliers and hosting | Assessment, audit decision, written agreement | Guidance: Annex 11, 3.1 to 3.3 and 4.5 |
| Specifications | User requirements; configuration and design specifications | Guidance: Annex 11, 4.4; WHO App. 5, 6 |
| Deliverables | Each document and its owner, or why it is not needed | Guidance: Annex 11, 4.1 |
| Testing | Method for each risk level; environments; testers | Guidance (devices): FDA CSA V.A(4); Guidance: Annex 11, 4.7 |
| Electronic records and signatures | The Part 11 controls the tests must show | Rule: 21 CFR 11.10 |
| Data migration | How moved data are checked, if any move | Guidance: Annex 11, 4.8 |
| Traceability | Requirement to risk, test and result | Guidance: Annex 11, 4.4 |
| Acceptance criteria | What the report will judge results against | Guidance: FDA PV IV.C.1; WHO App. 5, 3.3 |
| Deviations and plan changes | How failures and changes are recorded | Guidance: Annex 11, 4.2; Annex 15, 2.7 |
| Procedures and training | SOPs and training in place before release | Guidance: WHO App. 5, 11.1; Rule: 21 CFR 11.10(i) |
| Report and release | Who approves; whether conditional release is allowed | Guidance: WHO App. 5, 3.1; Draft guidance: Annex 11 (2025), 9.8 |
| After release | Change control and the first periodic review | Guidance: Annex 11, 10 and 11 |
The full list of life-cycle steps, with who usually owns each deliverable, is on the computer system validation page. The plan doesn’t repeat that list. It decides which steps this system needs, how deep each goes and why, and it names a document number, an owner and a date for each, so the summary report can close every line.
Three habits keep a plan usable:
- Say what is out. List the functions the system has but nobody relies on for a GxP decision, with the reason. FDA’s Part 11 guidance makes the point for whole systems: “validation would not be important for a word processor used only to generate SOPs.”10
- Check a supplier’s protocols before you adopt them. Annex 15 asks that “appropriate personnel at the manufacturing site should confirm suitability and compliance with internal procedures before approval.”9
- Write the acceptance criteria now. FDA wants the report’s conclusions to “address criteria in the plan”, so criteria written after testing judge nothing.4
2How the plan differs from the validation master plan.
The validation master plan (VMP) is the site’s: its policy, organization, systems and their status, and its strategy.9 The validation plan is one system’s: it applies that strategy to this system’s risks, components and suppliers. PIC/S puts it this way: “The scope or extent of validation for each system can be detailed in individual validation plans.”11 Annex 15 adds that for large and complex projects “separate validation plans may enhance clarity”.9
FDA’s software validation guidance for devices draws the other line, between the plan and the procedure: the plan defines “what” is to be accomplished, and procedures establish “how”.12 A site’s CSV SOP says how any system is validated; the plan says what is done for this one. Protocols and test scripts sit under the plan, and the summary report closes it. The table of all four documents is in how a VMP differs from a validation plan, protocol and report.
As practice, ISPE’s GAMP 5 Second Edition (July 2022) gives validation planning its own appendix, M1, and validation reporting another, M7.13
3Deciding what the plan commits to.
Two things set the depth of the plan: what each component is, and what each function’s failure could do.
First, is the system in scope? FDA’s Part 11 guidance recommends basing the approach to validation “on a justified and documented risk assessment and a determination of the potential of the system to affect product quality and safety, and record integrity.”10 If the answer is no, the signed assessment is the record, and no plan follows. How to make that call is on what GxP means.
Second, what is each component? Categorize components, not the whole system, as GAMP 5 software categories explains. Annex 11 separates the two halves: “The application should be validated; IT infrastructure should be qualified.”5 Off-the-shelf documentation is to be “reviewed by regulated users to check that user requirements are fulfilled.”5 What you configure needs a configuration specification, and code written for you needs a design specification, code review and developer testing.6
Third, how much harm could each function do? FDA’s Computer Software Assurance (CSA) guidance asks for assurance in proportion to whether a failure would be a high process risk.7 Its current version, final, is dated 3 February 2026 and replaced the version of 24 September 2025.14 It is written for medical device production and quality system software. For drugs, FDA says “The extent of validation studies should be commensurate with the risk posed by the automated system.”3 The four test methods in the diagram are the ones risk-based validation maps to CSA; mapping grades onto them is a site choice.
Every GxP plan then lists the same core: requirements, the risk assessment, traceability, procedures and training, and the report and release. Where the system holds electronic records under Part 11, the plan also lists the Part 11 controls the tests must show.6,
4How it runs in Seal.
In Seal’s computer system validation blueprint, you begin by stating the system’s intended use: the regulated decisions it supports, who uses it and where, the records it creates and the limits beyond which it is not relied upon. Those statements are versioned and approved. Risk is then assessed at the level of functions, and the assurance for each, from supplier evidence and automated checks to scripted, limited scripted and exploratory testing, follows from its risk.
Release-by-release evidence stays connected without rewriting the validation plan each time. Each supplier release is a change control in its own changeset, and the changeset cannot publish until its Check passes, which needs every approved test case to have a finished, passing run on the version being released, and until every sign-off is given.
5Example: Exampla’s validation plan for ExamMES 2.
Invented for illustration. Exampla Pharma Services LLC, a contract manufacturer and testing laboratory in Durham, North Carolina, moved its vial-filling batch records from paper to ExamMES 2, a vendor-hosted software as a service (SaaS) system. The production manager is the system owner. QA’s computer systems lead approved version 1 of plan QA-VP-001 on 3 February 2025, 119 days before the 2 June 2025 go-live. It set the scope, the components, the risk method, the testing method for each grade, the acceptance criteria, the schedule and the release rule. Version 2, approved on 4 April 2025 with the specifications and before any testing, added the counts below. In the diagram, ExamMES 2 takes the red path.
| Component | Category | The plan commits to |
|---|---|---|
| Vendor’s hosting | 1, infrastructure | Audit on 18 February 2025; quality agreement |
| ExamMES 2 release 2.3, with 3 master batch records | 4, configured | Configuration specification; tests of each record |
| Interface sending sample requests to ExamLIMS | 5, custom | Design specification, vendor code review, interface test |
The plan also says what is out, which Part 11 controls the tests must show, and what happens to the paper records:
- Out of scope. ExamMES 2’s shift-planning board and its equipment efficiency dashboard, which nobody uses to record, review or release a batch. Where one system has both CGMP and non-CGMP functions, FDA says “the potential for non-CGMP functions to affect CGMP operations should be assessed and mitigated appropriately”, so the plan records why neither can change a batch record.3
- Part 11 controls. Access limited to named accounts; authority checks, so the user who does a step cannot also check it; a time-stamped audit trail of every entry and change; step order enforced by the master record; and complete copies for inspection. Each is a high-risk requirement with its own test cases.2
- The paper records. Nothing is migrated. The 3 approved paper master batch records were rebuilt in ExamMES 2, and each was checked line by line against its paper master before its simulated batch. Batches started on paper finish on paper and stay in the paper archive.
Version 2 records the user requirements specification, approved on 24 February 2025: 84 requirements, each rated by what its failure could do to the batch, the patient or the record.
| Risk | Requirements | Planned testing |
|---|---|---|
| High | 26 | 38 scripted cases, 3 of them the simulated batches |
| Medium | 35 | 21 scripted cases, 5 unscripted sessions |
| Low | 23 | 2 exploratory sessions |
| Total | 84 | 59 scripted cases, 7 sessions |
FDA’s answer on master batch records drives the PQ: qualifying the platform is not enough, and “validating the workflow ensures that the intended steps, requirements, and calculations in the MPCR are accurate and perform properly.”3 So the plan commits to one simulated batch through each of the 3 master batch records, run as scripted cases PQ-01 to PQ-03, with every calculation checked by hand.
| Deliverable | Date | Owner |
|---|---|---|
| Requirements approved | 24 February 2025 | System owner, QA |
| Specifications and plan version 2 approved | 4 April 2025 | System owner, vendor, QA |
| Installation check of the tenant | 7 April 2025 | IT infrastructure manager |
| 56 scripted OQ cases and 7 unscripted sessions | 9 to 25 April 2025 | Validation testers |
| 3 simulated batches, PQ-01 to PQ-03 | 12 to 16 May 2025 | Production, QA |
| Training of users | Before go-live | System owner |
| Summary report QA-VSR-001 | Before go-live | QA |
The acceptance criteria are written into version 1: every high and medium requirement traced to a passing test case or unscripted session, each failure closed by a deviation with its root cause, and the 3 simulated batches matching the hand calculations. The plan allows a release with open items only where QA documents that an item cannot affect product quality, patient safety or data integrity, and an interim control covers it. That rule is Exampla’s own. The draft Annex 11, published in July 2025, after this plan, proposes the same documented assessment for taking a system into use, though not the interim control.8 Annex 15 allows conditional approval only to move to the next qualification stage.9 The first periodic review covers 2 June 2025 to 1 June 2026.
6Who writes, reviews and approves the plan.
In the US, FDA’s process validation guidance says of qualifying utilities and equipment: “The quality control unit must review and approve the qualification plan and report (§ 211.22).”4 The rule it cites gives the quality control unit, called QA on this page, “the responsibility for approving or rejecting all procedures or specifications impacting on the identity, strength, quality, and purity of the drug product.”17 In the EU, Annex 15 asks that validation documents be “approved and authorised by appropriate personnel as defined in the pharmaceutical quality system”,9 and Annex 11 names the people who should work together: “Process Owner, System Owner, Qualified Persons and IT.”5
| Role | Does | Signs |
|---|---|---|
| System owner | Writes the plan; owns requirements | Prepared by |
| IT, or the SaaS vendor’s contact | Checks hosting and interfaces | Reviewed by |
| QA | Checks risk, criteria and release rule | Approved by, before testing |
PIC/S, in a table it takes from GAMP 4, lists the plan among the user’s duties, not the supplier’s: “The Validation Plan should define the activities, procedures, and responsibilities for establishing the adequacy of the system.”11 A vendor can draft it, but the draft Annex 11 is plain that the regulated user “is fully accountable and should carefully review and authorise the use of the documentation.”8
7When the plan changes.
Before approval, change anything. After approval, Annex 15 asks that “Any significant changes to the approved protocol during execution, e.g. acceptance criteria, operating parameters etc., should be documented as a deviation and be scientifically justified.”9 Annex 11 wants those deviation reports kept with the validation documents.5 A plan revised under document control, before the affected work starts, is the cleaner route when scope grows.
After go-live the plan stops growing. Each new version of the software, each configuration change and each new intended use goes through change control, which decides what to retest from what moved. For a SaaS system that matters most: the supplier sets the release cadence, and validating SaaS covers the agreement and the vendor’s evidence. The plan’s last section names the procedure that will do this, and the date of the first periodic review.
Keep the plan short. CSA says “Documentation of assurance activities need not include more evidence than necessary to show that the software feature, function, or operation performs as intended for the risk identified.”7 How CSA changed the paperwork, and what it did not change, is in CSV vs CSA.
AQuestions and answers
Can one validation plan cover several computer systems?
Yes, where they are validated as one project, such as a batch record system and its interface to the LIMS. Annex 15 allows separate plans for large projects, and PIC/S describes a hierarchy of linked plans. Each system still needs its own risk assessment, deliverables and release, so a reader can see what was done for each one.
Does a SaaS system need its own validation plan?
Yes, if it holds GxP records or supports a GxP decision. The vendor runs the infrastructure, but you validate your intended use and your configuration. The plan adds a supplier assessment, a decision on whether to audit, and a written agreement that sets out the vendor’s responsibilities, as Annex 11 section 3 expects.
Does the validation plan have to be approved before testing starts?
Yes. FDA’s process validation guidance says QA, as the quality control unit, must review and approve a qualification plan, WHO wants a system validated according to an approved protocol, and the draft Annex 11 wants the work done to approved plans, protocols and test scripts. Approve the plan before the testing it governs starts.
Can the software supplier write our validation plan?
A supplier can draft it, and many offer packages. Annex 15 asks the site to confirm a supplier’s protocols suit its own procedures before approval, and the regulated company stays accountable for the result. Check that the supplier’s plan covers your intended use and configuration, not only the product as shipped.
References17 sources
References
- 121 CFR 211.68, Automatic, mechanical, and electronic equipment, paragraph (b), eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ section- 211. 68 (read 26 November 2026) - 221 CFR 11.10, Controls for closed systems, paragraphs (a), (b), (d) to (g) and (i), eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ section- 11. 10 (read 26 November 2026) - 3Data Integrity and Compliance With Drug CGMP: Questions and Answers, Guidance for Industry, question 3, FDA, December 2018. https:/
/ www. fda. gov/ media/ 119267/ download (read 26 November 2026) - 4Process Validation: General Principles and Practices, Guidance for Industry, section IV.C.1, FDA, January 2011. https:/
/ www. fda. gov/ media/ 71021/ download (read 26 November 2026) - 5EudraLex Volume 4, Annex 11: Computerised Systems, revision 1, principle and sections 1 to 4, 10 and 11, European Commission, in operation from 30 June 2011. https:/
/ health. ec. europa. eu/ document/ download/ 8d305550- dd22- 4dad- 8463- 2ddb4a1345f1_ en?filename=annex11_ 01- 2011_ en. pdf (read 26 November 2026) - 6Good manufacturing practices: guidelines on validation, WHO Technical Report Series No. 1019, Annex 3, Appendix 5, Validation of computerized systems, sections 3, 6, 8.3 and 11.1, World Health Organization, 2019. https:/
/ www. who. int/ docs/ default- source/ medicines/ norms- and- standards/ guidelines/ production/ trs1019- annex3- gmp- validation. pdf (read 26 November 2026) - 7Computer Software Assurance for Production and Quality Management System Software, Guidance for Industry and FDA Staff, sections V.A(1), V.A(2), V.A(4) and V.A(6), FDA, 3 February 2026. https:/
/ www. fda. gov/ media/ 188844/ download (read 26 November 2026) - 8EudraLex Volume 4, Annex 11: Computerised Systems, draft for consultation, sections 9.7 to 9.9, European Commission and PIC/S, July 2025. https:/
/ health. ec. europa. eu/ document/ download/ 40231f18- e564- 4043- 94de- c031f813d38b_ en?filename=mp_ vol4_ chap4_ annex11_ consultation_ guideline_ en. pdf (read 26 November 2026) - 9EudraLex Volume 4, Annex 15: Qualification and Validation, sections 1.4 to 1.6, 2.2, 2.6, 2.7 and 2.10, European Commission, in operation from 1 October 2015. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ 2015- 10_ annex15_ 0. pdf (read 26 November 2026) - 10Guidance for Industry: Part 11, Electronic Records; Electronic Signatures, Scope and Application, section III.C.1, FDA, August 2003. https:/
/ www. fda. gov/ media/ 75414/ download (read 26 November 2026) - 11PI 011-3, Good Practices for Computerised Systems in Regulated GxP Environments, section 7.3, footnote 25 and table 6, PIC/S, 25 September 2007. https:/
/ picscheme. org/ docview/ 3444 (read 26 November 2026) - 12General Principles of Software Validation, Final Guidance for Industry and FDA Staff, sections 4.5 and 4.6, FDA, January 2002. https:/
/ www. fda. gov/ media/ 73141/ download (read 26 November 2026) - 13ISPE GAMP 5 Guide: A Risk-Based Approach to Compliant GxP Computerized Systems, Second Edition, table of contents, appendices M1 and M7, ISPE, July 2022. https:/
/ ispe. org/ sites/ default/ files/ publications/ guidance- documents/ 2022- TOC/ ISPE- GAMP5- Ed2_ TOC. pdf (read 26 November 2026) - 14Computer Software Assurance for Production and Quality Management System Software, guidance document page, status final, FDA. https:/
/ www. fda. gov/ regulatory- information/ search- fda- guidance- documents/ computer- software- assurance- production- and- quality- management- system- software (read 26 November 2026) - 15EudraLex Volume 4, Good Manufacturing Practice guidelines, listing Annex 11 “Computerised Systems (revision January 2011)”, European Commission. https:/
/ health. ec. europa. eu/ medicinal- products/ eudralex/ eudralex- volume- 4_ en (read 26 November 2026) - 16Publications: Drafts, listing “Draft guidelines: Revised Annex 11 - Computerised systems”, PIC/S. https:/
/ picscheme. org/ en/ publications?tri=draft (read 26 November 2026) - 1721 CFR 211.22, Responsibilities of quality control unit, paragraph (c), eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ section- 211. 22 (read 26 November 2026)