1IQ, OQ and PQ at a glance.
Qualification is documented evidence that facilities, utilities, equipment and systems “are suitable for their intended use”.1 EU GMP Annex 15 sets out the stages and defines each, and the PIC/S GMP Guide carries the same annex:2,
- Installation qualification (IQ). “The documented verification that the facilities, systems and equipment, as installed or modified, comply with the approved design and the manufacturer’s recommendations.”
- Operational qualification (OQ). “The documented verification that the facilities, systems and equipment, as installed or modified, perform as intended throughout the anticipated operating ranges.”
- Performance qualification (PQ). “The documented verification that systems and equipment can perform effectively and reproducibly based on the approved process method and product specification.”
- Installation and operational qualification (IOQ). IQ and OQ performed as one stage, which Annex 15 allows “depending on the complexity of the equipment”, with their documents combined.2
Before IQ come the user requirements specification (URS), the point of reference throughout, and design qualification (DQ), which checks the design against the URS and GMP; factory and site acceptance tests (FAT, SAT) may follow.2
| Stage | Proves | Typical checks | When | Produces |
|---|---|---|---|---|
| IQ | Installed as designed and as its maker recommends | Drawings, materials, calibration, supplier manuals | After DQ and any FAT or SAT | Report; release to OQ |
| OQ | Works as designed across its operating ranges | Functions, alarms, limits, worst case | After IQ, or combined as an IOQ | Report; SOPs and training finalized |
| PQ | Performs reproducibly in normal use | Production or equivalent material, worst-case batch size | After OQ, or with OQ or process validation | Report; release for routine use |
After PQ, the equipment is reviewed at a justified frequency to confirm it stays qualified.2,
2IQ, OQ and PQ protocols: template and test scripts.
Annex 15 and PIC/S prescribe no form.2,
2.1Protocol skeleton.
| Section | What it holds | Source |
|---|---|---|
| Approval page | Document number and version; relevant functions and the quality unit sign before execution | WHO 8.2, 8.4;3 PI 006-4 4.1.61 |
| Scope | Stages covered, set by a documented risk assessment, with the reason for any stage left out | Annex 15, General;2 WHO 4.64 |
| System description | Identity, location, current drawings, and the URS and DQ each test traces to | PI 006-4 4.1.4(b), 4.3.1.5(a)1 |
| Responsibilities | Who executes, reviews and approves | WHO 8.23 |
| Prerequisites | Earlier stage released, or conditionally; test instruments calibrated; draft SOPs; trained executors | Annex 15 2.10;2 PI 006-4 4.3.2.3;1 WHO 8.53 |
| Test cases | Scripts traced to the requirements they verify, acceptance criteria fixed in advance | Annex 15 2.4;2 PI 006-4 4.1.4(b), 4.3.2.51 |
| Deviation log | Failures and protocol changes, each investigated and visible in the site deviation system | Annex 15 2.7, 2.8;2 PI 006-4 3.4.3(l)1 |
| Summary and release | Results against criteria, raw data, deviations, conclusion; data integrity confirmed by a non-executor; formal release | Annex 15 2.9, 2.10;2 PI 006-4 3.4.3(m);1 WHO 4.94 |
2.2Test script format.
Two filled scripts from the cold room example below:
| Field | OQ-05 high alarm | OQ-14 unit B mapping |
|---|---|---|
| Requirement | URS-07: alarm before 8.0 °C | URS-03: 2.0 to 8.0 °C on either unit alone |
| Method | Warm the control probe in a calibrated dry-block | Unit B alone, empty, 24 hours, 15 loggers |
| Acceptance criterion | Local alarm sounds and is logged at 7.5 °C or below | Every reading 2.0 to 8.0 °C |
| Expected result | Alarm at 7.5 °C | All loggers in range |
| Actual result | Alarm at 7.5 °C, logged at 10:42 | 1.7 °C at the rear high position |
| Pass or fail | Pass | Fail |
| Executed by, date | Validation engineer AK, 11 Feb 2026 | Validation engineer AK, 15 Feb 2026 |
| Verified by, date | QA reviewer MS, 12 Feb 2026 | QA reviewer MS, 16 Feb 2026 |
| Deviation | None | DEV-26-0219; retest OQ-14R passed |
The fields answer Annex 15 2.4 and 2.8, PI 006-4 4.1.6 and 3.4.3(m), and WHO’s rule that expected and actual results are compared.2,
2.3IQ lines.
| Item | What to show | Source |
|---|---|---|
| Documents | Approved drawings, P&IDs and specifications, current; field changes explained and drawn | PI 006-4 4.3.1.2, 4.3.1.5(a)1 |
| Installation | Components, instruments, pipework and utilities as drawn | Annex 15 3.9(i)2 |
| Supplier documents | Supplier drawings and manuals for operation, maintenance and cleaning collected; required procedures available, drafts allowed | Annex 15 3.9(iii);2 PI 006-4 4.3.1.5(c), (f)1 |
| Materials | Materials of construction meet the URS | Annex 15 3.9(v);2 PI 006-4 4.3.1.5(d)1 |
| Calibration | Instruments listed with ranges and calibrated, traceable to national or international standards | Annex 15 3.9(iv);2 PI 006-4 4.3.1.3;1 WHO 8.44 |
2.4OQ lines.
| Item | What to show | Source |
|---|---|---|
| Function and limits | Tests built from process knowledge, at upper and lower limits or worst case | Annex 15 3.112 |
| Controls | Alarms and other controls shown to work | WHO 4.24 |
| Load | Challenged “under load comparable to that expected during routine production”; FDA names no stage, and the example does it in PQ | FDA 20115 |
| Data and access | User roles, audit trail, sensor-failure alarm, backup and restore | PI 006-4 4.3.1.4;1 Annex 11 4.7, 7.2, 9, 12.16 |
| SOPs | Testing follows the draft SOP, final before the OQ report is approved | PI 006-4 4.3.2.4;1 Annex 15 3.122 |
2.5PQ lines.
| Item | What to show | Source |
|---|---|---|
| Material | Production material, qualified substitute or simulated product proven to behave equivalently | Annex 15 3.14(i)2 |
| Conditions | Normal operation with worst-case batch size, across the intended range unless development data confirm it | Annex 15 3.142 |
| Period | Covers normal events such as stoppages, staff changes, door openings and seasons, with the rationale recorded | PI 006-4 4.3.3.31 |
| Sampling | More than routine checks, frequency justified: hourly routine checks may mean 15-minute PQ sampling | Annex 15 3.14(i);2 PI 006-4 4.3.3.41 |
3Example: qualifying a 2 to 8 °C cold room.
This record is invented for illustration. It follows the template above and WHO’s temperature-mapping supplement.7
| Field | Entry |
|---|---|
| Equipment | Walk-in cold room CR-04, 18 m³ (3.0 × 2.5 × 2.4 m), for vials of an aqueous product at 2.0 to 8.0 °C. Duty and standby units; independent monitoring probe. |
| Scope | Direct product impact, so URS, DQ, IQ, OQ and PQ under change control CC-26-0207. |
| Criteria, 6 Feb 2026 | Approved with the protocol: every logger 2.0 to 8.0 °C, except up to 30 minutes after a defined door opening; alarms at 7.5 and 2.5 °C; standby running within 5 minutes of a duty unit failure. |
| Logger grid | 15 loggers at four corners and the center, each at 0.3, 1.2 and 2.1 m, reading every 5 minutes; 3-point calibration within ±0.5 °C. |
| IQ, 9 to 10 Feb | 36 checks passed. A drain moved 0.4 m on site was added to the drawing, approved under the change control. |
| OQ controls, 11 Feb | Alarms at 7.5 and 2.5 °C; standby running 2 minutes after a duty unit failure. |
| OQ data, 11 Feb | Operators could not change set points; an administrator’s change was audit-trailed with user, time and reason. A disconnected probe alarmed within a minute; a restored backup matched. |
| OQ power cut | 60 minutes with the door shut peaked at 6.9 °C. The controller restarted with its set points and logged the event. |
| OQ mapping, 12 to 17 Feb | 24 hours empty on each unit, 288 readings per logger. Unit A: 3.4 to 6.6 °C. |
| Deviation DEV-26-0219 | Unit B read 1.7 °C at the rear high position: its air deflector was on backwards. Refitted; a 24-hour re-map read 3.2 to 6.7 °C. |
| Release to PQ, 18 Feb | Conditional: remote alerts awaited a network change, with no significant impact since PQ is staffed and the local alarm works. Closed in PQ: alerts reached the on-call phone in 3 minutes. |
| PQ, 23 to 26 Feb | Maximum URS load: 480 cartons of water-filled vials in the product’s own vial, fill volume and carton. 72 hours, 36 on each unit, 864 readings per logger. |
| PQ door openings | 48 of up to 2 minutes and one of 10 minutes. All loggers stayed within 2.0 to 8.0 °C except the high door logger. |
| PQ excursion | 8.6 °C after the 10-minute opening, back under 8.0 °C in 14 minutes: inside the 30-minute allowance. |
| PQ cold spot | Low at the rear, mean 3.4 °C. |
| Season | Mapped once, in February: WHO says two-season mapping is typically not necessary for cold rooms. |
| Outcomes | Monitoring probe moved to the warmest position, by the door. The top door-side shelf, where 8.6 °C was seen, marked as a no-storage zone. |
| Release, 6 Mar 2026 | QA approved the report and released CR-04 for routine use, 25 days after IQ began. |
The settings follow WHO: loggers at three heights in rooms up to 3.6 m, readings every 1 to 15 minutes, 24 to 72 hours for a cold room, each unit mapped alone, 30 minutes to recover from a door opening, the monitoring sensor at the hot or cold spot, and no-storage zones.7 Water-filled vials count only as simulated product proven to behave equivalently, here an aqueous fill in the same pack.2
4How it runs in Seal.
In Seal’s commissioning and qualification blueprint, CR-04’s requirements, such as URS-03, link to their risks, tests, exceptions and turnover decision, so coverage is calculated from the links and shows any requirement left untested. Executors scan the instruments they use and record actual values as they test. OQ-14’s 1.7 °C reading becomes an exception on URS-03, and the re-map adds new evidence without overwriting it. Protocol completion distinguishes accepted, accepted with justified open items, failed, aborted and superseded, so a conditional release stays visible, and Seal shows the evidence still preventing release.
Because instrument eligibility is recorded against each execution, a logger that later fails calibration identifies the tests recorded as using it and opens an impact assessment. After release, the qualified baseline is the reference for change control and periodic review, and in equipment management a missing qualification or calibration prerequisite is flagged at the step that selects the asset.
5Who does what.
The VMP names who is responsible for protocols, testing, reports and approvals;1 this split is one way to do it.
| Role | Does | Source |
|---|---|---|
| Vendor or engineering | FAT, SAT and vendor protocols; may execute stages under a written agreement, the contract giver staying responsible | Annex 15 2.6;2 WHO 4.134 |
| Validation | Writes protocols, executes or supervises, compiles the report | PI 006-4 3.4.3(b), 4.3.1.11 |
| System owner | URS, SOPs (final before OQ approval), training and maintenance | PI 006-4 4.1.4(g), 4.3.2.41 |
| Quality unit | Approves protocols, criteria and reports | PI 006-4 4.1.6;1 FDA 20115 |
| Independent reviewer | Confirms data integrity in the report; did not execute the work | PI 006-4 3.4.3(m)1 |
| CDMO client | Reviews or approves as the quality agreement sets out, with access to the records | EU GMP Chapter 7, 7.4, 7.15, 7.168 |
See quality agreements.
6Judgment calls: what the rules allow.
| Situation | What to do | Rule |
|---|---|---|
| Simple, low-risk item | Scale the depth down and record why: an autoclave needs more than a leaflet inserter. | PI 006-4 4.1.5;1 Annex 15, General2 |
| Vendor FAT or SAT | Reuse tests that transport and installation cannot affect; site staff confirm vendor protocols first. | Annex 15 2.6, 3.6;2 PI 006-4 4.1.71 |
| ASTM E2500-type C&Q | Other approaches and terminology can apply in appropriate circumstances if they show fitness for purpose; trace verification to the URS. | PI 006-4 4.1.1;1 Annex 15 3.2;2 ASTM E2500-259 |
| Purified water PQ | Normally a full year: about 1 to 4 weeks of intensive testing, 4 to 12 weeks reduced, then 4 to 12 months extended. | PI 006-4 6.3.61 |
| Moved or modified | Change control assesses the impact on validation, calibration and maintenance and plans requalification. | Annex 15 11.42 |
| A test fails | Deviation, cause, fix, retest; accepting a failed result needs a scientific justification. | Annex 15 2.8, 2.9;2 WHO 9.5;3 Fareva letter10 |
| In use, never qualified | A protocol verifying URS, design, operation and performance elements, and a report. | WHO 11.74 |
For cleanroom requalification and sterilization loads, see EU GMP Annex 1 and cleanroom grades.
7Equipment PQ, process PQ and the rules compared.
Equipment PQ qualifies one item, utility or system in normal use.2 In FDA’s 2011 guidance, “PQ” is process qualification, Stage 2 of process validation: equipment and utility qualification, then process performance qualification (PPQ) of commercial batches.5 See the three stages of process validation.
| Topic | FDA | EU GMP and PIC/S |
|---|---|---|
| Status | 21 CFR 211.63 and 211.68 are law; the 2011 guidance is not binding, but notes that process validation, Stage 2 qualification included, is legally enforceable11, | Annex 15 is guidance on the GMP principles; PI 006-4 guides inspectors and industry2, |
| The terms | Part 211 uses “qualif” words only of people; the 2011 guidance describes the checks without naming IQ or OQ11, | Annex 15 defines DQ, IQ, OQ and PQ2 |
Section 211.63 requires equipment “of appropriate design, adequate size, and suitably located”; 211.68(a) requires routine calibration, inspection or checks of automatic, mechanical and electronic equipment under a written program.11
Three scopes differ. For active substances, ICH Q7 12.30, carried in EU GMP Part II and FDA’s Q7 guidance, expects critical equipment qualified before process validation, usually by DQ, IQ, OQ and PQ, alone or combined; Annex 15 is only optional guidance for them.12,
Device makers use the same words for processes. The QMSR requires a quality system meeting ISO 13485:2016, and FDA’s device inspection program maps process validation to its clause 7.5.6.17,
8What inspectors cite.
FDA’s drug inspection program names “Equipment installation and operational qualification where appropriate” under the facilities and equipment system, and lists “Pattern of failure to qualify equipment, including computers” among the problems that can lead to regulatory action.20 Two 2026 letters to drug manufacturers show the failures:
“The performance qualification report for your (b)(4) included over (b)(4) of (b)(4)-sampling data, showing that most samples failed USP (b)(4) standards. Despite obtaining failing data, you approved the qualification study in (b)(4).” Fareva Morton Grove, warning letter, 3 March 202610
“Your firm modified your (b)(4) system (number (b)(4)) in October 2024 by adding a production point of use in the (b)(4) area and replacing the (b)(4) tank with a (b)(4) tank without adequate requalification.” Island Kinetics, Inc. d.b.a. CoValence Laboratories, warning letter, 16 July 202621
Before an inspection, have ready:
- The list of qualified items with status and requalification due dates.4,
1 - For each critical item, the URS, protocols, reports, deviations and release decisions.1
- Periodic reviews and change controls since qualification, including approved like-for-like decisions.1
9What changed in 2024 to 2026, and what is still proposed.
- PIC/S PI 006-4 entered into force on 1 October 2026, replacing PI 006-3 of 25 September 2007.1
- EMA’s concept paper of 19 January 2026, consulted on until 9 April 2026, would make Annex 15 apply to active substance manufacturers. Its timetable, revised in July 2026, plans a draft for consultation in December 2026 and publication in April 2028.22
AQuestions and answers
How long do IQ, OQ and PQ take?
It depends on the system and on how long PQ must run to see normal events. The cold room example above took 25 days from the start of IQ to release. WHO suggests 24 to 72 hours of temperature mapping for a cold room and at least seven consecutive days for an ambient warehouse. A purified water system takes longest: PIC/S says its PQ should normally run for a full year, so that seasonal changes in the feed water are seen.
How many PQ runs does equipment qualification need?
Neither Annex 15 nor PIC/S PI 006-4 sets a number of runs for equipment PQ. PI 006-4 asks for a period long enough to cover normal events, such as adjustments, stoppages, personnel changes and seasons, with the rationale documented. The familiar three comes from process validation, where Annex 15 says a minimum of three consecutive batches is generally acceptable, and both Annex 15 and PI 006-4 ask for the number to be justified.
Is design qualification (DQ) required?
Annex 15 makes DQ the next element after the URS: a documented check that the design complies with GMP and meets the user requirements. PIC/S calls it a documentation verification process, and some sites write a separate design specification showing how the design meets each requirement. Its depth, like every stage’s, is set by a documented risk assessment, and WHO asks for a justification wherever a stage is left out.
Is commissioning the same as qualification?
No. WHO lists design, engineering, commissioning and qualification as separate phases that each compile evidence; qualification is the documented evidence, approved by the quality unit, that the item is suitable for its intended use. Commissioning, FAT and SAT tests can count toward IQ or OQ where that is justified, where site staff confirmed any vendor protocol before approval, and where transport and installation cannot affect what was tested.
Can one protocol cover several identical units?
Often, with a strategy based on risk. The EU ATMP guidelines accept a testing strategy across several identical pieces of equipment based on an evaluation of the risks. That evaluation, recorded, decides which tests each unit repeats; Annex 15 likewise sets the scope of qualification by a documented risk assessment.
References22 sources
References
- 1PI 006-4, Recommendations on Qualification and Validation, PIC/S, 1 October 2026, sections 2.3, 3.4.3, 4 and 6.3. https:/
/ picscheme. org/ docview/ 11277 (read 25 November 2026) - 2EudraLex Volume 4, Annex 15: Qualification and Validation, European Commission, 30 March 2015, in operation since 1 October 2015, Principle, General, sections 2, 3, 4, 5.19, 5.20 and 11 and the glossary (section 12). https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ 2015- 10_ annex15_ 0. pdf (read 25 November 2026) - 3Good manufacturing practices: guidelines on validation, WHO Technical Report Series No. 1019, Annex 3, sections 8 and 9 and Appendix 5 section 8.7, World Health Organization, 2019. https:/
/ www. who. int/ docs/ default- source/ medicines/ norms- and- standards/ guidelines/ production/ trs1019- annex3- gmp- validation. pdf (read 25 November 2026) - 4WHO Technical Report Series No. 1019, Annex 3, Good manufacturing practices: guidelines on validation, Appendix 6, Guidelines on qualification, World Health Organization, 2019. https:/
/ www. who. int/ docs/ default- source/ medicines/ norms- and- standards/ guidelines/ production/ trs1019- annex3- gmp- validation. pdf (read 25 November 2026) - 5Process Validation: General Principles and Practices, Guidance for Industry, Revision 1, FDA, January 2011, section IV.C.1 and footnote 7. https:/
/ www. fda. gov/ media/ 71021/ download (read 25 November 2026) - 6EudraLex Volume 4, Annex 11: Computerised Systems, European Commission, revision January 2011, in operation since 30 June 2011, sections 4.7, 7.2, 9 and 12.1. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ annex11_ 01- 2011_ en_ 0. pdf (read 25 November 2026) - 7Temperature mapping of storage areas, Supplement 8 to WHO Technical Report Series No. 961, Annex 9, World Health Organization, May 2015. https:/
/ cdn. who. int/ media/ docs/ default- source/ medicines/ norms- and- standards/ guidelines/ distribution/ trs961- annex9- supp8. pdf (read 25 November 2026) - 8EudraLex Volume 4, Chapter 7: Outsourced Activities, European Commission, in operation since 31 January 2013. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ vol4- chap7_ 2012- 06_ en_ 0. pdf (read 25 November 2026) - 9ASTM E2500-25, Standard Guide for Specification, Design, and Verification of Pharmaceutical and Biopharmaceutical Manufacturing Systems and Equipment: Science and Risk Based Approach, ASTM International, standard page, sections 1 and 5. https:/
/ store. astm. org/ e2500- 25. html (read 25 November 2026) - 10Warning letter 320-26-48 to Fareva Morton Grove, FDA, 3 March 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ fareva- morton- grove- 719408- 03032026 (read 25 November 2026) - 1121 CFR Part 211, Current Good Manufacturing Practice for Finished Pharmaceuticals, eCFR, as of 23 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211 (read 25 November 2026) - 12ICH Q7, Good Manufacturing Practice Guide for Active Pharmaceutical Ingredients, section 12.30, ICH, 10 November 2000. https:/
/ database. ich. org/ sites/ default/ files/ Q7%20Guideline. pdf (read 25 November 2026) - 13EudraLex Volume 4, Part II: Basic Requirements for Active Substances used as Starting Materials, section 12.30, European Commission, 13 August 2014. https:/
/ health. ec. europa. eu/ document/ download/ bd537ccf- 9271- 4230- bca1- 2d8cb655fd83_ en?filename=2014- 08_ gmp_ part1. pdf (read 25 November 2026) - 14Q7 Good Manufacturing Practice Guidance for Active Pharmaceutical Ingredients, Guidance for Industry, Revision 1, FDA, September 2016, section 12.30. https:/
/ www. fda. gov/ media/ 71518/ download (read 25 November 2026) - 15Guidelines on Good Manufacturing Practice specific to Advanced Therapy Medicinal Products, EudraLex Volume 4, Part IV, European Commission, 22 November 2017. https:/
/ health. ec. europa. eu/ system/ files/ 2017- 11/ 2017_ 11_ 22_ guidelines_ gmp_ for_ atmps_ 0. pdf (read 25 November 2026) - 16The Human Medicines Regulations 2012, regulation C17, Guidelines on good manufacturing practice and good distribution practice, legislation.gov.uk. https:/
/ www. legislation. gov. uk/ uksi/ 2012/ 1916/ regulation/ C17 (read 25 November 2026) - 1721 CFR 820.7 and 820.10, Quality Management System Regulation, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- H/ part- 820 (read 25 November 2026) - 18Compliance Program 7382.850, Inspection of Medical Device Manufacturers, FDA, implemented 2 February 2026, Attachment A. https:/
/ www. fda. gov/ media/ 80195/ download (read 25 November 2026) - 19GHTF/
SG3/ N99- 10:2004 (Edition 2), Quality Management Systems: Process Validation Guidance, Global Harmonization Task Force, January 2004, sections 2 and 5, reproduction hosted by gmp-compliance.org (the IMDRF copy did not load on 25 November 2026). https:/ / gmp- compliance. org/ files/ guidemgr/ ghtf- sg3- n99- 10- 2004- qms- process- guidance- 04010. pdf (read 25 November 2026) - 20Compliance Program 7356.002, Drug Manufacturing Inspections, FDA, implemented 17 October 2022, Parts III and V. https:/
/ www. fda. gov/ media/ 75167/ download (read 25 November 2026) - 21Warning letter 320-26-104 to Island Kinetics, Inc. d.b.a. CoValence Laboratories, FDA, 16 July 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ island- kinetics- inc- dba- covalence- laboratories- 726379- 07162026 (read 25 November 2026) - 22Concept paper on the revision of the guidelines on Good Manufacturing Practice for medicinal products, Annex 15, Qualification and Validation, EMA/
INS/ GMP/ 163466/ 2026, EMA GMP/GDP Inspectors Working Group, 19 January 2026, with the corrigendum to its timetable published by PIC/S on 16 July 2026. https:/ / picscheme. org/ docview/ 11269 (read 25 November 2026)