What is a user requirements specification (URS), and how do you write one for a GxP system?

A user requirements specification (URS) is the approved, controlled document stating what equipment, a utility or a computerised system must do for its intended use. EU GMP Annex 15 makes it a point of reference throughout validation, and Annex 11 asks that it rest on a documented risk assessment and stay traceable through the life cycle. Write each requirement once, numbered, testable and rated for GMP impact, and keep the URS under change control.Checked against its sources on 9 November 2026. How these answers are made

Illustration of a seal resting on four bound volumes, Requirements, Configuration, Verification and Change control, with a red ribbon running through them all.

1A URS template you can copy.

These sections cover equipment and computerised systems; drop the ones that don’t apply.

Table 1. URS template, each section tied to the rule that asks for it.
SectionWhat it holdsSource
1. Purpose and scopeThe system, site and process boundary, and what is out of scopeRequirements “necessary and sufficient”, Annex 15 glossary1
2. Intended useThe GMP processes and decisions it supports, its users and its critical dataWHO 5.2;2 draft Annex 11 6.13
3. Process and data flowProcess map, data flows, interfaces with other systems and with manual stepsWHO 5.3;2 PIC/S PI 011-⁠3 9.44
4. FunctionWhat it must do: calculations, limits, alarms, error handling, ranges it acceptsFDA software validation 5.2.2;5 Annex 11 4.76
5. Data integrityRole-based access, unique users, audit trail, electronic signatures, time stamps, input checksAnnex 11 6, 9, 12 and 14;6 PIC/S PI 041-⁠1 9.37
6. Records over timeBackup and restore, archive, retention, readable exportAnnex 11 7 and 17;6 WHO 5.32
7. PerformanceCapacity, volume, response times, orderly shutdown and recovery, business continuityWHO 5.3;2 Annex 11 166
8. Equipment designSize, cleanability, product-contact materials, lubricants kept out of product, operating principles suited to the use21 CFR 211.63, 211.65 and 211.67;8 FDA process validation IV.C.19
9. Installation and upkeepFootprint, utilities and room grade; calibrated instruments, preventive maintenance and spare parts lists; operator and maintenance training21 CFR 211.63 and 211.68(a);8 Annex 15 3.9 and 3.12;1 PI 006-⁠4 4.2.2 and 4.2.310
10. Supplier and serviceDocumentation to be delivered, FAT, support, release notice, audit access, exitAnnex 11 3;6 Annex 15 3.4 and 3.5;1 draft 7.53
11. Approval and historyAuthors, reviewers including the quality unit, version and change historyAnnex 15 2.2;1 PIC/S PI 006-⁠4 4.1.6 and 4.2.110

Each requirement then gets its own line with six fields: a unique ID, one statement, its GMP impact, whether it is mandatory or optional, how it will be verified, and its source, as in the examples below.

2Example: a URS extract.

Example, invented: Velloran Biologics and Kestrane LIMS are not real. Velloran is buying Kestrane LIMS, a software-as-a-service LIMS, for QC release testing at its Site 2. Eight of its 64 requirements:

Table 2. Example: eight lines of an invented URS for a SaaS LIMS.
IDRequirementImpactPriorityVerify bySource
URS-⁠012Only users with the QC Reviewer role can approve a result. The system refuses approval by the user who entered it.HighMandatoryTestAnnex 11 12;6 21 CFR 211.194(a)(8)8
URS-⁠018The LIMS calculates assay, as % of label claim, from peak areas received from the chromatography data system, as in method QCM-⁠104. It reports one decimal place, rounding half up.HighMandatoryTest with worked valuesFDA data integrity Q311
URS-⁠019A result outside its specification is flagged at entry and cannot be approved until an investigation number is linked.HighMandatoryTestWHO 5.3;2 21 CFR 211.1928
URS-⁠021Every creation, change or deletion of a result records the user, date and time, old and new value, and reason.HighMandatoryTestAnnex 11 9;6 WHO 5.32
URS-⁠027Peak areas arrive from the chromatography data system through an interface, with no manual transcription. The LIMS holds the calculation of record.HighMandatoryTestAnnex 11 5;6 draft 10.23
URS-⁠030Results, metadata and audit trails can be restored from backup within 24 hours.HighMandatoryTestAnnex 11 7.2 and 166
URS-⁠044The supplier notifies each release at least 30 days before production, with release notes naming the functions changed.MediumMandatoryInspection of the agreementAnnex 11 3.1;6 draft 7.53
URS-⁠052A dashboard shows each analyst’s count of samples awaiting review.LowOptionalSupplier evidencePIC/S PI 011-⁠3 9.3 and 9.44

URS-⁠018 and URS-⁠027 settle where the calculation of record lives: the chromatography data system sends peak areas and the LIMS computes assay, which is what OQ-⁠12 tests. The tester gets values to compute: 99.46% must be reported as 99.5%, a truncating configuration would show 99.4%, and exactly 99.45% tests the half-up rule. URS-⁠044 is verified by inspecting the signed agreement. URS-⁠052 is low because the count decides nothing; generating a certificate of analysis would be high.

The same format works for equipment. Five lines from Velloran’s URS for IS-⁠03, an invented filling isolator:

Table 3. Example: five lines of an invented URS for a filling isolator.
IDRequirementImpactPriorityVerify bySource
EQ-⁠004Interior surfaces are smooth and crevice-free and withstand the site’s sporicidal agent.HighMandatoryInspection at FAT, repeated at IQ; supplier’s compatibility data for the agent reviewed at FAT21 CFR 211.63 and 211.67(a)8
EQ-⁠007Product-contact parts are not reactive, additive or absorptive, with a material certificate for each part.HighMandatoryDocument review at DQ; materials checked at IQ21 CFR 211.65(a);8 Annex 15 3.91
EQ-⁠012An alarm sounds when the pressure difference to the room stays below 30 Pa for over 10 seconds. Acknowledging it records user, time and reason in the audit trail.HighMandatoryTest at OQAnnex 1 4.16 and 5.2;12 draft Annex 11 8.2 to 8.53
EQ-⁠013The differential pressure sensor behind EQ-⁠012 arrives calibrated, with its certificate, and the supplier states its calibration interval and maintenance tasks.HighMandatoryCertificate and manual checked at IQAnnex 15 3.9;1 21 CFR 211.68(a)8
EQ-⁠020The supplier runs FAT before shipment against a protocol Velloran approves, witnessed by Velloran engineering and QA.MediumMandatoryInspection of the approved FAT reportAnnex 15 3.4 and 3.5;1 PI 006-⁠4 4.2.310

EQ-⁠012 gives the OQ tester boundary values: 29 Pa held for 11 seconds must alarm and for 9 seconds must not. Its 10-second delay needs a recorded reason: Annex 1 says alarm delays “should be assessed and justified within the CCS”, the contamination control strategy, and wants equipment monitoring requirements defined in the URS early and “confirmed during qualification”.12 EQ-⁠004, EQ-⁠012 and six LIMS lines are traced to their results in the traceability matrix example.

2.1Rewriting weak requirements.

FDA’s software guidance says requirements should be “expressed in terms that are measurable or objectively verifiable”.5 Four common rewrites:

  • A secure system becomes URS-⁠012 and URS-⁠021: who can approve, and what the audit trail records.
  • A Part 11 compliant system becomes one line per control, such as: a signed result shows the signer’s printed name, the date and time of signing, and its meaning, such as review or approval.13
  • Fast searches become: a search by sample ID returns within 3 seconds with 40 users logged in.
  • A named product, such as one maker’s pressure sensor, becomes the need behind it: the range and accuracy it must measure. PIC/S suggests marking which elements are essential and which flexible, so suppliers aren’t ruled out needlessly.10

3How to write a URS, step by step.

  1. Map the process first. Identify the GMP decisions the system will support and the critical data each depends on. Data flow maps help find integrity risks.2,7
  2. Bring in every function that knows the need: production, engineering, quality, technical services and, for software, IT.10,6
  3. Write one requirement per line, numbered, specific and phrased so it can be verified objectively “by an authorised method, e.g. inspection, analysis or test”. Detail should follow the system’s risk and complexity.4,2
  4. Rate each for GMP impact, using the table below, and mark it mandatory or optional.4
  5. Assess the GMP risks found while writing. The URS is the basis for the system’s risk assessment.10,4
  6. Review and approve it, including the quality unit, and put it under document control.1,10
  7. Use it to choose and to check. Establish a configurable package’s degree of fit with the supplier; design qualification then verifies the URS, and equipment can be confirmed against it at the vendor before delivery.4,1
  8. Keep it current. Update it through change control as understanding grows and as the system changes.10,4

3.1Rating GMP impact.

Rate the function, not the system, and record why: PIC/S asks for “the reasons for the ranking” as critical or not critical to be documented.4

Table 4. Rating a requirement’s GMP impact, and the rule behind each rating.
RatingWhen it appliesExamplesBasis
HighIt decides or records release, calculates a result, or protects data integrityApproval, calculations, audit trail, access, interfaces, restoreDraft 9.6 focus list;3 Annex 11 section 16
MediumIt supports a GMP record without deciding itWorklists, sample scheduling, review remindersAnnex 11 section 1, extent based on risk6
LowIt creates no GMP record and decides nothingDashboard counts, a logo on reportsPI 011-⁠3 9.4, not critical, with reasons4
Not GMPA business function in the same systemInvoicing, time trackingIts effect on GMP functions assessed, FDA data integrity Q311

How much testing each rating needs is covered in risk-based validation.

4Bought, configured or SaaS: who writes the URS.

The regulated company owns the URS even when the supplier’s product sets most of its content. PIC/S says the URS, “although independent of the supplier”, should be understood and agreed by both. Users and suppliers determine a configurable package’s “degree of fit”; for a standard product, the URS may be compiled from the supplier’s specifications, taking the features you require.4 Annex 11 asks regulated users to review documentation supplied with commercial products “to check that user requirements are fulfilled”, which needs requirements to check against.6 The 2025 draft revision would have the regulated user take ownership of a vendor-supplied specification for the implemented version, and approve and control it.3

Two mistakes follow from getting this wrong. Copying the supplier’s full feature list makes you validate functions you don’t use. Accepting supplier documents without your own requirements leaves nothing to test your use against: MHRA says vendor-supplied validation data “in isolation of system configuration and users intended use is not acceptable”.14 The supplier’s share of the work is in validating SaaS for GxP.

5What inspectors find when the URS is weak.

PIC/S tells inspectors to verify that new systems were implemented through a process that gave adequate consideration to data integrity, and warns that inadequate consideration of data integrity requirements “may result in the purchase of software systems that do not include the basic functionality required”.7 FDA names user requirements at both ends of the life cycle.

Comprehensively assess procedures governing equipment design to ensure appropriate user requirements are established.

Indoco Remedies Limited, Goa, CDER warning letter of 16 December 2024, listing what the firm’s response failed to do after investigators found rough metal surfaces and protruding parts on a restricted access barrier system in its ISO 5 aseptic area, under 21 CFR 211.42(c)(10)(vi). The same barrier system had been remediated after a 2023 inspection.15 Lines such as EQ-⁠004 exist to prevent that.

the software-driven functional testing process used to evaluate device performance was not adequately validated to ensure that it consistently produced devices meeting specifications in that it did not include appropriate test cases to demonstrate user requirements met acceptance criteria.

Olympus Medical Systems Corporation, device warning letter of 7 October 2026, on its Shirakawa facility.16 Having user requirements is not enough; validation has to show each one was met.

6How EU GMP, PIC/S and FDA treat the URS.

Table 5. The URS under EU GMP, PIC/S and FDA.
QuestionEU GMP and PIC/SFDA
Is a URS named?Yes. Annex 15 defines it and makes it “a point of reference throughout the validation life cycle”; for sterile products, Annex 1 5.2 puts equipment monitoring in it1,12Not in 21 CFR Parts 11 or 211, which never use the term13,8
What it rests onAnnex 11 4.4: a documented risk assessment and GMP impact6211.63, design for intended use; materials, operating principles and performance selected “based on whether they are appropriate for their specific uses”, process validation IV.C.18,9
SoftwarePI 011-⁠3 section 9: complete, realistic, definitive and testable4Each CGMP workflow validated, data integrity Q3;11 devices: no validation “without predetermined and documented software requirements”5
How tests link to itPI 006-⁠4: IQ, OQ and PQ linked to the URS and DQ; inspectors check PQ against the URS10,4Devices: validation confirms that specifications “conform to user needs and intended uses”5
What is changingDraft Annex 11 6.1 to 6.6, consultation closed 7 October 2025, not adopted on 8 November 2026; PI 006-⁠4 in force 1 October 20263,17,18,10Device makers’ computer software assurance guidance of 3 February 2026 starts from intended use19

In the UK, regulation C17 of the Human Medicines Regulations 2012 keeps EU GMP guidelines as they applied at the end of 2020, Annexes 11 and 15 included, unless the licensing authority replaces them. MHRA’s data integrity guidance, quoted above, adds the UK’s own expectations.20,14 How the URS feeds IQ, OQ and PQ is covered in IQ, OQ and PQ.

7How it runs in Seal.

In Seal, the URS, functional, design and configuration specifications can be kept as controlled records linked to the configuration, its risks and its tests, with the depth of specification following the complexity and risk of the intended use, as the validation and AI assurance guide explains.

The commissioning and qualification blueprint keeps user requirements atomic, each with its rationale, criticality, acceptance intent, source and owner, and derived functional and design requirements keep their parents, so any requirement can be traced forward to verification and any result back to the approved need. The validation management blueprint maps a controlled URS, linked to its tests, onto the Annex 15 stages.

AQuestions and answers

What is the difference between a URS and a functional specification?

The URS says what the user needs the system to do. The functional specification describes the functions, performance and interfaces that meet those needs, and is linked back to them. WHO allows the two to be combined in one document, and Annex 15 lets the specification sit in a URS, a functional specification or both.

Who writes and approves the URS?

The regulated company writes it, drawing on production, engineering, quality, technical services and IT, even when a supplier drafts parts of it. PIC/S expects all relevant personnel and the quality unit to approve the specifications and acceptance criteria used in qualification, and Annex 15 asks that qualification documents be approved by appropriate personnel as defined in the quality system.

How detailed should a URS be?

Detailed enough to design, buy, configure and test against, and in proportion to the risk. WHO says the extent and detail should be commensurate with the operational risk and complexity of the system. Requirements behind GMP decisions and data integrity need to be explicit and testable; low-risk features can stay brief.

Is a URS the same as a system requirements specification?

In GxP work the names overlap. The draft revision of Annex 11 asks for an approved set of system requirements and gives a URS as its example, so the content matters more than the name: what you rely on the system to do. If a supplier’s system requirements specification describes how its product works, treat it as a functional specification and trace it back to your own requirements.

Does the URS change after go-live?

Yes. It stays a controlled document, updated through change control when the system or its use changes, so later testing and periodic review check the system as it is. PIC/S and the draft revision of Annex 11 both expect requirements to be kept current through the life cycle.

References20 sources

References

  1. 1EudraLex Volume 4, Annex 15: Qualification and Validation, European Commission, in operation from 1 October 2015, sections 2.2, 3.1 to 3.5, 3.9, 3.12 and glossary. https://health.ec.europa.eu/system/files/2016-11/2015-10_annex15_0.pdf (read 8 November 2026)
  2. 2WHO Technical Report Series No. 1019, Annex 3, Good manufacturing practices: guidelines on validation, Appendix 5, Validation of computerized systems, section 5, WHO, 2019. https://www.who.int/docs/default-source/medicines/norms-and-standards/guidelines/production/trs1019-annex3-gmp-validation.pdf (read 8 November 2026)
  3. 3Annex 11: Computerised Systems, draft for stakeholders’ consultation, European Commission, July 2025, sections 6, 7.5, 8, 9.6 and 10.2. https://health.ec.europa.eu/document/download/40231f18-e564-4043-94de-c031f813d38b_en?filename=mp_vol4_chap4_annex11_consultation_guideline_en.pdf (read 8 November 2026)
  4. 4PI 011-⁠3, Good Practices for Computerised Systems in Regulated GxP Environments, PIC/S, 25 September 2007, sections 9, 10 and 23.10. https://picscheme.org/docview/3444 (read 8 November 2026)
  5. 5General Principles of Software Validation; Final Guidance for Industry and FDA Staff, FDA, 11 January 2002, sections 3.1.2, 3.2 and 5.2.2. https://www.fda.gov/media/73141/download (read 8 November 2026)
  6. 6EudraLex Volume 4, Annex 11: Computerised Systems, European Commission, revision 1, in operation from 30 June 2011, sections 1, 2, 3, 4.4, 4.7, 5 to 7, 9, 12, 14, 16 and 17. https://health.ec.europa.eu/system/files/2016-11/annex11_01-2011_en_0.pdf (read 8 November 2026)
  7. 7PI 041-⁠1, Good Practices for Data Management and Integrity in Regulated GMP/GDP Environments, PIC/S, 1 July 2021, sections 9.1.6 and 9.3. https://picscheme.org/docview/4234 (read 8 November 2026)
  8. 821 CFR Part 211, Current Good Manufacturing Practice for Finished Pharmaceuticals, eCFR, sections 211.63, 211.65, 211.67, 211.68, 211.192 and 211.194, full text searched. https://www.ecfr.gov/current/title-21/chapter-I/subchapter-C/part-211 (read 8 November 2026)
  9. 9Process Validation: General Principles and Practices, guidance for industry, FDA, January 2011, section IV.C.1. https://www.fda.gov/media/71021/download (read 8 November 2026)
  10. 10PI 006-⁠4, Recommendations on Qualification and Validation, PIC/S, in force from 1 October 2026, sections 4.1.4, 4.1.6 and 4.2.1 to 4.2.3. https://picscheme.org/docview/11277 (read 8 November 2026)
  11. 11Data Integrity and Compliance With Drug CGMP: Questions and Answers, guidance for industry, FDA, December 2018, question 3. https://www.fda.gov/media/119267/download (read 8 November 2026)
  12. 12EudraLex Volume 4, Annex 1: Manufacture of Sterile Medicinal Products, European Commission, 22 August 2022, in operation from 25 August 2023, sections 4.16 and 5.2. https://health.ec.europa.eu/system/files/2022-08/20220825_gmp-an1_en_0.pdf (read 8 November 2026)
  13. 1321 CFR Part 11, Electronic Records; Electronic Signatures, eCFR, section 11.50, full text searched. https://www.ecfr.gov/current/title-21/chapter-I/subchapter-A/part-11 (read 8 November 2026)
  14. 14‘GXP’ Data Integrity Guidance and Definitions, Revision 1, MHRA, March 2018, section 6.19. https://assets.publishing.service.gov.uk/media/5aa2b9ede5274a3e391e37f3/MHRA_GxP_data_integrity_guide_March_edited_Final.pdf (read 8 November 2026)
  15. 15Warning letter to Indoco Remedies Limited, 320-⁠25-⁠23, MARCS-⁠CMS 691594, FDA, 16 December 2024. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/indoco-remedies-limited-691594-12162024 (read 8 November 2026)
  16. 16Warning letter to Olympus Medical Systems Corporation, MARCS-⁠CMS 729208, FDA, 7 October 2026. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/olympus-medical-systems-corporation-729208-10072026 (read 8 November 2026)
  17. 17Stakeholders’ Consultation on EudraLex Volume 4: Chapter 4, Annex 11 and New Annex 22, European Commission, 7 July to 7 October 2025. https://health.ec.europa.eu/consultations/stakeholders-consultation-eudralex-volume-4-good-manufacturing-practice-guidelines-chapter-4-annex_en (read 8 November 2026)
  18. 18EudraLex Volume 4, Good Manufacturing Practice guidelines, European Commission, listing Annex 11 as the January 2011 revision. https://health.ec.europa.eu/medicinal-products/eudralex/eudralex-volume-4_en (read 8 November 2026)
  19. 19Computer Software Assurance for Production and Quality Management System Software, guidance for industry and FDA staff, FDA, 3 February 2026, section V.A. https://www.fda.gov/media/188844/download (read 8 November 2026)
  20. 20The Human Medicines Regulations 2012, regulation C17, legislation.gov.uk. https://www.legislation.gov.uk/uksi/2012/1916/regulation/C17 (read 8 November 2026)