1Annex 15 section by section.
The current Annex 15 has been in operation since 1 October 2015. It applies to the facilities, equipment, utilities and processes used to make medicinal products, and “may also be used as supplementary optional guidance for active substances”.¹ The Commission’s Volume 4 page still lists this 2015 text as current.² PIC/S PI 006-4, in force since 1 October 2026, adds detail where inspectors found it needed, and its principles “equally apply” to active pharmaceutical ingredients, intermediates and finished dosage forms.³
The PIC/S GMP Guide and the UK use the same text. PIC/S carries it as Annex 15 of its GMP Guide, PE 009-18, with the EU references made general.⁴ In the UK, regulation C17 of the Human Medicines Regulations 2012 keeps the EU guidelines as they applied at the end of 2020 unless MHRA publishes its own,⁵ and MHRA’s GMP guidance still points to EU Volume 4.⁶ So the 2015 annex is the UK text too, and a later EU revision applies there only if MHRA publishes it. In the US, Part 211 and the 2011 process validation guidance cover the same ground.⁷⁸
| Section | What it requires | PI 006-4 adds | FDA counterpart |
|---|---|---|---|
| Principle, General | Control critical aspects through qualification and validation over the lifecycle; scope set by documented risk assessment; no retrospective validation | Other approaches accepted if they meet GMP principles (2.5.5) | 211.100(a); 2011 guidance |
| 1. Planning | Planned work by trained staff, quality oversight, a validation master plan (VMP) with seven minimum contents (below), checks on data integrity | VMP brief, referencing other documents rather than repeating them (3.4.1) | No VMP in Part 211 |
| 2. Documentation | Approved protocols with acceptance criteria; significant protocol changes and failed criteria as deviations; report against criteria; formal release to the next stage | Data integrity confirmed by people not doing the work (3.4.3 m) | 211.100(a), (b); 211.192 |
| 3. Qualification | URS, DQ, FAT and SAT, IQ, OQ and PQ, with operating limits and worst cases | URS as a controlled document (4.2) | 211.63; 211.68; guidance Stage 2 |
| 4. Requalification | Evaluate at an appropriate frequency; justify any fixed period and its criteria; assess small changes over time | Changes, maintenance and deviations reviewed together at set intervals (4.4.2) | 211.67(a); 211.68(a) |
| 5. Process validation | Prospective validation at commercial scale; justified number of batches; a protocol with twelve listed items (below); ongoing process verification | Ongoing verification replaces periodic revalidation (5.6) | 211.100(a); 211.110(a); 211.180(e) |
| 6. Transport | Defined routes, seasonal variation, risk assessment, continuous monitoring unless justified | Data logger placement and calibration (6.1) | No transport section; 211.142 and 211.150 cover warehousing and distribution |
| 7. Packaging | Qualify packaging equipment; primary packing at the minimum and maximum of critical parameters | Blister and sachet seal studies (6.2) | 211.63; 211.68 |
| 8. Utilities | Qualify steam, water, air and gases; seasonal variation; risk of product contact | Effort on utilities in direct product contact (6.3) | 211.46; 211.48 |
| 9. Test methods | Validate methods used in qualification, validation and cleaning; microbial recovery | Pharmacopoeial methods verified (6.4) | 211.165(e); 211.194(a)(2) |
| 10. Cleaning | Validate for all product contact equipment; visual check not alone; no cleaning and retesting until it passes; toxicological limits; hold times | Monitoring after validation; verification at every changeover if the carryover limit is below what is visible (7.13) | 211.67(b) |
| 11. Change control | Written procedure; risk-based impact assessment; approval; effectiveness check | A skipped effectiveness check justified in writing (2.6.8) | 211.100(a) |
Who does what. Validation staff need not report to QA, but there should be “appropriate quality oversight over the whole validation life cycle” (1.3), and site staff confirm a vendor’s protocols suit their procedures before approving them (2.6).¹ The Quality Unit should be involved in approving all change controls, and when contractors do the work, responsibility for its standard stays with the contract giver.³
1.1What the VMP and the process validation protocol must contain.
Annex 15 lists the minimum for two documents. A VMP, or an equivalent document, includes or references the qualification and validation policy; the organisation, roles and responsibilities; a summary of the facilities, equipment, systems and processes with their status; change control and deviation management for this work; guidance on developing acceptance criteria; references to existing documents; and the strategy, including requalification (1.5).¹ The VMP template sets these out as sections.
A process validation protocol should include at least (5.22):¹
- A short process description and a reference to the master batch record.
- Functions and responsibilities.
- The CQAs to be investigated.
- The CPPs and their limits.
- Other attributes and parameters monitored, and why.
- Equipment and facilities, including measuring and recording equipment, with calibration status.
- Analytical methods and their validation.
- In-process controls, their acceptance criteria and why each was chosen.
- Additional testing, with acceptance criteria.
- The sampling plan and its rationale.
- Methods for recording and evaluating results.
- The process for release and certification of batches, if applicable.
For the depth behind single rows, see IQ, OQ and PQ, PPQ protocols, how many PPQ batches, continued process verification and cleaning validation.
2The judgement calls Annex 15 leaves to you.
| Decision | Allowed | Only if | Clause |
|---|---|---|---|
| Batch count other than 3 | An alternative number | Justified by standard methods, or similar products or processes on site | 5.19, 5.20 |
| Concurrent validation | Routine production before validation ends | Exceptional, strong benefit-risk ratio, in the VMP, approved; results to the QP before certification | 5.16, 5.17 |
| Rely on FAT results | Tests at the vendor not repeated on site | Functionality not affected by transport and installation | 3.6 |
| Combined IQ and OQ | One IOQ document | Appropriate to the equipment’s complexity | 2.5, 3.10 |
| Proceed with open items | Conditional approval | Documented assessment of no significant impact on the next activity | 2.10 |
| External data | Data from outside your own programme | Justified, with assurance of controls when it was gathered | General |
Three consecutive batches are “generally considered acceptable”, but “without prejudice to” 5.19, under which each manufacturer “must determine and justify the number of batches necessary”.¹ PI 006-4 adds that any weakness in the validation package should be made up by extra testing in ongoing verification.³
3Example: a periodic requalification review.
This example is invented. A tablet site set a 24-month review interval for fluid bed dryer FBD-04 in its validation master plan, because the dryer is product-contact equipment that sets granule moisture. The last OQ and PQ closed on 14 October 2024, so the review was due by 14 October 2026; it was signed on 5 October 2026.
| Input | Finding | Requirement |
|---|---|---|
| Interval | 24 months, justified by criticality | Annex 15 4.2; PI 4.4.3 |
| Changes | Inlet filter housing replaced like for like (CC-24-118); outlet temperature probe replaced like for like (CC-25-031); control software updated (CC-25-207) | Annex 15 11.2; PI 4.4.1 |
| Maintenance, calibration | 8 planned visits done; every probe calibration within tolerance | PI 4.4.2 |
| Deviations | 2 deviations for inlet airflow alarms in 96 batches dried, both after the filter change | PI 4.4.2 |
| Product quality review | The 2025 review states the dryer functioned as expected | PI 4.4.4 |
| Decision | Three changes in two years, then airflow alarms after the filter change: the series may amount to a major change, so repeat the OQ airflow tests at the upper and lower limits and assess the software update under Annex 11 | Annex 15 3.11, 4.2, Principle; PI 4.4.2 |
| Next review | Due by 5 October 2028 | Annex 15 4.2 |
Annex 15 asks for “the possibility of small changes over time” to be assessed,¹ and PI 006-4 says why: a series of minor changes “may represent a major change over time”.³ Each change here was minor on its own; only the review sees them together.
4What inspectors ask for, and what they find.
PIC/S wrote PI 006-4 as “a training resource for GMP inspectors and the pharmaceutical industry” (2.1.2), so its expectations are the questions to prepare for. Have these ready:³
- The VMP, approved by management, regularly reviewed and updated after changes to facilities, utilities, equipment, systems or processes (3.4.2).
- The justification for each requalification frequency, based on risk and equipment criticality (3.4.3 f iii, 4.4.3).
- Qualification and validation deviations, in the report and also in the site deviation system (3.4.3 l).
- Each like-for-like decision, documented, justified and approved by the Quality Unit (4.4.1).
- An ongoing process verification programme for every process, normally reported at least once a year with a conclusion on the state of control (5.6.1, 5.6.5).
- Where cleanliness rests on visual inspection, the threshold at which residues are readily visible, set under production lighting and distances (7.8.3).
EU inspectors write up the same sections. Malta’s inspectors issued this statement of non-compliance after inspecting a maker of pellets:
The inspection resulted in a critical deficiency related to contamination risk in the Fluid Bed Coating (FBC) equipment due to an observed pool of liquid and residue in a section of the inlet air plenum of a fully cleaned FBC. The flaws were due to common design between FBCs (inclination of plenum not allowing gravity draining) and inadequate cleaning procedure.
Glukem Biocare Private Limited, Siddipet, India, statement MT/004NCR/2026, Malta Medicines Authority, 16 October 2026.⁹ Its eleven major findings included “Deficient process validation, including insufficient coverage of process, demonstration of its reproducibility and pellet homogeneity”, “Incomplete cleaning validation” and “Equipment qualification”, and supply to EEA markets was prohibited. Annex 15 expects DQ to show the design complies with GMP (3.3), cleaning validation protocols to justify the locations sampled (10.11) and validation batches to confirm reproducibility (5.18).¹
FDA makes the same points in US terms. To a maker of sterile injectables:
Notably, your acceptance criteria were inappropriate in that they allowed routine recovery of multiple BI survivors per re-qualification run.
Baxter International Inc., warning letter 320-26-132, 29 September 2026, under 211.113(b).¹⁰ FDA also objected that the firm “allowed repetition of re-qualification cycles without proper investigation into observed BI growth”. In Annex 15 terms, requalification confirms a system remains “in a state of control” (4.1), and results that fail pre-defined criteria are deviations to be “fully investigated” (2.8), not rerun.¹
5What the revision will change.
EMA and PIC/S plan a targeted revision. Its main purpose is to make Annex 15 mandatory for manufacturers of chemical and biological active substances, as the 2020 lessons-learnt report on nitrosamines found in sartan medicines in 2018 recommended. It will also bring in ICH Q9(R1) on quality risk management.¹¹
The concept paper was agreed by EMA’s GMP/GDP inspectors on 30 November 2025 and by PIC/S on 14 January 2026, and was out for comment from 9 February to 9 April 2026.¹¹ In July 2026 EMA replaced it with a corrigendum under a new reference number, still dated 19 January 2026 on its face, which moved the later steps back by eight to sixteen months.¹¹¹² Summaries written before July give the old dates.
| Step | January 2026 plan | Current plan |
|---|---|---|
| Draft out for 3 months’ consultation | April 2026 | December 2026 |
| Comments on the draft due | June 2026 | March 2027 |
| Endorsed by EMA inspectors | July 2026 | November 2027 |
| Published; adopted by PIC/S | By December 2026 | April 2028 |
For active substance makers the concept paper names, among other areas, the “Validation Master File”, validation by third parties, investigation of failed acceptance criteria, URS, FAT and SAT, concurrent validation, validation of solvent and material recovery, continuous and hybrid verification, and transport. A comprehensive review of the whole annex is to follow later.¹¹
5.1What API makers can prepare now.
| Topic | ICH Q7 today | Annex 15 | Prepare |
|---|---|---|---|
| Retrospective validation | Allowed for well-established processes, 10 to 30 batches (12.44, 12.50) | “no longer considered an acceptable approach” (General) | List every process validated this way and plan current data |
| Planning | A documented validation policy (12.10) | A VMP with seven elements (1.4, 1.5) | Write or extend the VMP |
| Qualification | DQ, IQ, OQ and PQ (12.30) | Also a URS kept as the reference, FAT and SAT (3.2 to 3.7) | Trace critical equipment to a URS |
| Failed criteria | Variations documented and justified (12.23) | Recorded as deviations and fully investigated (2.7, 2.8) | Route them through the deviation system |
| Ongoing verification | Periodic evaluation; no revalidation if nothing significant changed (12.60) | A protocol, trending and statistics (5.29 to 5.32) | Start trending critical attributes |
| Transport | No adverse effect on quality (10.21) | Defined routes, risk assessment, monitoring (6.1 to 6.4) | Risk-assess each route |
PI 006-4 already expects legacy processes validated to earlier standards to meet current ones, through ongoing verification and extra testing found by gap analysis.³ Start there: PI 006-4 applies now, and the revised annex is not planned for publication until April 2028.¹¹
6How it runs in Seal.
In Seal, the qualified state of a system is a released baseline that change control and periodic review work from, as in commissioning and qualification. A review like the one for FBD-04 starts from the changes, calibrations and deviations already linked to the dryer, and a later calibration failure finds the tests that used that instrument.
Process validation keeps the PPQ protocol, batch records, results and exceptions connected, so review starts from open exceptions rather than a batch count and carries into ongoing verification. Cleaning validation ties limits, worst-case rationale and hold times to each clean, and GxP validation checks equipment status at the point of use.
References
- 1EudraLex Volume 4, EU Guidelines for Good Manufacturing Practice, Annex 15: Qualification and Validation, European Commission, 30 March 2015, in operation from 1 October 2015. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ 2015- 10_ annex15_ 0. pdf (read 8 November 2026) - 2EudraLex Volume 4, Good Manufacturing Practice (GMP) guidelines, European Commission. https:/
/ health. ec. europa. eu/ medicinal- products/ eudralex/ eudralex- volume- 4_ en (read 8 November 2026) - 3PIC/S PI 006-4, Recommendations on Qualification and Validation, sections 2 to 7 and 9, Pharmaceutical Inspection Co-operation Scheme, 1 October 2026. https:/
/ picscheme. org/ docview/ 11277 (read 8 November 2026) - 4PIC/S GMP Guide, PE 009-18 (Annexes), Annex 15, Pharmaceutical Inspection Co-operation Scheme, 24 September 2026. https:/
/ picscheme. org/ docview/ 11333 (read 8 November 2026) - 5The Human Medicines Regulations 2012, regulation C17, legislation.gov.uk, as amended to 1 January 2025. https:/
/ www. legislation. gov. uk/ uksi/ 2012/ 1916/ regulation/ C17 (read 8 November 2026) - 6Medicines: good manufacturing practice and good distribution practice, Medicines and Healthcare products Regulatory Agency, GOV.UK, updated 13 May 2024. https:/
/ www. gov. uk/ guidance/ good- manufacturing- practice- and- good- distribution- practice (read 8 November 2026) - 721 CFR Part 211, Current Good Manufacturing Practice for Finished Pharmaceuticals, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211 (read 8 November 2026) - 8Process Validation: General Principles and Practices, guidance for industry, Revision 1, FDA, January 2011. https:/
/ www. fda. gov/ media/ 71021/ download (read 8 November 2026) - 9Glukem Biocare Private Limited, statement of non-compliance with GMP MT/004NCR/2026, EudraGMDP document reference 188112, Malta Medicines Authority, issued 16 October 2026, EudraGMDP non-compliance reports. https:/
/ eudragmdp. ema. europa. eu/ inspections/ gmpc/ searchGMPNonCompliance. do (read 8 November 2026) - 10Baxter International Inc., warning letter 320-26-132, MARCS-CMS 733231, FDA, 29 September 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ baxter- international- inc- 733231- 09292026 (read 8 November 2026) - 11Concept paper on the revision of the guidelines on Good Manufacturing Practice for medicinal products, Annex 15, corrigendum, EMA/
INS/ GMP/ 163466/ 2026, sections 1, 2 and 4, European Medicines Agency, dated 19 January 2026 on its face, published July 2026. https:/ / www. ema. europa. eu/ en/ documents/ scientific- guideline/ concept- paper- revision- guidelines- good- manufacturing- practice- medicinal- products- annex- 15- qualification- validation- corrigendum_ en. pdf (read 8 November 2026) - 12Concept paper on the revision of the guidelines on Good Manufacturing Practice for medicinal products, Annex 15, EMA/
INS/ GMP/ 20217/ 2026, section 4, European Medicines Agency, 19 January 2026, as archived on 19 February 2026. https:/ / web. archive. org/ web/ 20260219143351/ https:/ / www. ema. europa. eu/ en/ documents/ scientific- guideline/ concept- paper- revision- guidelines- good- manufacturing- practice- medicinal- products- annex- 15- qualification- validation_ en. pdf (read 8 November 2026) - 13ICH Q7, Good Manufacturing Practice Guide for Active Pharmaceutical Ingredients, sections 10 and 12, ICH, 10 November 2000. https:/
/ database. ich. org/ sites/ default/ files/ Q7%20Guideline. pdf (read 8 November 2026)
AQuestions and answers
What changed in PI 006-4 from PI 006-3?
PI 006-3, from 2007, was titled ‘Recommendations on validation master plan, installation and operational qualification, non-sterile process validation, cleaning validation’. PI 006-4, in force from 1 October 2026, updates and renames it to follow the 2015 Annex 15 and the revised GMP Chapters 3 and 5. Its sections run from URS, DQ, FAT and SAT through PQ and requalification to concurrent validation, ongoing verification, transport, packaging, utilities and test methods, and its principles apply equally to APIs.
Is a validation master plan mandatory under Annex 15, or will an equivalent document do?
Either will do. Annex 15 asks for the key elements of the qualification and validation programme to be defined in a VMP or an equivalent document, and its list of minimum contents applies to whichever you use. PI 006-4 expects a brief summary that refers to policies, procedures and protocols rather than repeating them, and says inspectors will consider different approaches as long as they meet GMP principles.
Does Annex 15 apply to investigational medicinal products?
Partly. Annex 15 sends process validation of investigational products to Annex 13, which is now the Commission’s 2017 guideline on GMP for investigational medicinal products. That guideline expects premises and equipment to be qualified under Annex 15, but the process is validated as far as is appropriate for the stage of development, not to the extent needed for routine production, and documented as Annex 15 requires. Sterilising processes are validated to the same standard as for authorised products, and Annex 15 notes that cleaning may need verification after each batch.
Where can I download the current Annex 15 PDF?
From the European Commission’s EudraLex Volume 4 page, where Annex 15, Qualification and validation, is listed as in operation since 1 October 2015. That 2015 text is still the current one: the revision is at concept-paper stage, with a draft planned for consultation in December 2026. PIC/S publishes the same text as Annex 15 of its GMP Guide.