1Where the revision stands, and when it will apply.
The revision is still a draft, written by EMA’s GMP/GDP Inspectors Working Group (IWG) with PIC/S and consulted on with a revised Chapter 4 on documentation and a new Annex 22 on artificial intelligence.1,
| Step | Planned in 2022 | What has happened |
|---|---|---|
| Concept paper | Consultation October to December 2022 | Consulted 16 November 2022 to 16 January 20236 |
| Draft annex | Consultation from December 2024 | Consulted 7 July to 7 October 20251 |
| Final text | IWG adoption, March 2026 | Target for a final text to the Commission: Q4 20267 |
| Publication | June 2026 | Not published3 |
| PIC/S adoption | September 2026 | Not adopted: still listed as a draft; PE 009-18 of 24 September 2026 revised Annex 198, |
The work plan puts the IWG’s last meeting of 2026 on 25 to 26 November, dates that “may be modified as needed”. After it, watch the EudraLex Volume 4 page, which lists revised annexes with their dates of application, and PIC/S news.7,
No date has been set; each adopted annex carries its own. The revised Annex 19, dated 23 June 2026, gave “3 months from the date of publication by the European Commission” and applied from 24 September 2026.10,
The revision is for human medicines: since 16 July 2026 veterinary GMP has its own binding rules, with computerized systems in Annex IV of Regulation (EU) 2025/2091.7,
2What the draft changes.
The draft replaces the 2011 annex’s five pages of short clauses with 19 pages in 17 sections by topic, plus a glossary.4,
Among the 2011 clauses with no counterpart in the draft are the inventory of systems (4.3), only Qualified Persons (QPs) certifying batches in a system (15), and clear printed copies (8.1), which the concept paper said “may be reconsidered”.4,
3A gap assessment checklist against the draft.
The lines select draft clauses a system test or record can show; they are not every clause. The last column says whether the point is already expected under the 2011 text or EMA’s answers, tightened, or new.13,
- Already cited first: 11.1, 11.5, 11.10 and 12.1 to 12.3, failures FDA and EU inspectors cite today (below).
- Tightened rows next: the 2011 text sets the principle, so the work is evidence and detail.
- New rows last: plan and budget them now, and confirm each against the final text.
| Clause | Check | Record that shows it | Today |
|---|---|---|---|
| 3.1 iv, v | Management review covers system metrics; senior management oversees the state of control | Management review minutes with system metrics | New |
| 6.1, 6.3, 6.6 | Approved user requirements (URS) for the implemented version, yours even if a vendor wrote them; settings recorded | URS; configuration specification | Tightened: 2011 4.4 |
| 7.3 to 7.5 | Contract, or procedure for internal IT, covers 7.5 i to ix, such as service levels, exit and testing new versions | Contract or IT procedure mapped to 7.5 | Tightened: 2011 3.1 |
| 8.4, 8.5 | Critical alarms acknowledged by authorized users with a reason; log holds alarm, times, user and role; no GMP user can edit it | Alarm log | New |
| 9.4 to 9.8 | Executed, repeatable test scripts, each traced to a requirement; any conditional go-live in the report | Protocols; trace matrix; report | Tightened: 2011 4.4, 4.7 |
| 9.9 | Vendor test evidence checked against the implemented version | Vendor evidence review | Tightened: 2011 3.3 |
| 10.2, 10.3 | Critical data moves by validated interface where possible; migrations validated | Interface and migration reports | Tightened: 2011 4.8, 5 |
| 11.1 | No shared account can change data or settings | Account list, one owner each | Expected: 2011 12.4; EMA |
| 11.4, 11.5 | Passwords confidential; issued ones changed at first login; rules set by risk and enforced by the system; for critical systems, long enough and mixing “uppercase, lowercase, numbers and symbols” | Password settings; procedure | New; already cited in the EU (below) |
| 11.3, 11.6 to 11.9 | No login by token or card alone if another user could use it; multifactor authentication (MFA) for remote access to critical systems; lockout; locked inactivity logout; access log | Configuration evidence | New; EMA cites MFA for remote QP work |
| 11.10, 11.11 | GMP users hold no admin rights; managers review accounts | Role matrix; signed review | Tightened: 2011 12.1, 12.3 |
| 12.1 to 12.3 | Audit trail on all manual interactions, old and new values, reason prompted, enabled and locked at all times | Audit trail test | Tightened: 2011 9; EMA |
| 12.5 to 12.8, 12.10 | Written, risk-targeted review by someone not involved, before release unless justified; release-relevant ones available to the QP | Procedure; dated reviews linked to the batch | Tightened: 2011 9; EMA |
| 12.9 | Complete electronic copy, audit trail included, searchable and sortable | Export test | New: 2011 8 asks for printouts |
| 13.3, 13.8 | Full re-authentication to sign (password or biometrics alone for later signatures in immediate sequence); a signed record can’t change, or shows as unsigned if it does | Signature test | Tightened: 2011 14 |
| 13.9 | Any change to a record signed in wet ink invalidates the signature, for example by a printed hash code | Signed page with checksum | New |
| 14.2, 14.3 | Periodic review covers the twelve listed inputs, at a risk-based frequency; final review at retirement | Last periodic review | Tightened: 2011 11 |
| 15.3 | Recurrent security awareness training, its effect evaluated, for example by simulated tests | Training and test results | New |
| 15.7 | Disaster recovery plan tested, with a recovery time objective where applicable | Plan; test report | Tightened: 2011 16 |
| 15.8, 15.9, 15.20, 10.4 | Networks segmented; firewall rules as strict as feasible and reviewed periodically; encrypted protocol for remote internet access; critical data encrypted where applicable | Network diagram; firewall rule review; encryption settings | New |
| 15.10 to 15.19 | Platforms supported and patched or isolated; USB ports off on critical computers; penetration tests on critical internet-facing systems | Platform list; test report | New |
| 16.2 to 16.6 | Backups by risk, kept physically and logically apart; restore tested | Backup design; restore record | Tightened: 2011 7.2 |
| 17.1, 17.2 | Released data read-only; checksum or manual check before deleting moved data | Archive procedure; verification log | Tightened: 2011 17 |
EMA’s 2011 workaround for systems whose printouts cannot show changes, a printed audit trail report linked manually to the batch release record, would not by itself meet row 12.9: “Flat and locked files are not acceptable”.5,
FDA already cites three of these rows (11.1, 11.10 and 12.1 to 12.3) under 21 CFR 211.68(b). To Ava Inc., Illinois, on 14 April 2026:14
your firm utilized a common username and password to access high performance liquid chromatography (HPLC) equipment used for impurity testing of drug products. Additionally, analysts had administrator privileges to modify and delete data.
And to Landy International, Xiamen, on 12 June 2024:15
Your stand-alone gas chromatogram (GC) computer system lacked appropriate controls, such as an audit trail and individual log-in access to prevent the deletion of data.
EU inspectors act on the same failures. Malta’s statement of non-compliance for Zenzi Pharmaceutical Industries, Thane, issued on 5 May 2026, records:16
Audit trail was disabled from chromatographic sequences in QC analysis. The password complexity policy for software was not enforced with high protection requirements.
3.1Who does what.
The draft names who should work together: “process owner, system owner, users, subject matter experts (SME), QA, QP, the internal IT department, vendors, and service providers” (5.1). It assigns few tasks by name: senior management’s oversight (3.1 v), managers’ access reviews (11.11), audit trail review by someone not involved (12.6), and audit trail settings changed only by an administrator outside GMP work (12.3).13 One workable split for the rest follows the 2011 annex’s definitions: the process owner, responsible for the business process, approves requirements (6) and alarm settings (8); the system owner, responsible for availability and maintenance, holds access, security and backup (11, 15, 16); validation runs testing (9); QA owns the audit trail and periodic review procedures (12, 14).4
3.2Example: three lines of a gap log.
Example, all names invented: CDS-02 is a chromatography data system at Site A, assessed against the draft in November 2026.
| Clause | Finding | Action and owner |
|---|---|---|
| 9.5 | 14 of 52 operational qualification (OQ) test cases (27%) cite no requirement | Map or retire the 14; validation lead, by 31 January 2027 |
| 11.1 | Two shared “QC-Lab” accounts can reprocess data | Personal accounts now, as 2011 12.4 already expects; QC system owner, by 15 December 2026 |
| 12.8, 12.10 | Audit trail review is monthly, after release | Review release-relevant runs before certification (12.10); justify any later review for the rest (12.8); QA, by 28 February 2027 |
How to run the review itself is in audit trail review.
4How it runs in Seal.
In Seal’s computer system assurance, each system you assess is a record with its owners, supplier, interfaces, electronic records and signatures. Each requirement links to its risk, its configuration and the test cases that cover it, and shows whether they passed and on which version, so a test that traces to no requirement, the 9.5 gap above, is visible while the work is done rather than in a matrix exported at the end. Supplier evidence is recorded against the claim it supports, with the gaps found, and roles, permissions, signatures and audit trail settings form a controlled configuration baseline.
Each change that closes a gap is a release with its own risk assessment, test evidence and approval: a Check on its change control passes only when every approved test case has a finished, passing run on the version being released, and it cannot publish until the Check passes and every sign-off is given. Neil can prepare a periodic access review or an audit trail review as a draft with its source evidence: the system owner decides on access, and the authorized reviewer assesses and signs the audit trail review.
5If you are inspected by FDA or MHRA.
5.1FDA already expects the access and audit trail rows.
Beyond 211.68(b), Part 11 requires for electronic records “limiting system access to authorized individuals” (11.10(d)) and secure, computer-generated, time-stamped audit trails (11.10(e)).17 FDA’s data integrity guidance, like draft 11.1, accepts shared accounts only for viewing data, and where a regulation sets when data is reviewed, such as before batch release under 211.22, it applies the same timing to the audit trail, much as draft 12.8 does.18,
5.2Testing is where FDA’s CSA guidance differs.
The draft expects “executed test scripts” (9.4) and mentions neither unscripted testing nor CSA. A case for unscripted testing would rest on 2.3, which allows alternative practices “if they have been proven and documented to provide the same or higher level of control”.13 FDA’s Computer Software Assurance (CSA) guidance, final since September 2025 and revised on 3 February 2026, allows scenario, error-guessing and exploratory testing for features that are not high process risk, but it is a device guidance, for production and quality system software under 21 CFR Part 820.19 The conflict is real for combination products run under Part 820 (21 CFR 4.4(b)(2)) and for drug firms that adopt CSA group-wide.20 For systems behind EU-released product, keep scripted tests at least where draft 9.6 focuses testing, such as access privileges, release, calculations, audit trails, alarms, interfaces and restore. See CSV vs CSA.
5.3In the UK the 2011 annex stays until the MHRA replaces it.
In the UK, EU GMP guidelines as they applied at the end of 2020 continue to apply unless the MHRA replaces them, which it may do only after consultation and “to take account of technical or scientific progress” (Human Medicines Regulations 2012, regulation C17), so a revised EU annex does not apply there by itself.21 MHRA’s 2018 data integrity guidance already covers two of the draft’s headline points: “For systems generating, amending or storing GXP data shared logins or generic user access should not be used”, and “Routine data review should include a documented audit trail review where this is determined by a risk assessment.”22
6Small devices: an EMA answer the draft would overturn.
EMA’s 2011 answer on small devices, whose data is often transient, says: “An audit trail is therefore not necessary and user access may be limited to those functions of parameter control.”5 The draft asks for an audit trail wherever users can create, modify or delete data or settings (12.1), and the concept paper says the revision should replace relevant parts of those answers.13,
AQuestions and answers
Where can I download the draft Annex 11 PDF?
The European Commission’s consultation page for Chapter 4, Annex 11 and Annex 22 links the draft as “Revised Annex 11 – Computerised Systems”, a 19-page PDF published in July 2025. PIC/S announced the same consultation and still lists the draft under Drafts on its Publications page. The consultation closed on 7 October 2025, so comments can no longer be sent.
What changes in the revised Chapter 4 on documentation?
The draft Chapter 4, consulted on alongside Annex 11, makes risk management central to a data governance system that keeps documents accurate, available and legible on paper, electronically or in hybrid form. Documents in any form, text, image, video or audio, must stay complete and readable through their lifecycle. It also clarifies electronic records, signatures and data integrity, consistently with the revised Annex 11.
Does the draft Annex 11 apply to cloud and software-as-a-service systems?
Yes. System requirements apply whether a system is developed in-house, bought off the shelf or provided as a service. The regulated user stays fully responsible when a vendor or service provider qualifies or runs the system, and the contract should cover oversight, audits, support during inspections, an exit strategy for the data and the chance to test new versions before release.
Does the draft Annex 11 cover artificial intelligence?
Only as part of a computerized system: the draft applies to all computerized systems but does not mention AI. A new Annex 22, consulted on at the same time, covers AI models in critical GMP applications, but only static models whose output is deterministic. It does not apply to generative AI or large language models, which it says should not be used in critical GMP applications; where they are used in non-critical work, trained staff stay responsible for checking their output.
References22 sources
References
- 1Stakeholders’ Consultation on EudraLex Volume 4, Good Manufacturing Practice Guidelines: Chapter 4, Annex 11 and New Annex 22, European Commission, July 2025. https:/
/ health. ec. europa. eu/ consultations/ stakeholders- consultation- eudralex- volume- 4- good- manufacturing- practice- guidelines- chapter- 4- annex_ en (read 25 November 2026) - 2Joint stakeholders consultation on the revision of Chapter 4, Annex 11 and the new Annex 22 of the PIC/S and EU GMP Guides, PIC/S, 7 July 2025. https:/
/ picscheme. org/ en/ news/ 131/ joint- stakeholders- consultation- on- the- revision- of- chapter- 4 (read 25 November 2026) - 3EudraLex Volume 4, Good Manufacturing Practice guidelines, European Commission, including its list of veterinary GMP legal acts. https:/
/ health. ec. europa. eu/ medicinal- products/ eudralex/ eudralex- volume- 4_ en (read 25 November 2026) - 4EudraLex Volume 4, Annex 11: Computerised Systems, revision 1, European Commission, January 2011. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ annex11_ 01- 2011_ en_ 0. pdf (read 25 November 2026) - 5Guidance on good manufacturing practice and good distribution practice: Questions and answers, Annex 11, data integrity and remote batch certification sections, European Medicines Agency. https:/
/ www. ema. europa. eu/ en/ human- regulatory- overview/ research- development/ compliance- research- development/ good- manufacturing- practice/ guidance- good- manufacturing- practice- good- distribution- practice- questions- answers (read 25 November 2026) - 6Concept Paper on the revision of Annex 11 of the guidelines on Good Manufacturing Practice for medicinal products, Computerised Systems, EMA GMP/GDP Inspectors Working Group and PIC/S, EMA/
INS/ GMP/ 778340/ 2022, 19 September 2022. https:/ / www. ema. europa. eu/ en/ documents/ regulatory- procedural- guideline/ concept- paper- revision- annex- 11- guidelines- good- manufacturing- practice- medicinal- products- computerised- systems_ en. pdf (read 25 November 2026) - 7The 3-year work plan for the Inspectors Working Group, January 2026 to December 2028, European Medicines Agency, March 2026. https:/
/ www. ema. europa. eu/ en/ documents/ other/ 3- year- work- plan- inspectors- working- group_ en. pdf (read 25 November 2026) - 8Publications: Drafts, PIC/S, listing “Draft guidelines: Revised Annex 11 - Computerised systems” of 7 July 2025. https:/
/ picscheme. org/ en/ publications?tri=draft (read 25 November 2026) - 9Revision of PIC/S GMP Guide (PE 009-18), PIC/S, 23 September 2026. https:/
/ picscheme. org/ en/ news/ 149 (read 25 November 2026) - 10EudraLex Volume 4, Annex 19: Reference and Retention Samples, C(2026) 4135 final, European Commission, Brussels, 23 June 2026. https:/
/ health. ec. europa. eu/ document/ download/ 831d392e- bcc4- 4552- 8011- 2b724b8655de_ en?filename=c2026- 4135_ en_ act_ en. pdf (read 25 November 2026) - 11EudraLex Volume 4, Annex 1: Manufacture of Sterile Medicinal Products, European Commission, 22 August 2022. https:/
/ health. ec. europa. eu/ system/ files/ 2022- 08/ 20220825_ gmp- an1_ en_ 0. pdf (read 25 November 2026) - 12Commission Implementing Regulation (EU) 2025/2091 of 17 October 2025 laying down good manufacturing practice for veterinary medicinal products, Article 46 and Annex IV, EUR-Lex. https:/
/ eur- lex. europa. eu/ legal- content/ EN/ TXT/ HTML/ ?uri=CELEX:32025R2091 (read 25 November 2026) - 13Annex 11: Computerised Systems, draft for consultation, European Commission and PIC/S, July 2025. https:/
/ health. ec. europa. eu/ document/ download/ 40231f18- e564- 4043- 94de- c031f813d38b_ en?filename=mp_ vol4_ chap4_ annex11_ consultation_ guideline_ en. pdf (read 25 November 2026) - 14Warning Letter 320-26-64 to Ava Inc., MARCS-CMS 721180, FDA, 14 April 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ ava- inc- 721180- 04142026 (read 25 November 2026) - 15Warning Letter 320-24-43 to Landy International, MARCS-CMS 679066, FDA, 12 June 2024. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ landy- international- 679066- 06122024 (read 25 November 2026) - 16Statement of non-compliance with GMP, report MT/002NCR/2026, Zenzi Pharmaceutical Industries Private Limited, Malta Medicines Authority, 5 May 2026, EudraGMDP document 184851. https:/
/ eudragmdp. ema. europa. eu/ inspections/ gmpc/ prepReviewSubmittedGMPC. do?key=184851 (read 25 November 2026) - 1721 CFR 11.10, Controls for closed systems, paragraphs (d) and (e), eCFR, current to 23 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- A/ part- 11/ subpart- B/ section- 11. 10 (read 25 November 2026) - 18Data Integrity and Compliance With Drug CGMP: Questions and Answers, guidance for industry, FDA, December 2018, questions 5 and 8. https:/
/ www. fda. gov/ media/ 119267/ download (read 25 November 2026) - 19Computer Software Assurance for Production and Quality Management System Software, guidance for industry and FDA staff, FDA, 3 February 2026. https:/
/ www. fda. gov/ media/ 188844/ download (read 25 November 2026) - 2021 CFR 4.4, How can I comply with these current good manufacturing practice requirements for a co-packaged or single-entity combination product?, paragraph (b)(2), eCFR, current to 23 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ section- 4. 4 (read 25 November 2026) - 21The Human Medicines Regulations 2012, regulation C17, Guidelines on good manufacturing practice and good distribution practice, legislation.gov.uk. https:/
/ www. legislation. gov. uk/ uksi/ 2012/ 1916/ regulation/ C17 (read 25 November 2026) - 22‘GXP’ Data Integrity Guidance and Definitions, Revision 1, MHRA, March 2018, sections 2.5, 6.13 and 6.16. https:/
/ assets. publishing. service. gov. uk/ media/ 5aa2b9ede5274a3e391e37f3/ MHRA_ GxP_ data_ integrity_ guide_ March_ edited_ Final. pdf (read 25 November 2026)