What is the difference between validation, verification, qualification and calibration?

Calibration shows an instrument’s readings agree with a reference standard within set limits. Qualification proves equipment, utilities, facilities or systems are installed correctly, work across their ranges and perform in use (IQ, OQ and PQ). Validation proves a process, cleaning procedure, test method or computerised application consistently meets predetermined criteria, on calibrated, qualified equipment. Verification confirms that specified requirements are met in a given case, such as a compendial method in your laboratory or cleaning after one campaign.Checked against its sources on 9 November 2026. How these answers are made

Illustration of a seal comparing two equipment versions, each linked to its retained evidence.

1The four terms side by side.

TermWhat it showsApplies toTypical recordDefined in
CalibrationReadings match a reference standard, within limitsMeasuring, weighing, recording and control instrumentsCalibration record against the programme’s limitsEU GMP glossary;1 ICH Q7 glossary2
QualificationEquipment is properly installed, works correctly and gives the expected resultsPremises, utilities, equipment, IT infrastructureDQ, IQ, OQ and PQ protocols and reportsICH Q7 glossary;2 Annex 15 section 33
ValidationA process, method or system consistently meets predetermined acceptance criteriaManufacturing processes, cleaning, test methods, computerised applicationsPlan, protocol and reportICH Q7 glossary;2 EU GMP glossary1
VerificationSpecified requirements are fulfilled, shown by objective evidenceCompendial methods, one cleaning campaign, the process in routine production, device designVerification record, routine results, trendsISO 9000:2015 3.8.12,4 used for devices by 21 CFR 820.35

The words overlap. The EU glossary says “the word validation is sometimes widened to incorporate the concept of qualification”.1 ICH Q7 puts the order in one sentence: “Qualification is part of validation, but the individual qualification steps alone do not constitute process validation.”2 Annex 15 defines DQ, IQ, OQ and PQ each as “documented verification”, and lists “Calibration of instrumentation” as part of IQ.3 PIC/S PI 006-⁠4 fixes its own usage: qualification for facilities, utilities, equipment and systems; validation for processes, cleaning and methods.6

So the four nest. Instruments are calibrated, equipment containing them is qualified, and processes are validated on qualified equipment. FDA’s process validation guidance says qualifying utilities and equipment includes checking they are “properly connected and calibrated”, and that these activities “necessarily precede manufacturing products at the commercial scale”.7 Verification sits at every level, as a one-off check against requirements or as routine monitoring after validation.

2Which word applies?

Table 2. Decision aid. The last three rows apply to medical devices.
You need to showWordRule
An instrument reads trueCalibration21 CFR 211.68(a) and 211.160(b)(4);8 EU GMP 3.419
Equipment is fit for useQualificationAnnex 15 sections 3 and 4;3 PI 006-⁠4 2.5.16
Lab instrument fit for useInstrument qualification, calibration within itUSP 〈1058〉;10 21 CFR 211.160(b)(4)8
A process is consistentProcess validation21 CFR 211.110(a);8 FDA guidance, section III7
Cleaning always worksCleaning validationAnnex 15 10.13
This campaign is cleanCleaning verificationAnnex 15 glossary and 10.33
Your own method worksMethod validation21 CFR 211.165(e);8 ICH Q2(R2) 1.1 and 1.2;11 EU GMP 6.1512
A USP method works hereMethod verification21 CFR 211.194(a)(2);8 USP 〈1226〉;13 EU GMP 6.1512
Process stays in controlContinued process verificationAnnex 15 glossary;3 FDA guidance, Stage 37
Software fits its useValidation, with the infrastructure qualifiedAnnex 11 principle14
Design meets its inputsDesign verificationISO 13485 7.3.6;15 ISO 9000 3.8.124
Device meets user needsDesign validationISO 13485 7.3.7;15 ISO 9000 3.8.134
Output can’t be checkedProcess validationISO 13485 7.5.6;15 former 21 CFR 820.75(a)16

In the laboratory, ICH Q2(R2) says validation shows a procedure “is fit for the intended purpose”.11 A laboratory running a compendial procedure for the first time verifies it under USP 〈1226〉, assessing selected performance characteristics “rather than repeating the validation process”; EU GMP 6.15 asks the same of any method a laboratory did not validate.13,12 For a balance, pH meter or HPLC, USP 〈1058〉 lists qualification, calibration, validation and maintenance as ways to show an instrument “is qualified and under control”, in one approach based on risk assessment.10 More in USP 1058, ICH Q2(R2) and method verification and transfer.

For devices, 21 CFR 820.3 uses ISO 9000’s definitions.5 Verification confirms, through objective evidence, that specified requirements “have been fulfilled”; validation confirms that the requirements “for a specific intended use or application have been fulfilled”.4 So, for example, bench tests showing an infusion pump delivers its specified flow rate are design verification; a simulated-use study showing nurses can run it as intended is design validation. FDA’s inspection programme maps the two to ISO 13485 clauses 7.3.6 and 7.3.7, and process validation to 7.5.6,15 which FDA already cites: in July 2026 it found a firm’s validation work instruction “does not include all the requirements found within sections a) through g) of Clause 7.5.6”.17 More in ISO 13485 vs 21 CFR 820.

3Example: one calibration failure on one dryer.

This example is invented: the equipment, batches and results are illustrative. Drying on fluid bed dryer FBD-⁠2 is validated at an inlet air temperature of 55 to 70 °C. The batch record sets operating limits of 56 to 69 °C, a guard band of 1.0 °C at each end, twice the ±0.5 °C tolerance of probe TE-⁠201, so a probe within tolerance cannot put product outside the validated range.

Table 3. Example. TE-⁠201 as found on 9 October 2026. After adjustment, point 1 read 55.1 °C, an error of +0.1 °C.
PointReferenceAs foundErrorWithin ±0.5 °C
155.0 °C55.7 °C+0.7 °CNo
262.5 °C62.8 °C+0.3 °CYes
370.0 °C70.2 °C+0.2 °CYes

The impact assessment, step by step:

  1. Assume the worst interval. Nothing shows when the drift began, so the +0.7 °C error is assumed to apply to all 23 batches dried since the last passing calibration, on 10 April 2026.
  2. Work out what the error can hide. The probe reads high at the low end, so the true temperature was about 0.7 °C below the display. A display of 56.0 °C, the lower operating limit, was really about 55.3 °C, still inside the validated range. Only a display below 55.7 °C can mean a true temperature below 55 °C. The high end was within tolerance.
  3. Check each batch’s record. The inlet temperature trends show 22 batches never displayed below 56.0 °C. Batch 26-⁠031 alarmed at 55.6 °C for 4 minutes on 2 July 2026; deviation DEV-⁠26-⁠118 closed it then as within the validated range. Its true minimum was about 54.9 °C.
  4. Weigh the product evidence. Batch 26-⁠031’s in-process loss on drying was 1.8% against a limit of not more than 2.0%.
  5. Conclude. QA reopened DEV-⁠26-⁠118: about 4 minutes near 54.9 °C, a drying result within limit and passing release tests supported no impact on batch 26-⁠031, and the record says so. The other 22 batches need no action.
  6. Prevent a repeat. TE-⁠201 had drifted out of tolerance within six months, so its calibration interval in the written programme was shortened to three.8

How a programme handles out-of-tolerance results is in calibration programmes.

4Where the words trip people up.

Calibration that misses the range of use. ICH Q7 defines calibration as a comparison with a reference standard “over an appropriate range of measurements”.2 A current certificate is not enough if its points don’t cover the validated setpoints:

“Heat sealer numbers 19-⁠11821 and 23-⁠70915 are only calibrated for time at 5 seconds and 10 seconds, but the nominal setpoint is 3 seconds … There is no documented justification on why this calibration is acceptable to demonstrate accuracy at the validated setpoint” Olympus Medical Systems Corporation, warning letter, 7 October 202618

System suitability taken for verification.

“In your response, you stated that all testing methods are verified under actual conditions by meeting the system suitability requirements mentioned in the method. Your response is inadequate. System suitability is not a substitute for method verification.” International Trading Pharm Lab Inc, warning letter, 24 April 202019

A change called too small to requalify. The label a firm gives a change does not decide whether it needs qualification:

“Your firm determined that qualification or validation is not required, though the DCO describes the change category as Major.” IsoTis OrthoBiologics, Inc., warning letter, 24 February 202620

The same letter records that its Director of Quality Systems and Assurance “considered the demineralization press to be a tool and not equipment”.20

Cleaning verified until it is validated. Annex 15 accepts verification as a stopgap: “validation with verification after each batch may be required for some products, e.g. investigational medicinal products.” Verification cannot stand in for a procedure that fails, though: “Repeated cleaning and retesting until acceptable residue results are obtained is not considered an acceptable approach.”3

Qualified assays in early development. For gene therapy INDs, FDA says “Validation of analytical procedures is usually not required for original IND submissions for Phase 1 studies”, but asks for safety and dose assays to be qualified before clinical use, and to “validate tests used to determine dose prior to initiating clinical studies to support licensure”.21

Commissioning and ASTM E2500. Neither Annex 15 nor PI 006-⁠4 uses the word commissioning, but PI 006-⁠4 accepts other approaches, naming ASTM E2500,6 a guide to “Specification, Design, and Verification” that shows systems are fit for use, “for example, qualified”.22 There, verification does the work qualification does in Annex 15.

5What changed in 2026.

  • Devices. Since 2 February 2026, 21 CFR 820.3 takes its definitions from ISO 13485 and Clause 3 of ISO 9000; FDA found its own definitions of design validation and process validation unnecessary.5,23 ISO 9000:2026 replaced the 2015 edition in May 2026,24 but 21 CFR 820.7 still incorporates the 2015 Clause 3, so US device law uses its definitions.5
  • Software. FDA’s computer software assurance guidance, reissued on 3 February 2026, supersedes section 6 of the 2002 software validation guidance,25 whose distinction stands: verification checks each phase’s outputs against its requirements; validation confirms the specifications “conform to user needs and intended uses”.26
  • PIC/S. PI 006-⁠4 replaced the 2007 recommendations on 1 October 2026.6

6How it runs in Seal.

In Seal’s commissioning and qualification blueprint, each requirement links to the test that proves it, and test equipment carries its calibration range, status, due date and standards traceability. Because that eligibility is recorded against each execution, a later calibration failure identifies the tests recorded as using the instrument and opens an impact assessment. The calibration management blueprint keeps each point’s as-found and as-left observations, procedure and reference standard, and links the event to the recorded uses of the instrument, so an out-of-tolerance result opens an assessment of the work it may affect.

The process validation blueprint runs PPQ protocols on the same platform as manufacturing, testing and quality, and carries the reviewed controls and residual risks into continued process verification.

AQuestions and answers

Is qualification part of validation?

Yes. ICH Q7 calls qualification part of validation, but says the qualification steps alone don’t amount to process validation. The EU glossary notes that the word validation is sometimes widened to include qualification.

Does validation or verification come first?

It depends on what is being proved. In software and device design, verification of each phase comes first and supports the final conclusion that the product is validated. In process validation, the order runs the other way: the process is validated, then verified continually in routine production. For a test method, the two are alternatives: you validate your own method and verify an unmodified compendial one.

Are validation and verification the same thing?

No, although some texts use them interchangeably. FDA’s software validation guidance notes that the device quality system regulation was harmonised with ISO 8402:1994, which treats them as separate and distinct terms, while many software textbooks blur them. Verification asks whether something meets its specified requirements; validation asks whether it consistently does what its intended use needs.

What is the difference between commissioning and qualification?

Commissioning usually means the engineering work of bringing equipment into service: checking it is built, installed and working as designed. Qualification is the GMP record, approved under the quality system, that it is fit for its intended use. Annex 15 lets tests done at factory acceptance or other stages count towards qualification, without repeating them on site, where that is justified and transport and installation did not affect the function tested.

What is the difference between assay qualification and assay validation?

Assay qualification shows a method is suitable for its purpose at an early stage, with data on accuracy, reproducibility, sensitivity and specificity. Validation is the full, formal demonstration expected before a method supports licensure. For gene therapy products, FDA asks for dose and safety assays to be qualified before first clinical use and dose assays to be validated before the studies that support licensure.

What is the difference between calibration and verification?

Calibration establishes the relationship between what an instrument indicates and the known values of a reference standard, at stated points, and records any error. Verification checks that the instrument meets a specified requirement, such as a balance check against a test weight before use. ISO 9000 treats both as part of metrological confirmation, which is complete only when the instrument is shown fit for its intended use. Adjusting the instrument is a separate step from either.

References26 sources

References

  1. 1EudraLex Volume 4, Glossary, European Commission. https://health.ec.europa.eu/document/download/e99884fd-2b52-470b-9453-10346ddb6cbd_en?filename=glos4en200408_en.pdf (read 9 November 2026)
  2. 2ICH Q7, Good Manufacturing Practice Guide for Active Pharmaceutical Ingredients, ICH, 10 November 2000, glossary, definitions of calibration, qualification and validation. https://database.ich.org/sites/default/files/Q7%20Guideline.pdf (read 9 November 2026)
  3. 3EudraLex Volume 4, Annex 15: Qualification and Validation, European Commission, in operation from 1 October 2015, sections 3, 4 and 10, and glossary. https://health.ec.europa.eu/system/files/2016-11/2015-10_annex15_0.pdf (read 9 November 2026)
  4. 4ISO 9000:2015, Quality management systems: Fundamentals and vocabulary, clauses 3.8.12 and 3.8.13, ISO Online Browsing Platform. https://www.iso.org/obp/ui/en/#iso:std:iso:9000:ed-4:v1:en (read 7 November 2026)
  5. 521 CFR 820.3, Definitions, and 820.7, Incorporation by reference, eCFR, up to date as of 5 November 2026. https://www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-820 (read 9 November 2026)
  6. 6PI 006-⁠4, Recommendations on Qualification and Validation, PIC/S, 1 October 2026, sections 1, 2.4, 2.5 and 4.1. https://picscheme.org/docview/11277 (read 9 November 2026)
  7. 7Process Validation: General Principles and Practices, Guidance for Industry, FDA, January 2011, sections III and IV. https://www.fda.gov/media/71021/download (read 9 November 2026)
  8. 821 CFR Part 211, sections 211.68(a), 211.110(a), 211.160(b)(4), 211.165(e) and 211.194(a)(2), eCFR, up to date as of 5 November 2026. https://www.ecfr.gov/current/title-21/chapter-I/subchapter-C/part-211 (read 9 November 2026)
  9. 9EudraLex Volume 4, Chapter 3: Premises and Equipment, European Commission, section 3.41. https://health.ec.europa.eu/document/download/18d76565-137b-41d2-a602-794527f708c1_en?filename=chapter_3.pdf (read 9 November 2026)
  10. 10General Chapter 〈1058〉 Analytical Instrument Qualification, introduction, USP–NF, United States Pharmacopeia, 2017, public preview. https://doi.usp.org/USPNF/USPNF_M1124_01_01.html (read 9 November 2026)
  11. 11ICH Q2(R2), Validation of Analytical Procedures, ICH, adopted 1 November 2023, sections 1.1 and 1.2. https://database.ich.org/sites/default/files/ICH_Q2%28R2%29_Guideline_2023_1130.pdf (read 9 November 2026)
  12. 12EudraLex Volume 4, Chapter 6: Quality Control, European Commission, in operation from 1 October 2014, section 6.15. https://health.ec.europa.eu/system/files/2016-11/2014-11_vol4_chapter_6_0.pdf (read 9 November 2026)
  13. 13General Chapter 〈1226〉 Verification of Compendial Procedures, introduction, USP–NF, United States Pharmacopeia, 2019, public preview. https://doi.usp.org/USPNF/USPNF_M870_03_01.html (read 9 November 2026)
  14. 14EudraLex Volume 4, Annex 11: Computerised Systems, European Commission, revision 1, in operation from 30 June 2011, principle. https://health.ec.europa.eu/system/files/2016-11/annex11_01-2011_en_0.pdf (read 9 November 2026)
  15. 15Compliance Program 7382.850, Inspection of Medical Device Manufacturers, FDA, implemented 2 February 2026, Attachment A. https://www.fda.gov/media/80195/download (read 9 November 2026)
  16. 1621 CFR 820.75, Process validation, eCFR, as in force on 30 January 2026. https://www.ecfr.gov/on/2026-01-30/title-21/section-820.75 (read 9 November 2026)
  17. 17Nipro Renal Solutions USA, Corporation, Warning Letter, MARCS-⁠CMS 732874, FDA, 24 July 2026. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/nipro-renal-solutions-usa-corporation-732874-07242026 (read 9 November 2026)
  18. 18Olympus Medical Systems Corporation, Warning Letter, MARCS-⁠CMS 729208, FDA, 7 October 2026. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/olympus-medical-systems-corporation-729208-10072026 (read 9 November 2026)
  19. 19International Trading Pharm Lab Inc, Warning Letter, MARCS-⁠CMS 598537, FDA, 24 April 2020. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/international-trading-pharm-lab-inc-598537-04242020 (read 9 November 2026)
  20. 20IsoTis OrthoBiologics, Inc., Warning Letter, MARCS-⁠CMS 723370, FDA, 24 February 2026. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/isotis-orthobiologics-inc-723370-02242026 (read 9 November 2026)
  21. 21Chemistry, Manufacturing, and Control (CMC) Information for Human Gene Therapy Investigational New Drug Applications (INDs), Guidance for Industry, FDA, January 2020, section V.A.4.c. https://www.fda.gov/media/113760/download (read 9 November 2026)
  22. 22ASTM E2500-⁠25, Standard Guide for Specification, Design, and Verification of Pharmaceutical and Biopharmaceutical Manufacturing Systems and Equipment: Science and Risk Based Approach, ASTM International, standard page, sections 1 and 5. https://store.astm.org/e2500-25.html (read 9 November 2026)
  23. 23Medical Devices; Quality System Regulation Amendments, final rule, FDA, Federal Register 89 FR 7496, 2 February 2024, effective 2 February 2026. https://www.federalregister.gov/documents/2024/02/02/2024-01709/medical-devices-quality-system-regulation-amendments (read 9 November 2026)
  24. 24ISO 9000:2026, Quality management: Fundamentals and vocabulary, edition 5, standard page, ISO, May 2026. https://www.iso.org/standard/9000 (read 9 November 2026)
  25. 25Computer Software Assurance for Production and Quality Management System Software, Guidance for Industry and FDA Staff, FDA, 3 February 2026, section I. https://www.fda.gov/media/188844/download (read 9 November 2026)
  26. 26General Principles of Software Validation; Final Guidance for Industry and FDA Staff, FDA, 11 January 2002, section 3.1.2. https://www.fda.gov/media/73141/download (read 9 November 2026)