1What FAT and SAT cover, and when they count toward IQ and OQ.
A factory acceptance test (FAT) is “a test conducted, usually at the vendor’s premises, to verify that the system, equipment or utility, as assembled or partially assembled, meets approved specifications”. A site acceptance test (SAT) is the same check “at the manufacturer’s site of use”.1 EU GMP Annex 15 places both after design qualification. Equipment, “especially if incorporating novel or complex technology”, may be evaluated at the vendor, and before installation it should be confirmed against the URS or functional specification there, if applicable. FAT “may be supplemented” by a SAT after the equipment is received;2 PIC/S has SAT confirm performance to the URS “when installed at the manufacturing site”.3 PIC/S expects a formally approved protocol and report for each.3
Neither replaces IQ and OQ. Results move across test by test: “Where appropriate and justified, documentation review and some tests could be performed at the FAT or other stages without the need to repeat on site at IQ/OQ if it can be shown that the functionality is not affected by the transport and installation.”2 PIC/S puts it as a smaller IQ and OQ: “FAT and SAT testing may be used with appropriate justification to reduce the required scope of IQ and OQ testing.”3
| Stage | Where | What it shows | Can its results count elsewhere? |
|---|---|---|---|
| FAT | Vendor’s works, before shipment | Build, documents and functions meet the URS and functional specification | Documentation review and tests transport and installation cannot affect, into IQ or OQ, when justified |
| SAT | Your site, once installed | Condition on arrival, installation effects, alterations agreed at FAT | Into IQ or OQ, on the same conditions |
| IQ | Your site | Installed to drawings and specifications; materials, calibration, supplier documents | Release to OQ |
| OQ | Your site | Operation as designed, upper and lower limits, worst cases | Release to PQ |
| PQ | Your site | Performance with production or equivalent materials under normal operating conditions | Annex 15 and PIC/S speak of FAT and SAT credit for IQ and OQ only |
A FAT or SAT result counts toward IQ or OQ only when all of these hold:
- A documented risk assessment justifies it. Annex 15 bases the scope and extent of qualification on “a justified and documented risk assessment”, and ICH Q9(R1) names deciding “the scope and extent of qualification” as a use of quality risk management, with effort, formality and documentation commensurate with the risk.2,
4 - The protocol was approved before it ran. Site staff should confirm a vendor’s protocol is suitable and complies with internal procedures before approval, and “Vendor protocols may be supplemented by additional documentation/test protocols before use.”2
- Controls were in place while the data were collected. Data from outside your own program “may be used provided that this approach has been justified and that there is adequate assurance that controls were in place throughout the acquisition of such data.”2 Test instruments should be identified and calibrated before use.3
- Transport and installation cannot affect it, and that is shown, test by test.2,
3 - The unit and configuration are the ones installed. IQ verifies the configuration specifications for the intended operational environment.1
- FAT deviations are closed or assessed. Deviations should be managed, with CAPA raised, before the equipment is considered fit for purpose, and SAT confirms “that any alterations made at the FAT have been completed”.3 A stage can still be released conditionally, with a documented assessment that open items have no significant impact on the next activity.2
The vendor can run the tests, but “the responsibility lies with the contract giver to ensure that the required quality standards for the work are met.”3,
2FAT and SAT checklist template.
Each row is a line in the FAT or SAT protocol, or in the assessment that carries results into IQ and OQ.
| Item | At FAT | At SAT | Source |
|---|---|---|---|
| 1. Protocol | Approved by site staff before execution; vendor protocol checked against your procedures and supplemented if needed | Approved before execution | Annex 15 2.2, 2.6; PI 006-4 4.2.3 |
| 2. Requirements | Each test traced to a URS or functional specification item | Same | Annex 15 3.2, 3.5; PI 006-4 4.2.3 |
| 3. Credit plan | Mark each test meant to count toward IQ or OQ, with why transport and installation cannot affect it | Mark tests repeated because they can | Annex 15 3.6; PI 006-4 4.1.7 |
| 4. Documents | Drawings, P&IDs, electrical and pneumatic drawings, materials of construction, manuals, spare parts list | Documents delivered match the FAT set | PI 006-4 4.2.2, 4.2.3, 4.3.1.5; WHO 10.16; Annex 15 3.9 |
| 5. Build | Components, instruments and materials against the design specification | Condition on arrival; parts match the FAT record | Annex 15 3.5; WHO Appendix 6, 7.4 |
| 6. Test instruments | Identified, calibrated, certificates in the record | Same | PI 006-4 4.3.2.3 |
| 7. Functions | Sequences, alarms, interlocks, emergency stops, recipe limits | Repeat those that depend on sensors, wiring, alignment or site utilities | Annex 15 3.6, 3.11; PI 006-4 4.2.3 |
| 8. Software | Versions, configuration, access levels, audit trail, data backup | Version and configuration unchanged since FAT, or the change assessed | WHO 10.16; PI 006-4 4.3.1.4; 21 CFR 211.68(b) |
| 9. Trial materials | Placebo or substitute sent in advance, in enough quantity for meaningful trials | Materials the protocol names | PI 006-4 4.2.3 |
| 10. Utilities | Record the vendor’s supply used for each test | Connect site utilities; repeat tests that depend on them | Annex 15 3.6, 3.9; PI 006-4 4.3.1.5 |
| 11. Training | Initial training of key operation, maintenance and validation staff | Further knowledge for site personnel | PI 006-4 4.2.3, 4.2.4 |
| 12. Deviations | Each failure recorded and investigated; fix and retest before shipment | Confirm FAT alterations are complete | Annex 15 2.8; PI 006-4 4.1.8, 4.2.4 |
| 13. Data integrity | Raw data, signatures and dates kept; results confirmed by someone not executing | Same | Annex 15 1.8; PI 006-4 3.4.3(m) |
| 14. Report | Conclusion on acceptability before shipment, formally approved | Conclusion on acceptability on receipt, formally approved | WHO Appendix 6, 7.3 and 7.5; PI 006-4 4.2.3, 4.2.4 |
| 15. Release | Credit decision per test written into the IQ and OQ protocols | Formal release to the next stage | Annex 15 2.10, 3.6 |
3How it runs in Seal.
In Seal’s commissioning and qualification workflow, supplier evidence is assessed before it is leveraged, and FAT results earn qualification credit only under an approved strategy. Seal records each result’s source, witness status, configuration, deviations, raw evidence and intended credit, so a vendor PDF is not treated as verified traceability. FAT, SAT, IQ, OQ and PQ tests capture actual values, evidence, instruments, configuration, exceptions and signatures, and stages can be combined or adapted under an approved lifecycle strategy while the intent and evidence of each test stay visible.
Coverage is calculated from the links between requirements, risks and tests, so it exposes untested requirements, orphan tests, open failures and requirements verified only in an obsolete configuration. A failed test becomes an exception on its exact requirement and step, and a retest adds new evidence without overwriting the failure.
4Example: leveraging a tablet press FAT into IQ and OQ.
Invented for illustration: a site buys a rotary tablet press, TP-07, controlled by a PLC with an HMI. A risk assessment approved on Monday 24 August 2026 marks which FAT tests can count toward IQ and OQ. Site engineering and QA approve the vendor’s protocol and witness the FAT from Monday 7 to Wednesday 9 September.
| Test group | FAT tests | Counted without repeating | Why |
|---|---|---|---|
| Documentation review | 18 | 18, into IQ | Documents do not change in transport |
| Software configuration and records | 22 | 15, into OQ | A firmware change after FAT touched 7 |
| Alarm logic in the PLC | 28 | 28, into OQ | PLC program unchanged since FAT |
| Alarm display, acknowledgment and history on the HMI | 3 | 0 | They run on the HMI, whose firmware changed |
| Sensor alarms, interlocks and emergency stops | 14 | 0 | Switches and wiring can shift in transport |
| Mechanical functions and speed ranges | 9 | 0 | Site power, utilities and leveling differ |
| Placebo runs | 4 | 0 | The vendor’s conditions, not normal operation |
| Instrument checks: 2 load cells, 1 encoder | 3 | 0 | Calibrated on site |
| Total | 101 | 61 (60.4%) |
At FAT the rear guard interlock did not stop the turret. The vendor replaced the switch bracket, the retest passed and the deviation closed before shipment; SAT confirmed the new bracket was fitted. On Monday 21 September the vendor replaced the HMI firmware tested at FAT, 3.2.0, with 3.2.1. Its release notes listed changes to audit trail export, session timeout and electronic signature, so the site withdrew credit from those 7 tests: 4 audit trail, 2 session timeout, 1 signature. It also withdrew credit from the 3 alarm display, acknowledgment and history tests, which run on the HMI whatever the release notes say. The PLC program checksum matched the FAT record, so the 28 results for alarm logic in the PLC stood.
The press arrived on Monday 5 October. SAT ran on 12 and 13 October, IQ from Wednesday 14 to Friday 16 October and OQ from Monday 19 to Friday 23 October.
| Planned without FAT credit | Counted from FAT | Run on site | |
|---|---|---|---|
| IQ | 43 | 18 (41.9%) | 25 |
| OQ | 88 | 43 (48.9%) | 45 |
| Total | 131 | 61 | 70 |
The 25 IQ checks include location, utilities, leveling, the firmware version and PLC checksum, and each product-contact part’s identity against the certificates reviewed at FAT. The 45 OQ tests are the 7 firmware-affected software tests, 3 HMI alarm tests, 14 sensor tests, 9 mechanical tests and 12 operating limits and worst cases with site utilities. The placebo runs informed PQ planning but earned no credit, since PQ uses production or equivalent materials under normal operating conditions.2 The load cells and encoder were calibrated on site, as WHO expects “unless otherwise appropriately justified”.1
5When FAT or SAT results cannot be carried over.
- Transport, installation or site utilities could change the result. Sensor and switch positions, wiring, leveling, seals and calibration: repeat the test.2,
3 - The equipment changed after FAT. Annex 15 asks that planned changes which may affect product quality be documented and their impact on the validated status assessed.2 A new firmware version or replaced part means the FAT result describes another configuration.
- It is a different unit. A sister machine’s results do not transfer by model number. For several identical pieces of equipment, the EU ATMP guidelines accept “a suitable testing strategy based on an evaluation of the risks”.6
- The vendor tested its settings, not your range. OQ should include tests to confirm “upper and lower operating limits” or worst-case conditions.2
- The evidence is thin. An unapproved vendor protocol, a summary without raw data or tests run with uncalibrated instruments give no assurance that controls were in place.2,
3 - The trial needs the active ingredient. PIC/S says “substitute products should be considered for trial runs rather than active ingredients as there may be inadequate health and safety controls at the supplier.”3
- There is no factory to test at. WHO frames FAT for equipment assembled, or partly assembled, away from the purchaser’s site.1 A system assembled on site has no FAT; its checks happen on site, in SAT, commissioning or IQ.
- A test fails. Record it as a deviation and investigate. Conditional release to the next stage needs a documented assessment that the open item has no significant impact on it.2
6What inspectors cite.
A full-text search of FDA’s warning letters, whose index reaches back to January 2021, finds none that uses the words “factory acceptance” or “site acceptance”.7 Leverage that fails shows up as failed qualification or validation.
“Only the nominal settings (232°F, 115 PSI, 4.5 seconds) showed passing results, which do not match your current production setpoints (253°F, 118 PSI, 4 seconds).”
Olympus Medical Systems Corporation, warning letter, 7 October 2026, on a tray sealer’s operational qualification at its Brooklyn Park facility, cited under the former 21 CFR 820.75(a): the letter notes the inspections, in October to December 2025, came before the Quality Management System Regulation took effect on 2 February 2026.8 The same letter found that the OQ and PQ reports offered for one sealer belonged to another, decommissioned in 2023, and that a procedure treated sealers as equivalent by model:
“This procedure allows for equipment with the same manufacturer and model number to be considered equivalent, regardless of the year purchased or any other modifications made to the sealers.”
Olympus Medical Systems Corporation, warning letter, 7 October 2026.8
“You also provide an unexecuted installation qualification (IQ) and operational qualification (OQ) for your tablet presses and mixers, and explain you plan to develop performance qualification (PQ).”
Kaylaan LLC, warning letter, 19 August 2024. FDA found the response inadequate, chiefly for lack of evidence on product impact.9 The lesson this page draws: a protocol is not evidence until it has been executed. To look up a firm’s letters, see the 483 and warning letter lookup.
7How the EU, PIC/S, WHO and FDA differ, and what is changing.
| Text | Status | FAT and SAT | Carrying results into IQ and OQ |
|---|---|---|---|
| EU GMP Annex 15, 2015 | Guideline for medicinal products; optional for active substances | 3.4 to 3.7 | Allowed where justified and transport and installation do not affect function |
| Regulation (EU) 2025/2091, Annex V | Binding for veterinary medicinal products from 16 July 2026 | IV.4, the Annex 15 text as law | Same condition |
| EU ATMP GMP guidelines, 2017 | Advanced therapy medicinal products | 10.24 | Same condition; risk-based strategy for identical units |
| PIC/S PI 006-4 | Recommendation for inspectors and industry, in force 1 October 2026 | 4.1.7, 4.2.3, 4.2.4 | “with appropriate justification” |
| WHO TRS 1019, Annex 3, 2019 | WHO GMP guideline | 10.14; Appendix 6, section 7 | Stages may be done by a supplier under written conditions |
| FDA | 21 CFR 211 subpart D; process validation guidance, 2011 | Not named | Quality unit approves the qualification plan and report |
FDA’s equipment rules ask for equipment “of appropriate design, adequate size, and suitably located” and for automatic equipment checked “according to a written program designed to assure proper performance”.5 Its process validation guidance says “It is essential that activities performed to assure proper facility design and commissioning precede PPQ”, and lets a qualification plan use risk management to set the level of effort; the quality control unit must approve the plan and report.11
ASTM E2500 calls the same work specification, design and verification. PIC/S says such approaches could also be applicable in appropriate circumstances: “Irrespective of the approach used, the intent is to show that facilities, supporting utilities, equipment or systems perform as expected and are fit for purpose.”3
What is changing:
- October 2026. PIC/S PI 006-4 replaced PI 006-3 of 25 September 2007; FAT and SAT have their own sections in it, 4.2.3 and 4.2.4.3
- July 2026. The veterinary GMP regulation began to apply, making the Annex 15 FAT and SAT text binding for veterinary medicines.10
- January 2026. EMA’s concept paper proposes extending URS, FAT and SAT to active substance manufacturers, with a draft for consultation planned for December 2026 and publication in April 2028.12
- January 2023. ICH Q9(R1), the revision of Q9, says higher uncertainty, importance or complexity may call for more formal risk management; the Annex 15 revision is to reflect it.4,
12
AQuestions and answers
What is the difference between FAT and SAT?
Where they happen and what they can show. A factory acceptance test runs at the vendor before shipment and confirms the equipment, as assembled, meets the URS and functional specification, while faults can still be put right before delivery. A site acceptance test runs at your site once the equipment is installed and confirms it performs to the URS there, including that changes agreed at FAT were made. PIC/S expects a formally approved protocol and report for each.
Is a SAT required if the FAT passed?
Not in every case. Annex 15 says FAT may be supplemented by a SAT, so there a SAT is optional. WHO expects FAT and SAT where appropriate, with the tests chosen by quality risk management. Neither requires a SAT for every item. IQ and OQ still run on site, so a SAT is worth running when it can repeat transport-sensitive tests in a form that counts toward IQ or OQ.
Who should witness a factory acceptance test?
No GMP text names the witnesses. Annex 15 asks for quality oversight over the whole validation life cycle, and data from outside your own program count only with adequate assurance that controls were in place while they were acquired. In practice your engineers witness the tests you plan to carry into IQ or OQ, QA approves the protocol and reviews the raw data, and the people who will run and maintain the equipment use the FAT for initial training.
Does FDA require factory and site acceptance tests?
Not by name. FDA’s drug GMP rules require suitable equipment and a written program of checks for automatic equipment, and its 2011 process validation guidance expects facility design and commissioning, and qualification of utilities and equipment, before process performance qualification. Using FAT and SAT results is a choice you justify in a qualification plan that the quality unit approves.
Can you run a FAT with the active ingredient?
PIC/S advises considering substitute products for FAT trial runs instead, because the vendor may lack adequate health and safety controls for the active ingredient. Send the trial materials in advance, in quantities that allow meaningful machine trials, and plan PQ on site with production or equivalent materials.
References12 sources
References
- 1Good manufacturing practices: guidelines on validation, WHO Technical Report Series No. 1019, Annex 3, sections 10.14 and 10.16, and Appendix 6, Guidelines on qualification, sections 2, 4.13, 7 and 8.4, World Health Organization, 2019. https:/
/ www. who. int/ docs/ default- source/ medicines/ norms- and- standards/ guidelines/ production/ trs1019- annex3- gmp- validation. pdf (read 25 November 2026) - 2EudraLex Volume 4, Annex 15: Qualification and Validation, Principle, General, sections 1.3, 1.7, 1.8, 2.2, 2.6, 2.8, 2.10, 3.2 to 3.11 and 3.14, European Commission, 30 March 2015, in operation since 1 October 2015. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ 2015- 10_ annex15_ 0. pdf (read 25 November 2026) - 3PI 006-4, Recommendations on Qualification and Validation, sections 1, 2.5.6, 3.4.3, 4.1, 4.2.2 to 4.2.4, 4.3.1.4, 4.3.1.5 and 4.3.2.3, PIC/S, 1 October 2026. https:/
/ picscheme. org/ docview/ 11277 (read 25 November 2026) - 4ICH Q9(R1), Quality Risk Management, sections 3 and 5.1 and Annex II.4, ICH, adopted 18 January 2023. https:/
/ database. ich. org/ sites/ default/ files/ ICH_ Q9%28R1%29_ Guideline_ Step4_ 2025_ 0115. pdf (read 25 November 2026) - 521 CFR 211.63, 211.65 and 211.68, Current Good Manufacturing Practice for Finished Pharmaceuticals, subpart D, Equipment, eCFR, up to date as of 23 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- D (read 25 November 2026) - 6Guidelines on Good Manufacturing Practice specific to Advanced Therapy Medicinal Products, EudraLex Volume 4, Part IV, sections 10.24 and 10.25, European Commission, 22 November 2017. https:/
/ health. ec. europa. eu/ system/ files/ 2017- 11/ 2017_ 11_ 22_ guidelines_ gmp_ for_ atmps_ 0. pdf (read 25 November 2026) - 7Warning letters, full-text search for “factory acceptance” and “site acceptance”, index from January 2021, FDA, 25 November 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ compliance- actions- and- activities/ warning- letters (read 25 November 2026) - 8Olympus Medical Systems Corporation, warning letter, MARCS-CMS 729208, FDA Center for Devices and Radiological Health, 7 October 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ olympus- medical- systems- corporation- 729208- 10072026 (read 25 November 2026) - 9Kaylaan LLC, warning letter, MARCS-CMS 681977, FDA, 19 August 2024. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ kaylaan- llc- 681977- 08192024 (read 25 November 2026) - 10Commission Implementing Regulation (EU) 2025/2091 laying down good manufacturing practice for veterinary medicinal products, Annex V, sections III.5 and IV.4, Official Journal of the European Union, 27 October 2025, applying from 16 July 2026. https:/
/ eur- lex. europa. eu/ eli/ reg_ impl/ 2025/ 2091/ oj/ eng (read 25 November 2026) - 11Process Validation: General Principles and Practices, guidance for industry, revision 1, section IV.C.1, FDA, January 2011. https:/
/ www. fda. gov/ media/ 71021/ download (read 25 November 2026) - 12Concept paper on the revision of the guidelines on Good Manufacturing Practice for medicinal products, Annex 15, Qualification and Validation, EMA/
INS/ GMP/ 163466/ 2026, sections 2 and 4, EMA GMP/GDP Inspectors Working Group, 19 January 2026. https:/ / picscheme. org/ docview/ 11269 (read 25 November 2026)
