1The quality risk management process, step by step.
| Step | What you do | Who, typically | What it leaves | Q9(R1) |
|---|---|---|---|---|
| 1. Initiate | Write the risk question and assumptions; gather data; set a timeline | Leader | A scoped risk question | 4.2 |
| 2. Hazard identification | Ask “What might go wrong?” from history, theory, informed opinion and stakeholders’ concerns | Team | Hazards and possible harms | 4.3 |
| 3. Risk analysis | Estimate likelihood and severity, and detectability if the tool uses it, as FMEA does | Team | Scores, with the evidence | 4.3 |
| 4. Risk evaluation | Compare against defined criteria, weighing the strength of evidence | Team | Risks ranked against the acceptance line | 4.3 |
| 5. Risk reduction | Reduce what exceeds the acceptable level; ask whether controls add new risks | Control owners | Controls with owners | 4.4 |
| 6. Risk acceptance | Decide case by case whether the residual risk is acceptable | Decision maker | The decision and who made it | 4.4 |
| 7. Communication | Share the outcome with those who act on it | Decision maker | The documented output | 4.5 |
| 8. Review | Revisit when planned or unplanned events could change the result | Decision maker | Review triggers and frequency | 4.6 |
Q9(R1) sets no durations, only “Specify a timeline” when initiating (4.2).1 The invented example below takes 65 days, 52 of them on the controls.
A hazard is “The potential source of harm”; harm includes “the damage that can occur from loss of product quality or availability”; risk is “The combination of the probability of occurrence of harm and the severity of that harm”.1
2What changed in Q9(R1).
| Area | Q9 (2005) | Q9(R1) (2023) |
|---|---|---|
| Step name | “Risk identification” (4.3, Figure 1) | “Hazard identification”, with the same definition: rename it in procedures and forms |
| Formality | “informal” processes can be acceptable | 5.1: formality “is not a binary concept” but a continuum set by uncertainty, importance and complexity; 5.2: highly structured, less structured and rule-based decisions |
| Risk acceptance | “The decision to accept risk”; could be “a passive decision in which residual risks are not specified” | “An informed decision to take a particular risk”; the passive option is deleted, so record who accepted each residual risk |
| Subjectivity | Not named | 5.3: bias, poorly defined questions and poorly designed scoring scales; 4.1: decision makers make sure it is “managed and minimized” |
| Availability | Harm already included loss of availability | 6.1: quality and manufacturing issues “are a significant cause of product availability issues”; new Annex II.9 on supply chains |
| Detectability | A factor in some tools | Detection controls “can reduce the probability of occurrence of harm” |
3Risk assessment template.
Each line traces to Q9(R1) or the PIC/S inspectors’ aide-memoire, PI 038-2 (PI).1,
| Field | What to record | At lower formality | Q9(R1) or PI |
|---|---|---|---|
| Risk question | Question, scope and assumptions; why now; the data used | One line | 4.2 |
| Formality | Level chosen and why: uncertainty, importance, complexity | One line | 5.1 |
| Team | Leader, members by function, any facilitator | Named owner | 4.1; PI 2.10 |
| Outsourced parts | Who performs and approves each part, client or contractor, under which agreement | If outsourced | 6.1(c); PI 2.10 |
| Scales | Each severity, probability and detectability level defined; the acceptance line | Not without a tool | 4.3 |
| Hazards and scores | Each hazard, its harm, its scores and the evidence for each | Conclusion in words | 5.1 |
| Discounted hazards | Hazards set aside, with the evidence | One line | PI 2.3 |
| Uncertainty | Assumptions and known gaps | One line | 4.3 |
| Controls | Each measure, owner, due date, any new risk | Parent record | 4.4 |
| Residual risk | Score after controls; who accepted it | Always | 4.4 |
| Communication | Who was told, and how | Parent record | 4.5 |
| Review | Reopening events; review frequency | Parent record | 4.6; PI 4.2 |
| Verification | Proof each control was implemented as written | Parent record | PI 4.1 |
4Example: a risk assessment for a second stopper supplier.
Invented throughout, with every name, record, date and value: Tarrowmere, a contract manufacturer (CDMO), fills Pellivane injection for its marketing authorization holder, “the client”.
| Field | Entry |
|---|---|
| Risk question | Can Supplier B’s ready-to-use stoppers be used on Pellivane 10 mg/mL vials without raising the risk to sterility, quality or supply? Assumes Supplier A’s specification. |
| Trigger | Supplier A is the only approved source, and a nine-week delay in 2026 left three weeks of stock. |
| Data | Supplier B’s specification and extractables report. |
| Formality | High: little data (uncertainty), a sterile product’s closure (importance), six functions and a filing (complexity). |
| Team | QA (leader), manufacturing, microbiology, engineering, regulatory affairs, supply chain. Each scored alone before the team reconciled. |
| Outsourced parts | Tarrowmere performed the assessment and owns it. The client’s QA approved the outcome under quality agreement QAG-07. Supplier B gave data only. |
| Discounted hazard | Stopper particulates: Supplier B’s washing and limits match Supplier A’s (comparison SC-114). |
| Uncertainty | At the start, no integrity or leachables data with this vial; where evidence is missing, P takes the higher level. |
| Not scored | Whether the change needs a variation or supplement: a filing rule, not a risk score. |
| Acceptance | Tarrowmere head of quality, 2 November 2026: two medium residual risks, accepted once every control is verified. The client’s QA countersigned. |
| Communication | Residual risks to the client’s QA and qualified person; outcome to the site quality council. The client files the change. |
| Review | After a year’s leak data and the stability data; on an integrity failure, supplier change notice or stopper complaint; otherwise at annual product review. |
| Verification | 5 November: QA confirmed each control in place as written (VAL-118, CCI-31, EXT-22, the stability protocol, the run report, the revised batch record, Supplier B’s approval). |
| Timeline | Opened 1 September 2026; team session 8 September; controls closed 30 October; accepted 2 November; verified 5 November. |
| Level | Severity (S) | Probability (P) |
|---|---|---|
| 5 | Possible loss of sterility reaching a patient | More than once a year |
| 4 | Patient harm from a chemical or physical defect | Once in 1 to 3 years |
| 3 | Batch rejection or a break in supply | Once in 3 to 10 years |
| 2 | A defect caught in-house, no patient or supply effect | Possible, not expected in 10 years |
| 1 | No effect on quality or supply | Not expected in the product’s life, shown by data |
| Hazard | Before | Control, owner, due | Evidence for P after | After |
|---|---|---|---|---|
| Closure integrity loss | 5 × 3 = 15, high | Integrity validated with Supplier B stoppers, after simulated shipping too; integrity added to stability; leak test of every unit for a year; validation and QC, 30 October | CCI-31 passed, shipping included; leak method validated, VAL-118; no shelf-life or commercial data yet | 5 × 2 = 10, medium, accepted |
| Different leachables | 4 × 3 = 12, medium | Extractables comparison; leachables added to stability; QC, 2 October | EXT-22: no new compound above threshold; stability data later, as a review trigger | 4 × 2 = 8, medium, accepted |
| Poor machinability | 3 × 3 = 9, medium | Two engineering runs on the filling line; engineering, 20 October | Rejects 0.02%, against 0.03% with Supplier A | 3 × 2 = 6, low |
| Stopper stock-out | 3 × 4 = 12, medium, with Supplier A alone | Approve Supplier B and order from both; supply chain, 30 October | Two approved sources at separate plants; both must fail at once | 3 × 2 = 6, low |
P moves only when evidence moves it: scores “should be based on an appropriate use of evidence, science and knowledge”, so on this example’s scale validation or trial data support P = 2 and only commercial data can support P = 1. Risk reduction can also “mitigate the severity”, but S stays fixed here because no control changes the harm itself.1 Leak testing at release would not support P = 2 on its own: Annex 1 wants final containers closed “by appropriately validated methods”, with integrity validation that takes shipping into account (8.21, 8.25).4
Where any part of the work is outsourced, PIC/S wants “adequate involvement and ownership of risk assessments” by the accountable staff (section 2) and “agreements in place” (2.10). In any case, “the residual risk should be communicated to the regulators and customers”;3 Q9(R1) adds that communication “need not be carried out for each and every risk acceptance” and can go “through existing channels”: here, the client’s filing.1
5How formal does a risk assessment need to be?
Q9(R1) 5.1 says the approach to formality “should be described within the quality system”, so a rule like this belongs in your SOP.1
| Situation | Approach | Q9(R1) |
|---|---|---|
| Rule already decides it | Rule-based: apply the SOP or limit, no new assessment | 5.2 |
| Routine, low importance | Lower formality: inside the change, deviation or CAPA record | 5.1 |
| Important, little doubt | Less structured: a simpler approach drawing on existing knowledge | 5.2 |
| New or complex | Higher formality: cross-functional team, recognized tool, stand-alone report | 5.1, 5.2 |
| Short of time or people | Not a reason: “Resource constraints should not be used to justify the use of lower levels of formality” | 5.11 |
| Would excuse a GMP gap | Stop: it should not justify a practice that would otherwise be unacceptable | Section 1; PI 038-2 3.173 |
6Quality risk management SOP: what it should cover.
Inspectors start by asking whether there is “a high level controlled document describing the company’s policies and approach to QRM” (PI 038-2 1.1).3 Give it these sections:
- Purpose and scope: where QRM applies, and how work is scoped, scheduled, authorized and communicated (1.5, 1.7).
- Responsibilities: senior management’s commitment and each role (1.3, 1.4).
- Method: the tools, the formality rule above, and the scoring scales with their acceptance line (1.10; Q9(R1) 4.3, 5.1, 5.3).1
- Training: QRM in GMP training, and what risk assessors learn (1.8, 1.9).
- Records and review: how risks are assessed, controlled, communicated and reviewed in management review (1.12).
- Effectiveness and change: how QRM is checked, and how the procedure itself changes (1.6, 1.11).
7Where inspectors expect to find it, and what they ask.
PI 038-2 dates from 1 January 2021 and cites Q9, so it asks nothing about subjectivity. It expects “evidence of the implementation of QRM principles” in areas including deviations, out-of-specification results, CAPA, complaints, change control, supplier qualification, validation, outsourcing, calibration, distribution and periodic review (3.4 to 3.16).3
It also checks that proactive assessments come “sufficiently early to allow appropriate risk mitigation” (2.11).3
FDA’s letters test an assessment’s reach, and whether it stands in for a fix:
“Your response is inadequate in that your risk assessment does not extend to all drug products where (b)(4) treatment was attempted …” Medical Products Laboratories, warning letter, 9 April 20265
“These risk assessments are outcome-based, focusing primarily on the absence of complaints or adverse events rather than evaluating the adequacy of your production and inspection controls. … risk assessment is being used as a substitute for corrective action rather than a complement to it.” Pine Pharmaceuticals, an outsourcing facility, warning letter, 7 August 20266
7.1What a pre-approval inspection checks.
CP 7346.832, FDA’s compliance program for pre-approval inspections (issued 29 June 2026), checks risk assessment under three of its objectives:7
- Objectives 1 and 2, readiness and conformance. Investigators confirm “that quality risk management is used to evaluate proposed changes for potential risks (e.g., hazardous impurities) and their impact on product quality”, and where impurity risks are identified they “Verify that the establishment has conducted a risk assessment for hazardous impurities”.
- Objective 4, development. They “Determine whether adequate risk assessment activities are included as part of the pharmaceutical development program”, and whether “Management is aware of residual risks”, on the initial inspection, then periodically on risk or after major changes to the quality system, management team or corporate structure.
8Is ICH Q9(R1) mandatory, and where does it stand?
Q9(R1) is “not intended to create any new expectations beyond the current regulatory requirements”.1 What binds is the rule around it.
- US: no, but the statute covers risk. FDA’s edition says it “is not binding on FDA or the public”.8 Since 2012, section 501 of the FD&C Act has said current good manufacturing practice for drugs “includes the implementation of oversight and controls over the manufacture of drugs to ensure quality, including managing the risk of” raw materials, manufacturing materials and finished products.9 21 CFR Part 211 contains neither “risk” nor “hazard”,10 so FDA cites the underlying CGMP failure. CP 7346.832 says a gap against Objective 4 “should not be cited on Form FDA 483 unless the discrepancy or the deficiency can be linked to a CGMP violation”.7
- EU: the principles, yes. Directive (EU) 2017/1572 tells manufacturers and authorities to “take into account” the detailed guidelines.11 Chapter 1 says “there must be” a quality system “incorporating Good Manufacturing Practice and Quality Risk Management” and states both principles (1.13).12 Volume 4 lists no Annex 20: Part III carries Q9(R1), in effect from 26 July 2023.13,
14 A draft Chapter 1, consulted on until 3 December 2025, adds formality, subjectivity and review, and has each site in the supply chain manage, “within its area of responsibility, any manufacturing / quality risks that could impact upon product availability”. The 2013 text stays in force.15, 13 - UK. Regulation 37(2) of the Human Medicines Regulations 2012 makes a manufacturer’s license holder comply with GMP principles and guidelines.16 MHRA lists Q9(R1) as implemented and states no UK difference.17,
18 - PIC/S. PI 038-2 calls Annex 20 “a voluntary standard” and relies mainly on “mandatory articles of Chapter 1 and Annex 15” (4.3).3 PE 009-18, dated 24 September 2026, still points to “Annex 20 or ICHQ9”.19
- WHO. TRS 981 Annex 2 (2013) is in force;20 draft QAS/26.994 was open for comment until 15 November 2026.21
- ICH. It records FDA implementing Q9(R1) on 4 May 2023; its Briefing Pack was fully revised in March and April 2026.22,
23
9How it runs in Seal.
Seal’s quality risk management blueprint links each scenario and control to its verification and to the complaints and deviations that test it. A failed verification challenges the assessment it concerns while the original observation stays intact, estimates keep their population, observation period and uncertainty, and the residual-risk decision is recorded separately. Distinct templates cover an ICH Q9 risk assessment, a process FMEA, an ISO 14971 risk file and rule-based decisions set as limits in a workflow, with the configured categories and criteria versioned so reviewers can see what an assigned value means. Neil prepares impact assessments and verification cases; your team makes the risk decision.
When you validate Seal itself, the validation and AI assurance guide sets the depth of specification and testing by the risk and complexity of the intended use, and your team owns the intended use, risk acceptance and production approval. Risk sits in Seal’s QMS alongside deviations, CAPA, change control, documents, training, audits, suppliers and complaints.
AQuestions and answers
What risk assessment tools are used in pharma?
ICH Q9(R1) lists basic methods such as flowcharts, check sheets, process maps and fishbone diagrams, then FMEA, FMECA, fault tree analysis, HACCP, HAZOP, preliminary hazard analysis, risk ranking and filtering, and statistical tools such as control charts and Pareto charts. It says no one tool fits every situation and that less formal methods can be acceptable. Choose by the risk question: FMEA for a process you understand step by step, fault tree analysis for the causes of a failure, risk ranking for comparing many different risks.
Is there an ICH Q9(R2)?
No. As of November 2026, ICH lists Q9(R1), adopted in January 2023, as the current version. ICH’s later work has been training material and questions and answers, not a new guideline.
Does ICH Q9 apply to medical devices?
Not directly. Its scope is drug substances, drug products and biological and biotechnological products. For medical devices, the standard is ISO 14971, Application of risk management to medical devices, which Q9(R1) lists among its references.
How often should a quality risk assessment be reviewed?
ICH Q9(R1) ties the frequency to the level of risk rather than setting a period. Write two kinds of review into each assessment: triggers, such as a change, a deviation, a complaint trend, an audit finding or a recall, and a periodic check, for example at the annual product review. PIC/S inspectors look for both routine and triggered review, and a risk register makes them easier to show.
References23 sources
References
- 1ICH Q9(R1), Quality Risk Management, ICH, adopted 18 January 2023, with corrections of 26 January 2023 and 15 January 2025. https:/
/ database. ich. org/ sites/ default/ files/ ICH_ Q9%28R1%29_ Guideline_ Step4_ 2025_ 0115_ 0. pdf (read 26 November 2026) - 2ICH Q9, Quality Risk Management, ICH, 9 November 2005. https:/
/ database. ich. org/ sites/ default/ files/ Q9%20Guideline. pdf (read 26 November 2026) - 3PI 038-2, Aide-Memoire: Assessment of Quality Risk Management Implementation, PIC/S, 1 January 2021. https:/
/ picscheme. org/ docview/ 3823 (read 26 November 2026) - 4EudraLex Volume 4, Annex 1, Manufacture of Sterile Medicinal Products, C(2022) 5938 final, sections 8.21 and 8.25, European Commission, 22 August 2022, fully applicable since 25 August 2024. https:/
/ health. ec. europa. eu/ document/ download/ e05af55b- 38e9- 42bf- 8495- 194bbf0b9262_ en?filename=20220825_ gmp- an1_ en_ 0. pdf (read 26 November 2026) - 5Medical Products Laboratories, Inc., warning letter 320-26-61, MARCS-CMS 721916, FDA, 9 April 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ medical- products- laboratories- inc- 721916- 04092026 (read 26 November 2026) - 6Pine Pharmaceuticals, LLC, warning letter, MARCS-CMS 728537, FDA, 7 August 2026. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ pine- pharmaceuticals- llc- 728537- 08072026 (read 26 November 2026) - 7Compliance Program 7346.832, Preapproval Inspections, Parts II and III, FDA, issued 29 June 2026. https:/
/ www. fda. gov/ media/ 193382/ download (read 26 November 2026) - 8Q9(R1) Quality Risk Management, guidance for industry, FDA, May 2023, page 1. https:/
/ www. fda. gov/ media/ 167721/ download (read 26 November 2026) - 921 U.S.C. 351, Adulterated drugs and devices, concluding provisions inserted by Public Law 112-144, section 711, 9 July 2012, United States Code, 2024 edition, govinfo. https:/
/ www. govinfo. gov/ content/ pkg/ USCODE- 2024- title21/ html/ USCODE- 2024- title21- chap9- subchapV- partA- sec351. htm (read 26 November 2026) - 1021 CFR Part 211, eCFR, text of 24 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ part- 211 (read 26 November 2026) - 11Commission Directive (EU) 2017/1572, Article 3(2), 15 September 2017. https:/
/ eur- lex. europa. eu/ legal- content/ EN/ TXT/ HTML/ ?uri=CELEX:32017L1572 (read 26 November 2026) - 12EudraLex Volume 4, Part I, Chapter 1, European Commission, in operation from 31 January 2013. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ vol4- chap1_ 2013- 01_ en_ 0. pdf (read 26 November 2026) - 13EudraLex Volume 4, European Commission. https:/
/ health. ec. europa. eu/ medicinal- products/ eudralex/ eudralex- volume- 4_ en (read 26 November 2026) - 14ICH guideline Q9 (R1), Step 5, EMA/
CHMP/ ICH/ 24235/ 2006, EMA, in effect from 26 July 2023. https:/ / health. ec. europa. eu/ document/ download/ d77ad692- 97ae- 4a5f- acfa- e853193ef6aa_ en?filename=mp_ ich_ q9guideline- ra_ en. pdf (read 26 November 2026) - 15Stakeholders’ Consultation on EudraLex Volume 4, Chapter 1, with the draft chapter, European Commission, 2025. https:/
/ health. ec. europa. eu/ consultations/ stakeholders- consultation- eudralex- volume- 4- good- manufacturing- practice- guidelines- chapter- 1_ en (read 26 November 2026) - 16The Human Medicines Regulations 2012, regulation 37. https:/
/ www. legislation. gov. uk/ uksi/ 2012/ 1916/ regulation/ 37 (read 26 November 2026) - 17International Council for Harmonisation of Technical Requirements for Pharmaceuticals for Human Use Guidelines, MHRA, updated 5 November 2026. https:/
/ www. gov. uk/ guidance/ international- council- for- harmonisation- of- technical- requirements- for- pharmaceuticals- for- human- use- guidelines (read 26 November 2026) - 18Medicines: good manufacturing practice and good distribution practice, MHRA. https:/
/ www. gov. uk/ guidance/ good- manufacturing- practice- and- good- distribution- practice (read 26 November 2026) - 19PE 009-18, Guide to Good Manufacturing Practice, Part I, Chapter 1, PIC/S, 24 September 2026. https:/
/ picscheme. org/ docview/ 11332 (read 26 November 2026) - 20WHO guidelines on quality risk management, TRS 981, Annex 2, WHO, 25 January 2013. https:/
/ www. who. int/ publications/ m/ item/ trs981- annex2 (read 26 November 2026) - 21WHO guidelines on quality risk management, draft QAS/26.994, WHO, September 2026. https:/
/ cdn. who. int/ media/ docs/ default- source/ mhp- hps/ 2026- 09- 18_ qas26_ 994_ qrm_ mna. pdf?sfvrsn=be1fb7b9_ 4 (read 26 November 2026) - 22Quality Guidelines, Q9 implementation status, ICH. https:/
/ www. ich. org/ page/ quality- guidelines (read 26 November 2026) - 23Q9(R1) Briefing Pack, ICH, fully revised March/April 2026. https:/
/ ich. org/ page/ q9r1- briefing- pack (read 26 November 2026)