Skip to main content

What is GAMP 5, and what changed in the Second Edition?

GAMP 5 is ISPE’s guide to risk-based validation of GxP computerized systems; GAMP stands for Good Automated Manufacturing Practice. It is industry guidance, not a regulation. The Second Edition, published in July 2022, keeps the 2008 framework. It renames the software categories and applies them to components, adds appendices on IT infrastructure, critical thinking, agile, software tools, blockchain and AI, retires three, and encourages exploratory and automated testing. Adopting it requires no revalidation: apply it at each system’s next review.Checked against its sources on 26 November 2026. How these answers are made

Illustration of a seal resting on four bound volumes, Requirements, Configuration, Verification and Change control, with a red ribbon running through them all.

1What changed in the Second Edition.

ISPE published the Second Edition in July 2022, at 404 pages.1 Its own summary says “The overall approach, framework, and key concepts remain unchanged from the first edition.”2 The technical content did change: ISPE adds new guidance on process risk assessment and says concepts of computer software assurance from FDA’s device center are “explored and applied”.2 The rest of its summary goes appendix group by appendix group; the table sets each change against the appendix whose title it matches, with every title changed since ISPE’s 2008 list.2,3,4

Table 1. Every other appendix keeps its number and title. The Second Edition’s contents mark D2, O7 and S5 “(Retired)”.4
AppendixSecond Edition titleWhat it now expects
M1, M7Validation Planning; Validation ReportingPlanning and reporting for SaaS and for agile, iterative delivery
M2Supplier AssessmentAssessment of cloud service providers and of cloud platforms and applications
M4Categories of Software and HardwareCategories applied to the components of a system; categories 3 to 5 “viewed as a continuum”; the category “just one factor in a risk-based approach”2
M5Design Review and TraceabilityAutomated, tool-based reviews and verification; automated rather than manual traceability
M6Supplier Quality Planning, was Supplier Quality and Project PlanningTitle change
M8Project Change and Configuration ManagementAgile toolsets for requirement changes, deliverables, DevOps and continuous deployment
M9Documentation and Information Management, was Document ManagementTool-based, searchable records, kept as the company’s “source of truth”2
M11IT Infrastructure, newRisk-based good practice for infrastructure on site and at IaaS, PaaS and SaaS suppliers
M12Critical Thinking, newExperts choose how to specify, test, operate and maintain a system for the business process it supports
D1Specifying Requirements, was User Requirements SpecificationsRequirements written for agile methods and captured with tools
D2Retired, was Functional SpecificationsNone
D5Testing of Computerized SystemsAssurance set by the company’s own risk; testing in any environment counts; exploratory and automated testing encouraged
D8Agile Software Development, newStandard agile processes, without duplicate linear V-model activities on top
D9Software Tools, newRisk-based use of tools for life cycle, IT and infrastructure processes that do not directly hold GxP records
D10, D11Distributed Ledger Systems (Blockchain); Artificial Intelligence and Machine Learning (AI/ML), both newFitness for use of systems built on these technologies
OIntroduction to Operation Appendices, now lettered ONone
O1HandoverHypercare, business readiness and support tools in handover
O2Establishing and Managing Support ServicesService agreements aligned with quality agreements, including contract exit
O3System Monitoring, was Performance MonitoringModern monitoring technologies
O4Incident Management and Problem Management, was Incident ManagementIncident, problem and deviation management related, using IT service management tools
O6Operational Change and Configuration ManagementHow the company’s, IT’s and external providers’ change processes relate
O7Retired, was Repair ActivityNone
O8Periodic ReviewMetrics and trends used to judge fitness for intended use
O10Business Continuity ManagementContinuity and disaster recovery linked to incident and problem management; anything as a service
O11Security ManagementIT security practice aligned with standards such as ISO 27001 and NIST
S2Electronic Production RecordsCloud and blockchain; real-time reports for review by exception; audit trail review for manufacturing systems
S3End User Applications Including SpreadsheetsMore data integrity considerations and risk-based decision recommendations
S4Patch and Update Management, was Patch ManagementTitle change
S5Retired, was Managing Quality within an Outsourced IS/IT EnvironmentM11 now covers infrastructure at external suppliers
G1, G2References and Glossary; the 2008 summary of good practice guides is goneNone

M4 keeps its title but renames the categories. GAMP 4’s “operating systems, firmware, standard software packages, configurable software packages and custom (bespoke) software” became “infrastructure software, tools and IT services, standard system components, configured components and custom applications and components”.5 Category 2, firmware, had already gone in 2008.3 What are the GAMP 5 software categories? explains each and sorts the arguable ones.

2What to update in your procedures.

GAMP 5 is guidance, so adopting the Second Edition is a choice your procedures make.6 If your computer system validation procedure cites GAMP 5, check these points.

Table 2. A gap check for a computer system validation procedure.
CheckWhat the procedure should sayBasis
CategoriesSecond Edition names; categories applied per component, never used to pick a fixed deliverable listM4; Section 12.2, quoted by ISPE5
Life cycleIterative and incremental delivery allowed, without a duplicate set of V-model documentsD8;2 draft Annex 11, 6.17
RequirementsKept current through changes, traceable to tests, held in tools where that worksAnnex 11, 4.4;8 draft Annex 11, 6.4 and 6.57
TestingUnscripted and automated testing for lower-risk functions, with what was tested and found recorded; executed scripts for high-risk functionsD5;2 21 CFR 211.68(b);9 draft Annex 11, 9.47
Supplier evidenceSupplier documentation assessed and reused, never in isolation from your configuration and use; audits set by riskAnnex 11, 3.2;8 MHRA, 6.1910
Service providersAgreements state the provider’s responsibilities, including contract exitAnnex 11, 3.1;8 O22
InfrastructureInfrastructure and cloud platforms qualified under good IT practice; provider updates assessed for their effect on GxP applicationsAnnex 11, principle;8 M11 and D911
IT changesPatches, upgrades and vendor changes made only through change controlAnnex 11, 10;8 S44
IncidentsIT incidents and problems linked to deviation managementO42
Periodic reviewDraws on incidents, problems, upgrade history, metrics and trendsAnnex 11, 11;8 O82

The Testing row needs care in the US and the EU. FDA’s computer software assurance guidance, which accepts unscripted testing for functions that are not high process risk, covers “production or the quality management system for medical devices”.12 A drug or biologic maker rests on 21 CFR 211.68(b): “The degree and frequency of input/output verification shall be based on the complexity and reliability of the computer or related system.”9 FDA’s data integrity guidance adds: “Yes, a CGMP workflow, such as creation of an electronic master production and control record (MPCR), is an intended use of a computer system to be checked through validation”.13 Neither rules out unscripted testing. Our judgment: for high-risk functions, such as release calculations and batch record logic, keep executed scripts. They meet draft Annex 11 clause 9.4 (“executed test scripts, and where relevant, screen dumps”),7 and the CSA guidance itself names scripted or hybrid testing as options for more rigor where process risk is high.12 In the EU, the 2011 Annex 11 asks for evidence of “appropriate test methods and test scenarios” (4.7) and never mentions scripts.8 The 2025 draft never mentions unscripted or exploratory testing and asks that qualification and validation follow “approved plans, protocols and test scripts” (9.7), so check the final text before an EU procedure relies on unscripted evidence.7

3Example: gap check of SOP-⁠CSV-⁠001.

This example is invented: Fernmoor Biologics and its procedure SOP-⁠CSV-⁠001, written to the 2008 edition, are illustrative.

Table 3. Invented example.
ClauseSays nowGapActionWhen
4.2 CategoriesOne category per system sets the deliverablesCategorization “is not intended to provide a checklist approach”5Categorize components with current names; scale work by riskSOP revision; each system at its next review
6.1 TestingEvery test pre-scripted, with screenshotsD5 encourages exploratory and automated testing2Unscripted testing for lower-risk functions, recorded; scripts kept for release calculationsNext change to each system
7.3 Cloud suppliersQuestionnaire onlyNo contract exit; platform updates not assessed2,11Exit terms in agreements; provider updates screened through change controlContract renewal
9.1 Periodic reviewEvery three years, checks the validation fileAnnex 11 also lists incidents, problems, upgrade history and performance8Add incident, problem and change trends to the review templateNext periodic review

4Do we need to revalidate?

Not because the guide changed: a new edition of an industry guide does not undo validation done under the first. Annex 11 keeps a system validated through controlled change and periodic evaluation “to confirm that they remain in a valid state and are compliant with GMP”.8 The draft Annex 11 gives periodic review the decision on whether “re-validation (complete or in parts) is required”.7 So apply the Second Edition to new systems now, and to existing ones at their next significant change or periodic review, recording the decision there. What does trigger work is change: a supplier release, a platform update or a reconfiguration goes through change control whichever edition your procedure cites.8

5How inspectors approach it.

PIC/S guidance written for inspectors says what they look for: “Inspectors will be interested in the company’s approach to identifying GxP risks and the criteria for assessing the fitness for purpose of the system application.”14 The 2025 draft Annex 11 does not mention GAMP, and FDA’s CSA guidance names the Second Edition only as one industry resource.7,12

FDA drug letters cite the regulation instead. In April 2026 FDA wrote to Ava Inc. under 21 CFR 211.68(b):

You also state a software update allowed users to bypass “User-⁠Security Access Restrictions” and that you have disabled the automatic software update function.

FDA called the response inadequate and asked for an independent assessment of each laboratory system’s “qualification/validation status” and “change management, and management oversight”.15 An update is a change, whichever appendix covers it. The software categories page has more letters.

UK law keeps EU GMP guidelines as they applied at the end of 2020 unless MHRA publishes replacements, so a final revised Annex 11 would not apply there by itself.16 MHRA adds that “the acceptance of vendor-supplied validation data in isolation of system configuration and users intended use is not acceptable”.10

6What has happened since 2022.

DateWhat happenedStatus
7 Jul to 7 Oct 2025The European Commission consulted on a revised Annex 11, a revised Chapter 4 and a new Annex 22 on AI17Draft
July 2025ISPE published its GAMP Guide: Artificial Intelligence, 290 pages, for use alongside the Second Edition18Industry guide
2 Feb 2026FDA’s Quality Management System Regulation took effect, removing 21 CFR 820.70 and incorporating ISO 13485 by reference12Regulation
3 Feb 2026FDA reissued its CSA guidance for device production and quality system software under the new regulation12Final guidance
Q4 2026Target of EMA’s GMP/GDP Inspectors Working Group for final Annex 11 and Annex 22 texts19Planned

Until a final text is published and comes into operation, the 2011 Annex 11 applies, and EudraLex still lists that revision.20 CSA compared with CSV and the Annex 11 revision go further.

7What GAMP 5 is.

GAMP stands for Good Automated Manufacturing Practice.6 It began as a supplier guide from the UK’s Pharmaceutical Industry Systems Validation Forum, and the GAMP Forum is now sponsored by ISPE.14 GAMP 4 dates from 2001,14 the first edition of GAMP 5 from 20083 and the Second Edition from 2022.1 ISPE says GAMP “does not define a prescriptive method or a standard”.6 Computer system validation and Part 11 compared with Annex 11 cover the regulations themselves.

8How it runs in Seal.

Seal’s validation and AI assurance guide sets out how it applies GAMP 5, Second Edition. Requirements and specifications, the URS, FS, DS and configuration specification, can be kept as controlled records linked to the configured process and its tests, and assurance is assessed at three boundaries: the managed platform, your configured process, and custom logic and connected systems. Your team owns the intended use, risk acceptance and production approval. For the managed platform, request Seal’s development, verification and release evidence.

The computer system assurance blueprint follows one configured system from intended use and function-level risk through supplier evidence, scripted and exploratory testing, release against a configuration baseline and later change.

AQuestions and answers

Is there a free PDF of GAMP 5 Second Edition?

Not from ISPE, which sells it as a digital edition: on 26 November 2026 its page listed US$540 for members and US$1,125 for non-members, with half off the member price for members in emerging economies. The table of contents is free on ISPE’s site and lists every chapter and appendix.

Is GAMP 5 mandatory?

No. ISPE says GAMP does not define a prescriptive method or a standard. The obligations come from regulations and GMP guidelines such as the US CGMP rules, 21 CFR Part 11 and EU GMP Annex 11, which require systems validated for their intended use; Annex 11 also bases the extent of validation on a documented risk assessment. Following GAMP 5 is one way to meet them, not a requirement in itself.

What does GAMP stand for?

Good Automated Manufacturing Practice. It began as the GAMP Supplier Guide, written by a UK industry forum of pharmaceutical validation specialists; the GAMP Forum is now sponsored by ISPE. The current guide’s full title is GAMP 5: A Risk-⁠Based Approach to Compliant GxP Computerized Systems.

Does GAMP 5 Second Edition still use the V-model?

Its specification and verification approach remains, but ISPE says it is not inherently linear and fully supports iterative and incremental methods. The new agile appendix shows how to use standard agile processes for GxP software and does not advocate adding duplicate V-model activities on top.

What is the difference between GAMP 4 and GAMP 5?

GAMP 4 was published in 2001 and GAMP 5 in 2008. ISPE’s 2008 summary says GAMP 5 widened the life cycle to every phase from concept to retirement, scaled work by risk, complexity and novelty, introduced the process owner, system owner and subject matter expert roles, and leaned on supplier documentation to avoid duplicated work, while staying compatible with GAMP 4’s principles.

References20 sources

References

  1. 1ISPE GAMP 5 Guide: A Risk-⁠Based Approach to Compliant GxP Computerized Systems, Second Edition, ISPE, July 2022. https://ispe.org/publications/guidance-documents/gamp-5-guide-2nd-edition (read 26 November 2026)
  2. 2What You Need to Know About GAMP 5 Guide, 2nd Edition, Pharmaceutical Engineering, ISPE, January/February 2023, sections on management, development, operation and special interest appendices. https://ispe.org/pharmaceutical-engineering/january-february-2023/what-you-need-know-about-gampr-5-guide-2nd-edition (read 26 November 2026)
  3. 3GAMP 4 to GAMP 5 Summary, ISPE, 2008, published through Accuris (formerly Techstreet), sections 4 and 5. https://images.techstreet.com/direct/tocs/ISPE/ISPE_GAMP_4-5_sum.pdf (read 26 November 2026)
  4. 4ISPE GAMP 5 Guide, Second Edition, table of contents, ISPE, 2022. https://ispe.org/sites/default/files/publications/guidance-documents/2022-TOC/ISPE-GAMP5-Ed2_TOC.pdf (read 26 November 2026)
  5. 5When Is a Category Not a Category?, Pharmaceutical Engineering, ISPE, January/February 2026. https://ispe.org/pharmaceutical-engineering/january-february-2026/when-category-not-category (read 26 November 2026)
  6. 6What is GAMP?, ISPE. https://ispe.org/initiatives/regulatory/what-gamp (read 26 November 2026)
  7. 7Annex 11: Computerised Systems, draft for consultation, European Commission and PIC/S, July 2025, clauses 6.1, 6.4, 6.5, 9.4, 9.7 and 14.1. https://health.ec.europa.eu/document/download/40231f18-e564-4043-94de-c031f813d38b_en?filename=mp_vol4_chap4_annex11_consultation_guideline_en.pdf (read 26 November 2026)
  8. 8EudraLex Volume 4, Annex 11: Computerised Systems, revision 1, European Commission, in operation from 30 June 2011, principle and sections 3, 4.4, 4.7, 10 and 11. https://health.ec.europa.eu/system/files/2016-11/annex11_01-2011_en_0.pdf (read 26 November 2026)
  9. 921 CFR 211.68, Automatic, mechanical, and electronic equipment, eCFR. https://www.ecfr.gov/current/title-21/chapter-I/subchapter-C/part-211/subpart-D/section-211.68 (read 26 November 2026)
  10. 10‘GXP’ Data Integrity Guidance and Definitions, Revision 1, MHRA, March 2018, section 6.19. https://assets.publishing.service.gov.uk/media/5aa2b9ede5274a3e391e37f3/MHRA_GxP_data_integrity_guide_March_edited_Final.pdf (read 26 November 2026)
  11. 11Continuous Operational Control of PaaS in GxP Environments, Pharmaceutical Engineering, ISPE, July/August 2026. https://ispe.org/index.php/pharmaceutical-engineering/july-august-2026/continuous-operational-control-paas-gxp-environments (read 26 November 2026)
  12. 12Computer Software Assurance for Production and Quality Management System Software, Guidance for Industry and FDA Staff, FDA, 3 February 2026, sections I, III and V, footnotes 3 and 25, and guidance history. https://www.fda.gov/media/188844/download (read 26 November 2026)
  13. 13Data Integrity and Compliance With Drug CGMP: Questions and Answers, Guidance for Industry, FDA, December 2018, question 3. https://www.fda.gov/media/119267/download (read 26 November 2026)
  14. 14PI 011-⁠3, Good Practices for Computerised Systems in Regulated “GXP” Environments, PIC/S, 25 September 2007, sections 4.7 and 15.2 and references. https://picscheme.org/docview/3444 (read 26 November 2026)
  15. 15Warning letter 320-⁠26-⁠64 to Ava Inc., MARCS-⁠CMS 721180, FDA, 14 April 2026. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/ava-inc-721180-04142026 (read 26 November 2026)
  16. 16The Human Medicines Regulations 2012, regulation C17, legislation.gov.uk. https://www.legislation.gov.uk/uksi/2012/1916/regulation/C17 (read 26 November 2026)
  17. 17Stakeholders’ Consultation on EudraLex Volume 4, Good Manufacturing Practice Guidelines: Chapter 4, Annex 11 and New Annex 22, European Commission, July 2025. https://health.ec.europa.eu/consultations/stakeholders-consultation-eudralex-volume-4-good-manufacturing-practice-guidelines-chapter-4-annex_en (read 26 November 2026)
  18. 18ISPE GAMP Guide: Artificial Intelligence, ISPE, July 2025. https://ispe.org/publications/guidance-documents/gamp-guide-artificial-intelligence (read 26 November 2026)
  19. 19The 3-year work plan for the Inspectors Working Group, January 2026 to December 2028, European Medicines Agency, 2026. https://www.ema.europa.eu/en/documents/other/3-year-work-plan-inspectors-working-group_en.pdf (read 26 November 2026)
  20. 20EudraLex Volume 4, Good Manufacturing Practice guidelines, European Commission. https://health.ec.europa.eu/medicinal-products/eudralex/eudralex-volume-4_en (read 26 November 2026)

See your process in Seal.

Bring a procedure or a recurring problem. See how your team configures it with Neil and improves the next run.