1What technology transfer is.
In ICH Q10, the goal of technology transfer is “to transfer product and process knowledge between development and manufacturing, and within or between manufacturing sites to achieve product realisation”.1 WHO’s 2022 guideline, Annex 4 of Technical Report Series No. 1044, defines it as “a logical procedure that controls the transfer of any product or process, including product or process knowledge, together with its documentation and professional expertise”, from a sending unit (SU) to a receiving unit (RU).2
It covers moves from development to production and between sites, before or after marketing authorization. WHO calls a transfer between sites of one group of companies intracompany, and one “between the sites of different companies”, such as to a CDMO, intercompany. The rigor should be “commensurate with the respective product life cycle phase”, and the project should end with “documented evidence that the RU can routinely reproduce the transferred product, process or procedure against a predefined set of specifications, as agreed between the SU and RU”.2
2Tech transfer protocol template.
WHO section 7.1 lists the protocol’s minimum content; the other rows come from the clauses cited.2,
| Section | What to write | Source |
|---|---|---|
| 1. Purpose and scope | Title, objective, and what is and is not transferred: strengths, process steps, methods, packaging | WHO 7.1 |
| 2. Units | Names and addresses of the SU and RU, and the marketing authorization holder | WHO 7.1, 5.3 |
| 3. Team | Key people from both units and their responsibilities, both quality units included | WHO 7.1, 4.3, 5.6 |
| 4. Agreements | The signed agreement and each party’s duties before, during and after transfer | WHO 5.2 |
| 5. Phases and timing | Activities, deliverables, owners and approximate dates, including trial and validation batches | WHO 7.1 |
| 6. Knowledge package | Starting materials (below), process maps, master batch record, hold times, validation reports, stability data | WHO 12.11 to 12.18 |
| 7. Site comparison | Premises, equipment by make, model, working principle and capacity, batch sizes, materials, procedures and methods, side by side | WHO 7.1, 9.2, 9.5 |
| 8. Gaps and risks | References to the gap analysis and risk assessments, and the action each gap needs | WHO 7.1, 12.8 |
| 9. Control strategy | CQAs, CPPs, in-process controls, specifications, sampling plans | WHO 12.10 |
| 10. Qualification | Equipment IQ and OQ, room qualification, cleaning validation, process and method validation plans | WHO 5.13, 7.1, 10 |
| 11. Analytical transfer | Each method, its approach and acceptance criteria based on the current validation | WHO 12.24, 12.25; EU GMP 6.37 to 6.41 |
| 12. Cleaning | Cleanability, solubility, health-based exposure limits, residue limits and their rationale | WHO 12.38 to 12.41 |
| 13. Training | Topics, trainees and how effectiveness is checked | WHO 5.14 |
| 14. Changes, deviations | The change control and deviation procedures that apply during transfer | WHO 5.15, 12.43; ICH Q10 |
| 15. Acceptance criteria | Measurable criteria for a successful transfer, fixed before execution | WHO 5.16, 7.1 |
| 16. Regulatory route | The filing each market needs, any agreed protocol, and when product made at the RU can ship | WHO 12.21; 21 CFR 314.70, 601.12; EU variations |
| 17. Report and close-out | Report content, who authorizes it, stability and commitments still open | WHO 7.3, 12.42 to 12.46 |
The quality agreement page covers row 4.
2.1Tech transfer report: what it contains.
WHO and EU GMP expect the report to give:2,
- the scope, the critical parameters as obtained at the SU and RU, and the conclusions (WHO 7.3);
- each change, deviation and investigation with its action (7.3), assessed before close-out (12.46);
- each analytical method’s comparative outcome and any revalidation needed (EU GMP 6.40);
- what the close-out review keeps open, such as stability studies and post-marketing commitments (WHO 12.42);
- an assessment of the data, a conclusion and whether the transfer is complete, authorized by the responsible people (12.46).
2.2Starting materials: what the sending unit hands over.
For the API and excipients, WHO expects the SU to hand over their specifications and critical material attributes, which stay as they were unless a planned change has the approval it needs (12.11), the open part of the drug master file or equivalent information (12.12), and storage and distribution requirements (12.16). Its Appendix 1 adds the product development report, stability and forced stability data and supplier qualification.2 Analytical methods move under their own protocol, checked against the marketing authorization first (EU GMP 6.37 to 6.41); method validation, verification and transfer has the detail.3
3The steps of a tech transfer.
WHO suggests four phases.2
- Initiation. Due diligence and a gap analysis, with visits to both units, establish whether the RU has the expertise and technology.
- Planning. The marketing authorization holder, SU and RU form a joint team, which assesses risks, writes the protocol and builds the control strategy; the SU hands over its knowledge package.
- Execution. The RU resolves differences in facilities and capabilities, writes its own procedures and training plan, fixes critical steps such as hold times and end points, implements the analytical procedures before it tests validation samples, and designs site-specific cleaning and stability work.
- Review and close-out. The team checks results against the protocol, statistically where possible, and issues the transfer report.
4Example: Quellotin moves to Fenmoor.
In this invented example, Quellotin 20 mg/mL injection, an aseptically filled solution in 10R vials with a US NDA and an EU marketing authorization, moves from its contract manufacturer (the SU) to the Fenmoor fill suite (the RU), authorized in the EU for aseptic filling. Protocol TT-26-004 was approved on 12 January 2026. The site comparison found five differences.
| Item | SU | RU | Gap and action |
|---|---|---|---|
| Batch size | 60 L | 120 L | Twice the scale; mixing study at 120 L |
| Compounding vessel | 80 L, top-entry impeller | 150 L, bottom magnetic mixer | Different working principle; mixing time study with top and bottom assay samples |
| Bulk hold | Validated to 24 h | Planned 30 h | 6 h beyond the validated hold; schedule changed to 18 h or less |
| Sterilizing filter | 0.2 µm PES, 10 inch | Same grade, new housing | Integrity test limits confirmed; PUPSIT under Annex 1 |
| Assay method | HPLC, version 5 | Version 5, new laboratory | Comparative testing on three lots |
The RU agreed the analytical criteria before testing: mean assay within 2.0 percentage points of the SU, and impurity B within 0.05 points. On lots 25-118, 25-121 and 25-124, the SU’s last three batches, the SU found 100.4%, 99.8% and 100.1% (mean 100.1%) and the RU 99.7%, 99.5% and 99.2% (mean 99.47%), a difference of 0.63 points. Impurity B averaged 0.11% at the SU and 0.14% at the RU, a difference of 0.03 points. Both passed.
Three validation batches followed, 26-011, 26-014 and 26-017, with assays of 99.6%, 100.3% and 99.9% against a 95.0 to 105.0% specification. The protocol also required their mean to fall within 2.0 points of the SU’s last three batches: 99.93% against 100.1%, a difference of 0.17 points.
Fenmoor’s aseptic suite already fills approved products in 10R vials and had a satisfactory FDA inspection of that operation, so the move, the new mixer and the scale-up went to FDA as one CBE-30, the most restrictive of their categories. A scale-up extending total processing, bulk hold included, more than 50 percent beyond the validated limits would have needed prior approval.4 In the EU the new site was Type IB under Q.II.b.1(e). The scale-up failed Type IA condition 2 of Q.II.b.4, which a sterile injection cannot meet. The new mixer failed condition 2 of Q.II.b.3, which a sterile product meets only for a process parameter already assessed as non-critical. Both went as “Type IB by default”, grouped with the site change.5
Report TR-26-004 was authorized on 2 June 2026, 141 days after the protocol. It left open stability on the three validation batches and data on the next two production batches, which the EU guideline expects on request.5
4.1Validation batches at the receiving site.
How many PPQ batches covers the count. EU GMP Annex 15 adds three points for transfers.6
- Bracketing. A product moved between or within sites may use bracketing to reduce validation batches, if “existing product knowledge, including the content of the previous validation” is available (5.5).
- Legacy products. The process and controls “must comply with the marketing authorisation and meet current standards for marketing authorisation for that product type”, with variations filed if necessary (5.6).
- Who makes the batches. Development or site transfer staff may take part, but “It is expected that production personnel are involved” (5.11).
5How a site change is filed in the US, EU and UK.
For a US NDA, 21 CFR 314.70 sorts changes by their potential for an adverse effect into three tiers: a prior approval supplement, after which product ships only once FDA approves; a CBE-30 supplement, filed at least 30 days before distribution; and the annual report.7 FDA’s 2004 guidance applies these tiers to site changes (table below).4 A comparability protocol approved in advance “may subsequently justify a reduced reporting category” (314.70(e)),7 but seldom below CBE-30 for a site: moves to a different facility “generally do not justify a reporting category other than a PAS or CBE-30 supplement”.8 CBE-30 vs PAS compares the tiers and protocols.
In the EU, Delegated Regulation (EU) 2024/1701 amended the Variations Regulation from 1 January 2025, and the Commission’s new classification guidelines apply from 15 January 2026.9,
| Site change | FDA | EU, from 15 January 2026 |
|---|---|---|
| Finished product making | CBE-30 | Type IB |
| Modified release | Prior approval supplement, with some modified-release exceptions | Type IB, or Type II for a novel or complex process |
| New aseptic area | Prior approval supplement | Type IB, or Type II for a novel or complex process |
| Site not yet inspected | Prior approval supplement | Type II where the site needs an initial or product-specific GMP inspection |
| Biological product | Prior approval supplement under a BLA | Finished product: Type IB with three batches from both sites, unless Type II applies. Active substance: Type II (Q.I.a.1(d)) |
A new aseptic area, in FDA’s sense, is a newly built or refurbished one, or one that makes no similar approved products in the same container types and sizes; otherwise the move is CBE-30.4
5.1Biologics: the site is part of the process.
For a BLA, 21 CFR 601.12(b) requires a prior approval supplement for a change in facilities with a substantial potential for adverse effect.10 FDA’s June 2021 guidance, which covers cell and gene therapies and vaccines among others, puts “Addition or replacement of a manufacturing facility for production of Drug Substance, Drug Product or intermediates” in that category.11 For the specified products of 601.2(a), such as monoclonal antibodies for in vivo use, FDA’s July 1997 guidance lists as major a change of site, “addition of a new location, or contracting of a manufacturing step”.12,
The evidence is comparability: under ICH Q5E, comparable means “highly similar”, not identical, with no adverse impact on safety or efficacy.15 In the EU, a batch size change that needs a comparability assessment is Type II (Q.II.b.4(c)).5
5.2The UK.
The UK has implemented Regulation 2024/1701, and MHRA applies the EU’s new guidelines from 15 January 2026. Its guidance says “MHRA must approve Type IB changes before they are implemented”, within 30 days of having the documents.16
6What inspectors ask before approval.
For NDAs and ANDAs, FDA’s Compliance Program 7346.832, issued on 29 June 2026, covers objectives 1a and 2 on every PAI, and objective 4 on the initial PAI and then periodically by risk.17
- Conformance (objective 2). Investigators check that the formulation, methods and batch records match the application’s CMC section, including “the proposed commercial-scale process”.
- Development deviations (objective 1a). The examples include “Discrepancies found while conducting the method validation (particularly issues that may have occurred in its final stages) or technical transfer.”
- Development oversight (objective 4). Investigators determine “whether there is quality assurance oversight in product development, scale-up, and technology transfer, thus ensuring development processes and procedures are implementable at the commercial scale”.
- Form FDA 483 findings. A facility, equipment or operation unsuitable for commercial manufacture “may result from inadequate development, scale-up, or technology transfer activities”.
Validation at the receiving site need not be finished by the inspection. “A withhold recommendation will not be made for the approval of NDAs and ANDAs solely for a lack of complete commercial-scale process validation at the time of a PAI”, but the firm “must achieve a high degree of assurance that the manufacturing process consistently produces a product that meets its quality attributes before distribution.”17
Biologics follow other programs. Under CP 7346.832M, for CDER-regulated biologics such as monoclonal antibodies, process validation data are evaluated during application assessment, and investigators verify “that all failed campaigns during the PPQ batch manufacturing were reported in the application” and review “discrepancies in the method validation or technical transfer results from those submitted in the application”.18 CBER’s CP 7345.848, which includes cell and gene therapies, has pre-license inspectors “Verify that the manufacturing history is accurate and complete when compared to the submission”.19
Pre-approval inspection covers the rest of the program.
7What a failed transfer looks like.
FDA’s June 2021 warning letter to Novel Laboratories, trading as Lupin, in Somerset, New Jersey, cited 21 CFR 211.100(a) for products moved to a new building.20
You failed to adequately validate the manufacturing processes for temazepam 15mg and 30mg capsules before the transfer of product manufacturing to a new building. You did not adequately assess the process and equipment changes (e.g., charging order of the active pharmaceutical ingredient, different model (b)(4)) you made to your manufacturing operations, and failed to identify their impact to product quality.
Batches made with the changes were released to the US market, and several had out-
8How it runs in Seal.
Where the receiving site uses Seal, it starts from a permitted copy of the configured process as a separate draft, which keeps the steps, fields, calculations and references and none of the sign-offs. Each difference from the source, such as a different hold limit, working volume or method revision, becomes owned work with its own evidence and approval, as the technology transfer blueprint sets out. Copying the process does not approve equipment equivalence, validation or site readiness.
Neil, Seal’s AI agent, compares the sending process with the receiving site’s equipment and plan and drafts a transfer gap assessment whose findings link to their sources; the transfer team evaluates comparability and approves trial readiness. The MSAT blueprint follows the transfer through engineering batches, method transfer, training, qualification and validation, showing which knowledge was accepted, adapted, rejected or is still provisional.
AQuestions and answers
What is the difference between tech transfer and method transfer?
Method transfer moves one analytical procedure from one laboratory to another and shows the receiving laboratory gets equivalent results. Tech transfer moves the whole product or process: its knowledge, the equipment comparison, cleaning, validation and the regulatory filing. The method transfers sit inside it and finish before the receiving site tests its validation batches.
Who writes the technology transfer protocol?
A joint team from the sending and receiving units, coordinated by the marketing authorization holder where there is one. Both quality units should take part in the gap analysis, and the protocol is an authorized document. The receiving unit agrees the acceptance criteria before execution, not after it has seen the results.
Does a move between two sites of the same company need a full tech transfer?
It needs a documented transfer scaled to the risk. WHO’s guideline covers transfers between two production sites for marketed products. A move within one facility using the same equipment, procedures and people may need little beyond change control, while a move to another site usually needs comparison batches and a regulatory filing.
Does tech transfer apply to clinical trial manufacturing?
Yes, scaled to the phase. WHO’s guideline says a transfer can happen before or after marketing authorization, during development as well as commercial manufacture, with rigor commensurate with the product’s life cycle phase, and its principles may also be applied to investigational products. The elements are the same, a knowledge package, a gap analysis and agreed acceptance criteria; what grows toward commercial manufacture is the depth of comparison and validation.
How long does a tech transfer take?
No regulation sets a duration. WHO asks the protocol to give the approximate timing of key activities and scales the rigor to the product’s life cycle phase. The time is set by the longest chain: methods transferred before validation testing, the validation batches, and in the US any prior approval supplement, since product cannot ship until FDA approves it. The invented example on this page took 141 days from protocol to report, with stability still running.
Can the receiving site change the process during a transfer?
Yes, through change control. Each adjustment is assessed, documented and approved. A change to a registered detail, such as a hold time or material outside the dossier, also needs the regulatory filing its category requires. Only US annual-report changes and EU or UK Type IA changes can be distributed before they are reported.
References20 sources
References
- 1ICH Q10, Pharmaceutical Quality System, ICH, Step 4, 4 June 2008. https:/
/ database. ich. org/ sites/ default/ files/ Q10%20Guideline. pdf (read 25 November 2026) - 2WHO guidelines on technology transfer in pharmaceutical manufacturing, WHO Technical Report Series No. 1044, Annex 4, sections 1 to 5, 7, 9, 10 and 12 and Appendix 1, World Health Organization, 2022. https:/
/ cdn. who. int/ media/ docs/ default- source/ medicines/ norms- and- standards/ guidelines/ production/ trs1044- annex4- technology- transfer- in- pharmaceutical- manufacturing. pdf (read 25 November 2026) - 3EudraLex Volume 4, Part I, Chapter 6: Quality Control, sections 6.37 to 6.41, European Commission, 28 March 2014, in operation 1 October 2014. https:/
/ health. ec. europa. eu/ document/ download/ c74c8720- 27bf- 4252- 808f- d65a206a90bb_ en?filename=2014- 11_ vol4_ chapter_ 6. pdf (read 25 November 2026) - 4Guidance for Industry: Changes to an Approved NDA or ANDA, Revision 1, sections VI, VII and XII and Attachment B, FDA, April 2004. https:/
/ www. fda. gov/ media/ 71846/ download (read 25 November 2026) - 5Guidelines on the details of the various categories of variation, on the operation of the procedures and on the documentation to be submitted, C/2025/5045, sections 1, 2.2 and 4 and Annex entries Q.I.a.1, Q.II.b.1, Q.II.b.3 and Q.II.b.4, European Commission, Official Journal of the European Union, 22 September 2025. https:/
/ eur- lex. europa. eu/ legal- content/ EN/ TXT/ ?uri=OJ%3AC_ 202505045 (read 25 November 2026) - 6EudraLex Volume 4, Annex 15: Qualification and Validation, points 5.5, 5.6 and 5.11, European Commission, 30 March 2015, in operation since 1 October 2015. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ 2015- 10_ annex15_ 0. pdf (read 25 November 2026) - 721 CFR 314.70, Supplements and other changes to an approved NDA, eCFR, as of 24 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- D/ part- 314/ subpart- B/ section- 314. 70 (read 25 November 2026) - 8Comparability Protocols for Postapproval Changes to the Chemistry, Manufacturing, and Controls Information in an NDA, ANDA, or BLA, guidance for industry, FDA, October 2022. https:/
/ www. fda. gov/ media/ 162263/ download (read 25 November 2026) - 9Commission Delegated Regulation (EU) 2024/1701 of 11 March 2024 amending Regulation (EC) No 1234/2008, Official Journal of the European Union, 17 June 2024. https:/
/ eur- lex. europa. eu/ eli/ reg_ del/ 2024/ 1701/ oj/ eng (read 25 November 2026) - 1021 CFR 601.12, Changes to an approved application, eCFR, as of 24 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- F/ part- 601/ subpart- C/ section- 601. 12 (read 25 November 2026) - 11Chemistry, Manufacturing, and Controls Changes to an Approved Application: Certain Biological Products, guidance for industry, sections III and the facilities table, FDA, June 2021. https:/
/ www. fda. gov/ media/ 109615/ download (read 25 November 2026) - 1221 CFR 601.2, Applications for biologics licenses; procedures for filing, paragraph (a), eCFR, as of 24 November 2026. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- F/ part- 601/ subpart- A/ section- 601. 2 (read 25 November 2026) - 13Guidance for Industry: Changes to an Approved Application for Specified Biotechnology and Specified Synthetic Biological Products, section II, FDA, July 1997. https:/
/ www. fda. gov/ media/ 75318/ download (read 25 November 2026) - 14Manufacturing Changes and Comparability for Human Cellular and Gene Therapy Products, draft guidance for industry, section V.A, FDA (CBER), July 2023, still marked Draft on fda.gov. https:/
/ www. fda. gov/ media/ 170198/ download (read 25 November 2026) - 15ICH Q5E, Comparability of Biotechnological/
Biological Products Subject to Changes in Their Manufacturing Process, ICH, Step 4, 18 November 2004. https:/ / database. ich. org/ sites/ default/ files/ Q5E%20Guideline. pdf (read 25 November 2026) - 16Medicines: apply for a variation to your marketing authorisation, MHRA, last updated 14 October 2026. https:/
/ www. gov. uk/ guidance/ medicines- apply- for- a- variation- to- your- marketing- authorisation (read 25 November 2026) - 17Compliance Program 7346.832, Preapproval Inspections, remark 4, objectives 1a, 2 and 4, coverage table, Form FDA 483 findings and part V (exception to withhold recommendation), FDA, issued 29 June 2026, implemented 10 August 2026. https:/
/ www. fda. gov/ media/ 193382/ download (read 25 November 2026) - 18Compliance Program 7346.832M, Prelicense and Preapproval Inspections of CDER-Regulated Biological Product Manufacturers, part III, objectives 1d(a) and 1e(b), FDA, issued 14 April 2026, implemented 14 May 2026. https:/
/ www. fda. gov/ media/ 191983/ download (read 25 November 2026) - 19Compliance Program 7345.848, Inspection of Biological Drug Products (CBER), attachment 6, pre-license and pre-approval inspections, FDA, implemented 1 October 2010. https:/
/ www. fda. gov/ media/ 73834/ download (read 25 November 2026) - 20Warning Letter CMS 613385 to Novel Laboratories, Inc. d.b.a. Lupin, Somerset, New Jersey, item 2, FDA, 11 June 2021, inspection 10 September to 5 November 2020. https:/
/ www. fda. gov/ inspections- compliance- enforcement- and- criminal- investigations/ warning- letters/ novel- laboratories- inc- dba- lupin- 613385- 06112021 (read 25 November 2026)
