1What you are choosing it to prove.
A maintenance system for any factory schedules work and keeps the parts. In a GMP site the record is asked harder questions: was the work done as the procedure says, did it check that the equipment works, was the instrument right when it was used, and if it was not, what did it touch?
The rules ask for less than many checklists claim, so it pays to know which lines are law. 21 CFR 211.67 requires written cleaning and maintenance procedures with responsibilities, schedules and methods, inspection for cleanliness immediately before use, and records.1 211.182 puts cleaning, maintenance and use in an equipment log, signed by those who performed and double-checked it, and leaves out routine maintenance such as lubrication and adjustments.2 211.68(a) and 211.160(b)(4) require calibration to a written program; the second adds limits, remedial action and that an instrument outside its specifications “shall not be used”.3,
2A CMMS requirements checklist to copy.
| Requirement | The system must | Basis | Test it by |
|---|---|---|---|
| Identity | Give each asset one number that follows it when it moves | 211.105(b); 211.188(b)(2) | Moving an asset between lines, then asking for its history |
| Plans | Hold each schedule and method at a version, and ask for a reason and approval when an interval changes | 211.67(b); Annex 11, 10 | Extending a PM from 3 months to 6 |
| Function | Record a result that shows the equipment works, not only a tick | 211.67(a) | Entering a detector that misses its test piece |
| Parts and materials | Record part, lot and whether it is like for like; and which lubricants may touch product areas | 211.65(b); 211.67(b)(3) | Fitting a substitute seal |
| Calibration result | Keep the reading found, the adjustment and the reading left, by point and with limits | 211.68(a); 211.160(b)(4); EU 3.41 | Entering a failing first reading, then correcting it |
| Standards | Record the reference used and its traceability; refuse one out of date | Q7, 5.31 | Choosing an expired reference |
| Status | Show whether an instrument may be used, where it is used | Q7, 5.33 and 5.34; 211.160(b)(4); EU 3.44 | Starting a batch step with it overdue |
| Look-back | List what used it since the last good calibration | Q7, 5.35; 211.192 | The script below |
| Equipment log | Show cleaning, maintenance and use in date order, with performer and checker | 211.182; 211.68(c) | Printing one month for one asset |
| Return | Keep equipment restricted after the job until the named review is signed | 211.67(b)(6); Annex 15, 4.1 | Closing the work order, then trying to use the asset |
| Audit trail | Record who changed what, when and why, with the old value visible | 11.10(e); Annex 11, 9 | Changing a tolerance after a result |
| Access | One account for each person, contractors included, and no edit rights to plans for those who do the work | 211.68(b); 11.10(d) and (g) | Asking for a contractor’s log-in |
| Copies and retention | Give complete copies, readable for as long as the batches that relied on them | 11.10(b) and (c); 211.180 | Exporting one asset’s whole record |
ICH Q7 is written for APIs, and its paragraphs 5.30 to 5.35 put the calibration rule most plainly: traceable standards, status “known and verifiable”, failed instruments not used, and deviations investigated for impact “since the last successful calibration”.12
3Questions to put to any vendor, and what a good answer contains.
| Ask | A good answer contains | Be wary of |
|---|---|---|
| How do I find every batch that used this instrument between two dates? | A live answer from use records, by the asset and not its place | “Export both lists and compare” |
| What does a technician see when the first reading fails? | The limits for that point, no way to overwrite the reading, and what happens next | A single result field |
| What can be used while a work order is open? | A state on the asset that other systems or screens check | A colour on a dashboard |
| Who can change a tolerance or an interval, and what happens to open work? | A named role, a reason, an approval, and open work kept on the version it started on | Any planner, effective at once |
| How is overdue defined? | Due date, window and what happens at each edge, set by you, with the history of changes | A window the vendor fixes |
| How do contractors work in it? | Their own account with access to their jobs, on a phone or a kiosk, at a price you can see | One shared log-in |
| What happens with no signal in the plant room? | Which steps still work, how entries are timed and how conflicts are shown | “The network is usually fine” |
| How does it get instrument readings? | From the calibrator’s file where there is one, kept as the original, and checked entry elsewhere | Typing from a certificate with no second check |
| Show me the last release you sent. | Notes by function, test evidence, notice given and a place to try it first | “Updates are automatic” |
| How do we leave? | Every record, attachment, signature and audit trail entry, in a format you can read without the vendor, rehearsed | A PDF for each work order |
The last two are in the draft Annex 11, consulted on in 2025, which would have the contract define an exit strategy “by which the regulated user may retain control of system data”, and agree how new versions are released and your chance to test them first.15 They are easier to agree before signing.
4A demonstration script on your own records.
Pick an instrument that failed in the past three years, where you already know the answer. This one is invented; replace every value with yours.
The case. Checkweigher CW-07 at Tarnwick Biologics, tolerance ±0.03 g at 10 g. Calibrated 14 March 2026, passed. Due 14 September with a 14-day window; done on 22 September, 8 days late and inside the window. Found reading 10.08 g for a 10.00 g weight; adjusted; left reading 10.00 g. It moved from Line 3 to Line 2 on 8 June. The fill limit is 10.00 to 10.40 g.
- Load the history. Give the vendor the asset, its two positions and nine runs: seven commercial lots, a media fill and an engineering run. Watch how long it takes and what they could not load.
- Record the calibration on 22 September with an expired reference weight, then a good one. The first should be refused.
- Enter 10.08, adjust, enter 10.00. Then ask for the first reading, as a reviewer.
- Try to use CW-07. It should be restricted, and say why, wherever someone would select it.
- Ask what it touched. The right answer is nine runs, of which seven are lots, on two lines.
- Ask for the numbers. For each lot, the lowest recorded fill less the error. The table below has the answer.
- Return it to service. Close the work order as the technician. CW-07 should stay restricted until someone else signs the review, with the look-back attached.
- Change the plan. Shorten the interval to 3 months with a reason. The next due date should move and the old plan should stay on the old work.
- Print the log for March to September, and read it as an inspector would.
- Export the case, and open it on a laptop without the vendor’s software.
Time steps 3, 5, 8 and 10 with your own people at the keyboard.
| Lot | Line | Lowest fill recorded | Less the error, 0.08 g | Where the lot is |
|---|---|---|---|---|
| Lot 1 | 3 | 10.14 g | 10.06 g | Released |
| Lot 2 | 3 | 10.11 g | 10.03 g | Released |
| Lot 3 | 2 | 10.06 g | 9.98 g | Released |
| Lot 4 | 2 | 10.12 g | 10.04 g | Quarantine |
| Lot 5 | 2 | 10.09 g | 10.01 g | Quarantine |
| Lot 6 | 2 | 10.07 g | 9.99 g | In process |
| Lot 7 | 2 | 10.13 g | 10.05 g | In process |
Lots 3 and 6 could hold units under 10.00 g. Lot 6 is held and lot 3, already released, goes to investigation. 211.192 extends an investigation to other batches that may have been associated with the failure, distributed or not.8 Five are assessed and closed. The system does not decide any of that. It has to put the seven in front of QA, and the decision in the record.
5Example: scoring three suppliers.
Each criterion scores 0 to 3 and is multiplied by its weight, so the most is 300. A 0 for calibration and look-back rules a supplier out.
| Criterion | Weight | Supplier A | Supplier B | Supplier C |
|---|---|---|---|---|
| Calibration and look-back | 25 | 3 (75) | 3 (75) | 0 (0) |
| Work at the machine | 20 | 3 (60) | 1 (20) | 2 (40) |
| Restriction and return | 15 | 2 (30) | 3 (45) | 2 (30) |
| Audit trail and signatures | 15 | 2 (30) | 3 (45) | 3 (45) |
| Migration | 10 | 1 (10) | 3 (30) | 2 (20) |
| Supplier and validation | 10 | 2 (20) | 2 (20) | 2 (20) |
| Contract and exit | 5 | 1 (5) | 3 (15) | 2 (10) |
| Points | 100 | 230 | 250 | 165 |
Supplier C searched by line, found five of the seven lots and missed both from Line 3. It is out. Between A and B the points say B, and the stopwatch complicates it. A technician closed a routine PM in 4 minutes in A and 11 in B. At 3,800 PMs a year, 7 minutes is 26,600 minutes, or 443 hours, and people who lose that time find ways round the screen. The team asked B to shorten the PM form and ran it again: 6 minutes, so 127 hours against A. B was chosen on that condition, written into the order, and the decision record says so.
6Move the asset list before you sign.
Most of the work is not in the software. It is in finding out what you own. Take the legacy list, sort it once, and give a sample to each supplier to load.
| Legacy rows | Count | What happens to them |
|---|---|---|
| GMP assets, matched at a walk-round | 1,612 | Migrate with plan, last two results and due date |
| Non-GMP | 333 | Migrate without GMP controls, or leave where they are |
| Duplicates of another row | 131 | Merge, keeping both old numbers as references |
| Scrapped or not found | 64 | Archive; a deviation if a GMP plan was still open |
| Total | 2,140 | Every row has one outcome |
Annex 11 asks that migrated data are checked as not altered in value or meaning.13 Three checks catch most errors: the count by class before and after, the next due date of every critical instrument compared one by one, and a sample of old results read against the originals. Choose the cut-over so that no calibration falls due in the first week. See validating a data migration.
7The data integrity and validation work it brings.
| Work | Why | When |
|---|---|---|
| Requirements and risk assessment | Annex 11, 1 and 4.4; tests follow from what each function decides | Before choosing |
| Supplier assessment | Annex 11, 3.2 and 4.5 | Before signing |
| Configuration record: states, windows, roles, limits | Draft Annex 11, 6.6 | Before testing |
| Tests on status, look-back, limits and return | The functions that decide alone; see GAMP 5 software categories | Before use |
| Interfaces to batch records and the LIMS | Annex 11, 5: checks for correct entry and processing | Before use |
| Roles: planner, technician, reviewer, administrator | 211.68(b): changes only by authorised people | Before use, then periodically |
| Audit trail review of plans and tolerances | Annex 11, 9 | With each out-of-tolerance review, and at a set interval |
| Backup and restore | Annex 11, 7.2 | Before use, then periodically |
| Periodic evaluation | Annex 11, 11 | At a set interval |
Validating a SaaS system covers what a supplier’s package can and cannot replace.
8What FDA found.
Your preventive maintenance procedures were also inadequate, focusing only on the metal detector’s physical appearance rather than its operational functionality.
Winder Laboratories, warning letter 320-26-36, 7 January 2026. The detector did not work during the inspection and a metal screw had been found in a sealed bottle. FDA also faulted the response for not committing to a “retrospective risk assessment for batches that were processed while the metal detector was not functioning properly”, which is the look-back.16
While you had performed the preventive maintenance (PM) on these equipment pieces, the preventive maintenance activities did not identify the damage on the equipment parts
Fareva Amboise, 10 April 2026, on aseptic filling and capping lines.17 The first procedure did not ask whether the equipment worked; the second was carried out and missed the damage. Ask of each PM in the demonstration: what would this record say if the equipment did not work?
9Before you sign.
- The export from step 10, opened and read by someone who has never used the system.
- A restore of your own test data, by the supplier, with the time it took.
- The price for five years: accounts by type, contractors, interfaces, test environments, storage, validation documents, and what each becomes if your assets double.
- The release terms: notice, notes, a place to test, and how long you may wait.
- A named person at two sites of your size to ring, with two questions: what did you still keep in a spreadsheet after a year, and how long did your last look-back take?
10Scorecard template.
| Criterion | Weight | Score 0 to 3 | What we saw | Points |
|---|---|---|---|---|
| Calibration and look-back (must) | 25 | |||
| Work at the machine, with minutes timed | 20 | |||
| Restriction and return (must) | 15 | |||
| Audit trail and signatures (must) | 15 | |||
| Migration, with rows loaded and rejected | 10 | |||
| Supplier and validation | 10 | |||
| Contract and exit | 5 |
11How it runs in Seal.
Seal Maintenance runs preventive maintenance, work orders, parts and calibration on the same records as the batches, samples and qualifications each asset serves. An out-of-tolerance reading keeps the value it found beside the adjusted one, restricts the instrument and opens a review of its earlier work, and return to service is its own authorised review. You can start with one asset beside the CMMS you have.
The CMMS blueprint and the calibration management blueprint show the records, and the calibration and maintenance comparison lists what to check.
AQuestions and answers
Can a standard facility CMMS be used in a GMP plant?
Yes, if it is validated for the GMP use you make of it and its records meet the rules: one account for each person, an audit trail on results and plans, readings kept as found, copies on request and retention. Test it on an out-of-tolerance reading before deciding, because that is where general systems differ.
Why must return to service be separate from closing a work order?
Neither 21 CFR 211.67 and 211.182 nor EU GMP Chapter 3 names the signature. Closing the work order says the technician’s task is done. Whether the equipment is clean, put back as it was, still qualified and calibrated, and whether earlier batches are affected, are other people’s questions, and a separate review shows that they were asked.
Does a CMMS need to connect to batch records and LIMS?
The rules on this page do not ask for a connection. The batch record has to show the specific equipment used, and a failed calibration has to be traced to what used it. A site can do that by hand if the use records are complete and searchable by instrument; the demonstration shows how long it takes.
Can we move critical GMP instruments before replacing our corporate CMMS?
Yes. Agree which system owns the asset number, the plan and the due date for each instrument, so that no instrument is scheduled in two places, and move one class at a time. Keep the old number as a reference, because old batch records use it.
What should a CMMS demonstration include?
One failure you already know the answer to, on your own records: an expired reference refused, a failing first reading kept, the instrument restricted, every batch it touched listed, a return-to-service review by someone else, a plan change with its reason, and the whole case exported and read without the vendor’s software.
References17 sources
References
- 121 CFR 211.67, Equipment cleaning and maintenance, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- D/ section- 211. 67 (read 24 November 2026) - 221 CFR 211.182, Equipment cleaning and use log, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- J/ section- 211. 182 (read 24 November 2026) - 321 CFR 211.68, Automatic, mechanical, and electronic equipment, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- D/ section- 211. 68 (read 24 November 2026) - 421 CFR 211.160, General requirements (laboratory controls), eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- I/ section- 211. 160 (read 24 November 2026) - 521 CFR 211.105, Equipment identification, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- F/ section- 211. 105 (read 24 November 2026) - 621 CFR 211.188, Batch production and control records, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- J/ section- 211. 188 (read 24 November 2026) - 721 CFR 211.65, Equipment construction, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- D/ section- 211. 65 (read 24 November 2026) - 821 CFR 211.192, Production record review, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- J/ section- 211. 192 (read 24 November 2026) - 921 CFR 211.180, General requirements (records and reports), eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- C/ part- 211/ subpart- J/ section- 211. 180 (read 24 November 2026) - 1021 CFR 11.10, Controls for closed systems, eCFR. https:/
/ www. ecfr. gov/ current/ title- 21/ chapter- I/ subchapter- A/ part- 11/ subpart- B/ section- 11. 10 (read 24 November 2026) - 11EudraLex Volume 4, Part I, Chapter 3: Premises and Equipment, paragraphs 3.41 and 3.44, European Commission, in operation since 1 March 2015. https:/
/ health. ec. europa. eu/ document/ download/ 18d76565- 137b- 41d2- a602- 794527f708c1_ en?filename=chapter_ 3. pdf (read 24 November 2026) - 12ICH Q7, Good Manufacturing Practice Guide for Active Pharmaceutical Ingredients, ICH, 10 November 2000, section 5.3. https:/
/ database. ich. org/ sites/ default/ files/ Q7%20Guideline. pdf (read 24 November 2026) - 13EudraLex Volume 4, Annex 11: Computerised Systems, revision 1, European Commission, in operation from 30 June 2011. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ annex11_ 01- 2011_ en_ 0. pdf (read 24 November 2026) - 14EudraLex Volume 4, Annex 15: Qualification and Validation, European Commission, in operation since 1 October 2015, section 4.1. https:/
/ health. ec. europa. eu/ system/ files/ 2016- 11/ 2015- 10_ annex15_ 0. pdf (read 24 November 2026) - 15Annex 11: Computerised Systems, draft for consultation, European Commission and PIC/S, July 2025, sections 6.6 and 7.5. https:/
/ health. ec. europa. eu/ document/ download/ 40231f18- e564- 4043- 94de- c031f813d38b_ en?filename=mp_ vol4_ chap4_ annex11_ consultation_ guideline_ en. pdf (read 24 November 2026) - 16Warning letter 320-26-36 to Winder Laboratories, LLC, MARCS-CMS 718601, FDA, 7 January 2026. https:/