Batch record review time, from your own lots.
Enter your lots, review hours and exception rate to see what review costs now and what a target you set would free, with a case for Word.
Your site and review baseline
Estimate for Site 1, Commercial Manufacturing
- Annual capacity freed
- 504 h/year0.26 FTE (at 1,920 h/FTE-year)
- Annual cost equivalent
- $47,880/yearAt your 40% target reduction
- Baseline review and rework
- 1,260 h/year7 h/lot average ($119,700/year)
| Step | Calculation | Estimate |
|---|---|---|
| Annual routine QA review | 180 lots × 6 h/lot | 1,080 h |
| Annual exception and rework | 180 lots × 25% × 4 h/lot | 180 h |
| Total baseline review and rework | 1,080 h + 180 h (7 h/lot average) | 1,260 h, or $119,700/year |
| Estimated capacity freed | 1,260 h × 40% target (÷ 1,920 h/FTE) | 504 h/year (0.26 FTE) |
| Annual cost equivalent freed | 504 h × 95 USD/h (2.8 h/lot freed) | $47,880/year |
| Remaining annual review time | 1,260 h − 504 h | 756 h/year |
What five companies measured on Seal
What each measured on its own process after adopting Seal. They are different measures: only Paradromics’ traveler review time is the review of a record. Set your own target; none is a promise of what your site will save.
| Company | Scope | Measured outcomes |
|---|---|---|
| Acclinate | QMS | Quality cycle times: −50%; Time taken to prepare for audits: −40%; Confidence in correct training: 100% |
| MiAlgae | eBR, QMS, ELN | Documentation time: −75%; Traceability: Instant lot genealogy; Scale: Lab to commercial on one platform |
| Skye Biologics | eBR, QMS | Increase in throughput: +35%; Non-conformances: −40%; Procedure review cycles: 2× faster |
| Bioventix | QMS, ELN | Document admin time: −80%; Audit readiness: Customer-approved; Data traceability: 100% |
| Paradromics | QMS, ELN, eBR, MES | Operator paperwork: −80%; Traveler review time for engineers: −90%; Process innovation time: −15% |
Where each number comes from.
Routine review is lots × hours per lot. Exception rework is the lots affected × the extra hours spent returning corrections, chasing signatures and closing deviations. The reduction is yours to set, and applies to both. FTE is hours ÷ 1,920, which is 48 weeks of 40 hours, before leave, training and meetings.
Whatever the time, the review stays. 21 CFR 211.192 has all production and control records “reviewed and approved by the quality control unit” before release, and in the EU a QP certifies the batch under EU GMP Annex 16.
Worked: one line, and what moves the answer.
Example, all invented: Line 4 releases 80 lots a year. QA timed 12 reviews, 9.5 hours on average; 28 of the 80 lots, 35%, came back with a correction that took 7 hours more; the blended rate is £62.
| Step | Calculation | Estimate |
|---|---|---|
| Annual routine QA review | 80 lots × 9.5 h/lot | 760 h |
| Annual exception and rework | 80 lots × 35% × 7 h/lot | 196 h |
| Total baseline review and rework | 760 h + 196 h (12 h/lot average) | 956 h, or £59,272/year |
| Estimated capacity freed | 956 h × 30% target (÷ 1,920 h/FTE) | 286.8 h/year (0.15 FTE) |
| Annual cost equivalent freed | 286.8 h × 62 GBP/h (3.6 h/lot freed) | £17,782/year |
| Remaining annual review time | 956 h − 286.8 h | 669.2 h/year |
The same line, one figure moved
| Case | Time now | Freed | Cost equivalent |
|---|---|---|---|
| As measured, 30% target | 956 h | 286.8 h, 0.15 FTE | £17,782 |
| Half the target, 15% | 956 h | 143.4 h, 0.07 FTE | £8,891 |
| Target 45% | 956 h | 430.2 h, 0.22 FTE | £26,672 |
| Review is 8 hours, not 9.5 | 836 h | 250.8 h, 0.13 FTE | £15,550 |
| Exceptions fall to 20% of lots | 872 h | 261.6 h, 0.14 FTE | £16,219 |
The target moves the answer most and is the only figure nobody can measure first. Present it as a range. At 30% the line frees under a sixth of one person, so the case rests on days off the release date as much as on cost.
How to get figures finance will accept.
| Figure | Measure it | Common fault |
|---|---|---|
| Review hours per lot | Time at least ten reviews of ordinary lots, hands on, excluding the wait | Counting the days a record sat in a tray |
| Exception rate | Lots returned at least once ÷ lots reviewed, over a full year | Counting corrections, so one bad lot counts five times |
| Rework per affected lot | QA and operations time from return to closed, from the deviation log | Leaving operations out |
| Hourly rate | Finance’s loaded rate for the people who do the work | Salary alone |
| Target reduction | What a pilot on one product showed | Another company’s figure |
Who uses the case, and for what.
| Decision | Who makes it | What holds it |
|---|---|---|
| Whether the saving is real | Finance, with the head of QA | Hours freed are cash only if a post, overtime or a contract goes. Otherwise they are capacity. |
| What review may narrow | QA | 21 CFR 211.22(a): the authority “to review production records to assure that no errors have occurred”, or that they were fully investigated. |
| What must still be investigated | QA | 211.192: any unexplained discrepancy is “thoroughly investigated, whether or not the batch has already been distributed”. |
| What the QP relies on | The QP | Annex 16, 1.7: the tasks may be delegated, but the QP needs “on-going assurance that this reliance is well founded”. |
Where the estimate stops.
Time on task, not time to release. A lot can need nine hours’ review and wait three weeks for it. The days are a separate measure, and often the bigger one.
One reduction for two kinds of work. Reading falls when a system checks entries as they are made; rework falls only if the errors do. If yours will move differently, run the estimator once for each.
No cost of getting there. Master records to convert, validation and training come off the first year. Paper to electronic batch records sets out that work, batch record review what a reviewer checks, and review by exception what can be narrowed and what can’t.
Sources.
- 21 CFR 211.192. Production record review and investigation.
- 21 CFR 211.22. Responsibilities of the quality control unit.
- EU GMP Annex 16 (2015). QP certification, and 1.7 on what may be delegated.
Each was read on 24 November 2026.
Where this runs in Seal.
- Batch release in Seal
Execution, QC results, deviations and CoAs brought into one release case for QA disposition and QP certification.
- Electronic batch records
Guided steps, instrument capture and exception flags so QA reviews exceptions instead of every handwritten line.
- Verified customer impact
Five life-science companies measured up to 80% less paperwork on Seal.
- Best MES and eBR software for GMP
How GMP batch record and execution systems compare on speed to first batch and review by exception.
Review the exceptions, not every line.
Bring one master batch record to a demo. We configure it with your checks so your team can see how review by exception runs on your own process.