What is a planned deviation, and should it go through change control instead?

A planned deviation is a one-off departure from an approved instruction, approved in writing by QA before the work and limited to a set scope such as one batch. It is recorded in the batch record and shown to whoever releases or certifies the batch. Anything repeated, lasting, or touching a specification, the marketing authorization or an approved application is a change: run it through change control, as a temporary change if it has an end date.Checked against its sources on 25 November 2026. How these answers are made

Illustration of a seal examining a circled change in a trace alongside run, sample and procedure records.

1Planned deviation or change control?

The label matters less than the route. FDA’s drug CGMP rules, 21 CFR Part 211, do not use the term.1 They require any deviation from written procedures or laboratory controls to be “recorded and justified”, and any change to them to be approved by the quality control unit.2,3 EU GMP wants planned changes evaluated and approved “prior to implementation”.4 A planned deviation must meet both.

A departure meant to cover several batches or a set period is a temporary change under change control: batches or end date fixed in advance, QA approval before the first, and at the end the evaluation EU GMP requires after any change, with the instruction restored or a permanent change raised.4,5 ECA Academy, a training body, warns: “Too many temporary changes indicate problems with process control and stability.”5

SituationRouteRule
Found during or afterA deviation, investigated where unexplained or critical211.192;6 ICH Q7 2.167
One-off, not registeredA planned deviation, approved in writing before the work, in production or the laboratory211.100(b) and 211.160(a);2,3 WHO 16.3;8 EU GMP 1.4(xii)4
Repeated or ongoingChange control, as a temporary change if it has an end dateEMA, of repeats after an unexpected deviation: “should be considered changes”;9 ICH Q10 3.2.310
Change to spec or planChange control: a new specification, method or sampling plan211.160(a): “including any change”3
Registered detailChange control, then the holder’s EU variation or US supplement or annual report, as requiredEMA Annex 16 Q&A 3;9 314.70(a)(1)(i);11 314.97;12 601.12(a)13
Medical devicesA “deviation permit”, given “prior to its realization”; afterwards, a concessionISO 9000:2015 3.12.5 and 3.12.6;14 820.3 and 820.715

1.1What to call it.

Regulators still use the term: EMA’s GMP Q&A and MHRA’s guidance for specials (unlicensed medicines) manufacturers both do.9,16 But ECA reports that “More and more regulators are now demanding that the nomenclature of a planned deviation is replaced”,5 and Pink Sheet reported FDA compliance experts at the 2018 PDA/FDA conference advising firms to call it a “temporary change control” or simply a “deviation” instead.17 Both are secondary reports. A suggested course: at the next SOP revision, name the pre-approved route a temporary change inside change control; until then, keep “planned deviation” for the one-off, unregistered row above.

2Planned deviation examples.

ExampleWhere it belongsWhy
Another packing lineOne batch on another line validated for the product: a planned deviation, if the line is not registeredEU GMP 4.19(h) and 4.21(g);18 211.105(b)19
Extra samplesExtra in-process samples for a study: a planned deviation from the sampling instructions211.160(a): record and justify3
Smaller batchesChange control: each batch size needs its own master record, and the application may fix the size211.186(a);20 314.70(a)(1)(i)11
New material supplierChange control, with the supplier approved firstICH Q7 7.14;7 EU GMP 5.2721
API form or step changedChange control with a risk and product impact assessmentFDA Form 483 below;22 ICH Q10 3.2.3(a)10
Use before releaseNot for drug product components; possible for APIs under defined systems211.84(a);23 EU GMP 5.34;21 ICH Q7 2.177

3Planned deviation template.

The Who column is a common split; your procedure sets it.

FieldWhoWhat to enterRequirement it serves
Number and scopeRequesterThe batch, equipment or period covered, and an end dateWHO 16.3: deviation “should be avoided as far as possible”8
InstructionRequesterDocument, version and step departed from, and what will be done instead211.100(b);2 EU GMP 4.20(h)18
ReasonRequesterWhy the instruction cannot be followed this time211.100(b): “justified”2
Registered detailsRegulatory affairsDoes it touch a specification, the MA, NDA, ANDA or BLA? If yes, stop: change control314.70;11 EMA Annex 16 Q&A 39
Risk assessmentProduction and QAEffect on quality and on the validated state of process and equipment, in proportion to the riskICH Q10 3.2.3(a);10 EU GMP 1.4(xii)4
Extra controlsProduction, QCAdditional sampling, inspection or tests that cover the departureWHO 9.14(f)8
Client approvalClient’s quality unitAt a CDMO, the client’s written approval, as the quality agreement requiresEU GMP 7.12;24 FDA quality agreements guidance25
ApprovalProduction head and QAA designated person, with QC involved where appropriate, in writing before the work startsWHO 16.3;8 EU GMP 1.4(xii)4
Batch recordProductionThe planned deviation number and signed authorization at the stepEU GMP 4.20(h) and 4.21(g)18
ReleaseQA; in the EU, the QPShown to whoever releases or certifies the batchAnnex 16, 1.7.15;26 WHO 9.14(e)8
OutcomeProduction, QCResults of the extra controls, the reconciliation, and any unplanned deviation raised211.192;6 EU GMP 4.21(h)18
Repeat checkQAEarlier planned deviations on the same instruction; if any, the change control or CAPA numberICH Q10 3.2.3;10 EMA Annex 16 Q&A 39

At a CDMO, put the client’s response time in the quality agreement, which FDA says should describe “how and when the owner and contract facility will communicate with each other”.25

4Example: a completed planned deviation.

This record is invented: the site, product, batch and numbers are illustrative.

Table 4. Example. A planned deviation record.
FieldEntry
Number and scopePD-⁠26-⁠014, Quillmere site. Narvexil 20 mg tablets, Batch 26-⁠117 only. Expires 15 November 2026.
InstructionPackaging instruction PI-⁠NRV-⁠20 version 7, step 4, names blister line P-⁠2. Batch 26-⁠117 will be packed on line P-⁠4.
ReasonP-⁠2’s forming station failed on 2 November (deviation DEV-⁠26-⁠0298); the part arrives on 20 November. Batch 26-⁠117 must pack on 5 November to meet a supply commitment.
Registered detailsPack size, blister materials and carton unchanged; neither line is named in the marketing authorization, so no variation (regulatory affairs, 3 November).
Risk assessmentP-⁠4 is qualified for this blister format; its sealing is validated for the same PVC/PVDC film and lidding foil (PV-⁠112). Risks: a missed defect or a weak seal at a new set-up.
Extra controlsAt start-up and at 2, 4 and 6 hours: a vision challenge with 10 defect cards and a leak test on 20 blisters. First 200 blisters checked by hand; final sample doubled.
ApprovalPackaging manager and QA, 3 November, before line set-up on 5 November
Batch recordPD-⁠26-⁠014 and its signed authorization entered at step 4; line P-⁠4 recorded as the equipment
ReleaseListed for the Qualified Person in the batch certification summary
Outcome4,000 cartons of 30 (three blisters of 10), 120,000 tablets, packed in 6 hours. All four challenges rejected 10 of 10 cards; all 80 leak-test blisters passed; no defect by hand or in the doubled sample. Closed 6 November.
ReconciliationBulk: 121,000 tablets issued; 120,000 packed, 800 destroyed in leak tests, 200 in rejected blisters. Printed cartons: 4,100 issued; 4,000 used, 62 destroyed at set-up, 38 returned.
Repeat checkNone on PI-⁠NRV-⁠20 step 4. Change control CC-⁠26-⁠0211, opened 3 November, assesses adding P-⁠4 to PI-⁠NRV-⁠20; any later batch on P-⁠4 goes through it.

Had P-⁠4’s sealing not been validated for these materials, the request would have gone straight to change control.

5Planned departures from a validation protocol.

WhenRouteRule
Before executionRevise the protocol; execution waits for approval by all appropriate departments, “including the quality unit”FDA PV guidance IV.C.427
During executionA departure under your procedure or the protocol’s provisions, justified and approved by the quality unit “before implementation”FDA PV guidance IV.C.4;27 211.1002
Significant changeEU: a change to acceptance criteria or operating parameters “should be documented as a deviation and be scientifically justified”Annex 15, 2.728
A PPQ batchRoutine procedures as written: they “must be followed during PPQ protocol execution”, with lots made “under normal conditions”FDA PV guidance IV.C.4;27 211.100(b) and 211.110(a)2,29
The reportShould “Summarize and discuss all manufacturing nonconformances”; later changes to acceptance criteria are justifiedFDA PV guidance IV.C.4;27 Annex 15, 2.928

If the process itself must change, change it first: FDA says “additional process design and process qualification activities could be warranted”.27

6How inspectors treat planned deviations.

A May 2026 Form 483 to an outsourcing facility cites a planned deviation used to switch an API’s form and drop a manufacturing step; three lots made under it were released:

“No formal risk assessment or product impact assessment documenting the potential effect of these changes on drug product quality, safety, identity, strength, or purity was performed prior to or in conjunction with the implementation of this deviation.” Sincerus Florida, LLC, Form FDA 483, Observation 6, 29 May 202622

A 483 records observations, not a final agency determination.22 Warning letters cite the same thing under other names:

“Your manufacturing personnel were observed to use a written work instruction (Pre-⁠Job Briefing) describing itself as ‘… not a GMP document/process…’ to deviate from your validated manufacturing procedure” Sanofi, warning letter 320-⁠25-⁠22, 15 January 202530

A device maker routed design changes through its deviation procedure, cited under the former 21 CFR 820.30(i), which the QMSR replaced on 2 February 2026:31,32

“However, multiple design changes were instead processed using Manufacturing Deviation, SOP025-⁠5.1, intended for temporary deviations from manufacturing procedures.” Micro-⁠X Ltd., warning letter, 10 September 202431

FDA faulted both firms’ responses for lacking a retrospective review.31,30

In the EU, a planned departure cannot use Annex 16 section 3, the route for certifying a batch after an unexpected deviation: EMA says “Planned deviations” are “outside the scope of the paragraph 3.1”.26,9

7How it runs in Seal.

In Seal a deviation and a change control are separate, linked records. Change control is configured by change type, including an authorized urgent-change path with recorded scope, limits and follow-up, so urgency does not become an unrecorded bypass. A change defines any temporary restriction with its expiry, the responsible role and the recovery route, and links the revision to every record it affects; the next run uses the released version.

The deviation workflow links each event to the batch, sample and procedure version behind it. Each immediate action keeps its scope, actor, time, reason and verification and, where it is temporary, its expiry.

AQuestions and answers

Does FDA require a planned deviation to be approved in advance?

Part 211 itself requires only that a deviation be recorded and justified. But procedures and specifications, and any change to them, need quality control unit approval, and FDA’s process validation guidance says departures from a PPQ protocol must be approved by the quality unit before implementation. So get QA approval before the work starts.

What is the difference between a planned and an unplanned deviation?

An unplanned deviation is found during or after the work and is investigated afterwards. A planned deviation is decided before the work and assessed and approved before it starts. The planned one needs the evaluation a change needs; the unplanned one needs an investigation proportionate to its risk.

Is a clinical protocol deviation the same as a planned deviation?

No. A protocol deviation departs from a clinical trial protocol, not a manufacturing instruction, and has its own rules. FDA’s December 2024 draft guidance says that in a drug or biologic trial an investigator who intends to depart from the protocol for a single participant should get the sponsor’s approval and must get the IRB’s approval first, unless there is an urgent need to eliminate an apparent immediate hazard. It adds that such deviations should be extremely rare, because sponsors should build appropriate flexibility into the protocol.

How many planned deviations are too many?

No rule sets a number. A request for a second planned deviation on the same instruction is the signal: the instruction no longer fits the work, so that request belongs in change control. Trend planned deviations with the rest in the product quality review, which EU GMP expects to cover all significant deviations, and treat a rising count on one line or product as a process problem to investigate.

Can a Qualified Person certify a batch made under a planned deviation?

Yes, if the batch still complies with GMP and the marketing authorization and the QP knows about the departure and its extra checks. What the QP cannot use is Annex 16’s provision for unexpected deviations, which EMA says excludes planned ones. If the departure touches the marketing authorization, the holder should apply for a variation where needed.

What should a planned deviation SOP cover?

Who may raise one, the limit on scope and duration, the check against specifications and registered details that sends a request to change control, the risk assessment, who approves before the work, what goes on the batch record, how the releasing person is told, how repeats are detected and, at a contract manufacturer, how the client approves.

References32 sources

References

  1. 121 CFR Part 211, Current Good Manufacturing Practice for Finished Pharmaceuticals, full text searched, eCFR, up to date as of 24 November 2026. https://www.ecfr.gov/current/title-21/chapter-I/subchapter-C/part-211 (read 25 November 2026)
  2. 221 CFR 211.100, Written procedures; deviations, eCFR. https://www.ecfr.gov/current/title-21/section-211.100 (read 25 November 2026)
  3. 321 CFR 211.160, General requirements, paragraph (a), eCFR. https://www.ecfr.gov/current/title-21/section-211.160 (read 25 November 2026)
  4. 4EudraLex Volume 4, Part I, Chapter 1: Pharmaceutical Quality System, European Commission, in operation since 31 January 2013, full text searched, sections 1.4(xii) and (xiii). https://health.ec.europa.eu/document/download/e458c423-f564-4171-b344-030a461c567f_en?filename=vol4-chap1_2013-01_en.pdf (read 25 November 2026)
  5. 5GMP and “Planned Deviations”: a Contradiction?, ECA Academy news, 26 August 2026, secondary source. https://www.gmp-compliance.org/gmp-news/gmp-and-planned-deviations-a-contradiction (read 25 November 2026)
  6. 621 CFR 211.192, Production record review, eCFR. https://www.ecfr.gov/current/title-21/section-211.192 (read 25 November 2026)
  7. 7ICH Q7, Good Manufacturing Practice Guide for Active Pharmaceutical Ingredients, ICH, 10 November 2000, sections 2.16, 2.17 and 7.14. https://database.ich.org/sites/default/files/Q7%20Guideline.pdf (read 25 November 2026)
  8. 8WHO good manufacturing practices for pharmaceutical products: main principles, WHO Technical Report Series No. 986, Annex 2, World Health Organization, 2014, full text searched, sections 9.14 and 16.3. https://cdn.who.int/media/docs/default-source/medicines/norms-and-standards/guidelines/inspections/trs986annex2.pdf (read 25 November 2026)
  9. 9Guidance on good manufacturing practice and good distribution practice: Questions and answers, EU GMP guide annexes: Annex 16, question 3, European Medicines Agency. https://www.ema.europa.eu/en/human-regulatory-overview/research-development/compliance-research-development/good-manufacturing-practice/guidance-good-manufacturing-practice-good-distribution-practice-questions-answers (read 25 November 2026)
  10. 10ICH Q10, Pharmaceutical Quality System, ICH, 4 June 2008, section 3.2.3. https://database.ich.org/sites/default/files/Q10%20Guideline.pdf (read 25 November 2026)
  11. 1121 CFR 314.70, Supplements and other changes to an approved NDA, paragraph (a)(1)(i), eCFR. https://www.ecfr.gov/current/title-21/section-314.70 (read 25 November 2026)
  12. 1221 CFR 314.97, Supplements and other changes to an approved ANDA, eCFR. https://www.ecfr.gov/current/title-21/section-314.97 (read 25 November 2026)
  13. 1321 CFR 601.12, Changes to an approved application, paragraph (a), eCFR. https://www.ecfr.gov/current/title-21/section-601.12 (read 25 November 2026)
  14. 14ISO 9000:2015, Quality management systems: Fundamentals and vocabulary, clauses 3.12.5 (concession) and 3.12.6 (deviation permit), ISO Online Browsing Platform, marked withdrawn. https://www.iso.org/obp/ui/#iso:std:iso:9000:ed-4:v1:en (read 25 November 2026)
  15. 1521 CFR 820.3, Definitions, and 820.7, Incorporation by reference, which names ISO 9000:2015 Clause 3, eCFR. https://www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-820 (read 25 November 2026)
  16. 16MHRA Guidance for Specials Manufacturers, Revision 2, January 2021, section 3.1.3, MHRA, GOV.UK. https://assets.publishing.service.gov.uk/media/603526f28fa8f54330a8e25f/QA_Version_3_-_Aseptic_manip_updates.pdf (read 25 November 2026)
  17. 17FDA Compliance Experts Advise Against Treating Minor Changes As ‘Planned Deviations’, Bowman Cox, Pink Sheet, Citeline, 5 October 2018, key points, secondary source. https://insights.citeline.com/PS124020/FDA-Compliance-Experts-Advise-Against-Treating-Minor-Changes-As-Planned-Deviations/link-JDZRCNKOIBGDTGBXDETPYZMEIM (read 25 November 2026)
  18. 18EudraLex Volume 4, Part I, Chapter 4: Documentation, European Commission, in operation since 30 June 2011, sections 4.19 to 4.21, including 4.21(h). https://health.ec.europa.eu/document/download/104b3eb8-81a7-4858-9419-cb06562adb66_en?filename=chapter4_01-2011_en.pdf (read 25 November 2026)
  19. 1921 CFR 211.105, Equipment identification, paragraph (b), eCFR. https://www.ecfr.gov/current/title-21/section-211.105 (read 25 November 2026)
  20. 2021 CFR 211.186, Master production and control records, paragraph (a), eCFR. https://www.ecfr.gov/current/title-21/section-211.186 (read 25 November 2026)
  21. 21EudraLex Volume 4, Part I, Chapter 5: Production, European Commission, in operation since 1 March 2015, sections 5.27 and 5.34. https://health.ec.europa.eu/document/download/4a1fdb4f-6f6f-49c4-b264-8056e5bbe078_en?filename=chapter_5.pdf (read 25 November 2026)
  22. 22Sincerus Florida, LLC dba SKNV, Form FDA 483, outsourcing facility, inspection 18 to 29 May 2026, issued 29 May 2026, Observation 6, item 2, FDA. https://www.fda.gov/media/193727/download (read 25 November 2026)
  23. 2321 CFR 211.84, Testing and approval or rejection of components, drug product containers, and closures, paragraph (a), eCFR. https://www.ecfr.gov/current/title-21/section-211.84 (read 25 November 2026)
  24. 24EudraLex Volume 4, Part I, Chapter 7: Outsourced Activities, European Commission, in operation since 31 January 2013, section 7.12. https://health.ec.europa.eu/document/download/58b5106a-cf6f-4352-9dca-1caf5d27d97e_en?filename=vol4-chap7_2012-06_en.pdf (read 25 November 2026)
  25. 25Contract Manufacturing Arrangements for Drugs: Quality Agreements, guidance for industry, FDA, November 2016, sections IV.B.1 and IV.B.2. https://www.fda.gov/media/86193/download (read 25 November 2026)
  26. 26EudraLex Volume 4, Annex 16: Certification by a Qualified Person and Batch Release, European Commission, 12 October 2015, in operation since 15 April 2016, sections 1.7.15 and 3. https://health.ec.europa.eu/system/files/2016-11/v4_an16_201510_en_0.pdf (read 25 November 2026)
  27. 27Process Validation: General Principles and Practices, guidance for industry, Revision 1, FDA, January 2011, sections IV.C.4 and IV.D. https://www.fda.gov/media/71021/download (read 25 November 2026)
  28. 28EudraLex Volume 4, Annex 15: Qualification and Validation, European Commission, 30 March 2015, in operation since 1 October 2015, sections 2.7 and 2.9. https://health.ec.europa.eu/system/files/2016-11/2015-10_annex15_0.pdf (read 25 November 2026)
  29. 2921 CFR 211.110, Sampling and testing of in-process materials and drug products, paragraph (a), eCFR. https://www.ecfr.gov/current/title-21/section-211.110 (read 25 November 2026)
  30. 30Sanofi (Genzyme Corporation, Framingham), warning letter 320-⁠25-⁠22, MARCS-⁠CMS 690604, FDA, 15 January 2025, amended, item 2. https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/sanofi-690604-01152025 (read 25 November 2026)
  31. 31Micro-⁠X Ltd., warning letter, MARCS-⁠CMS 692084, FDA, 10 September 2024, item 1, 21 CFR 820.30(i). https://www.fda.gov/inspections-compliance-enforcement-and-criminal-investigations/warning-letters/micro-x-ltd-692084-09102024 (read 25 November 2026)
  32. 32Medical Devices; Quality System Regulation Amendments, final rule, 89 FR 7496, Federal Register, 2 February 2024, effective 2 February 2026. https://www.federalregister.gov/documents/2024/02/02/2024-01709/medical-devices-quality-system-regulation-amendments (read 25 November 2026)